This is a Statement of Work (SOW) for the Roofing Repair, Replacement Follow-on (R3F) program, issued by the Air Force Installation and Mission Support Center (AFIMSC) in April 2026. The SOW establishes requirements for commercial roof replacement and corrective repair services across Department of the Air Force installations, with optional use for Air Force Guard and Reserve, U.S. Army Active/Guard/Reserve, and U.S. Navy Active/Guard/Reserve facilities within the Continental United States and Alaska. Services will be acquired on a recurring basis for DAF facilities and on an as-needed basis for other agencies.
The scope encompasses repair and replacement of low-slope weatherproof membrane roofing systems (slopes ≤3:12), steep-slope water-shedding roof coverings (slopes >3:12), and metal roofing systems, including all thermal insulation, vapor retarders, membranes, drainage components, flashings, and related details. Work includes roof-mounted appurtenances and incidental construction activities such as asbestos abatement, HVAC modifications, and lightning protection, with incidental work capped at 30 percent of direct roofing costs. All roof types listed in UFC 3-110-03 are included; unlisted types require AFCEC Roofing Subject Matter Expert approval. Specific projects will be awarded as task orders under a design-bid-build or design-build delivery method, with task orders ≤$250,000 first offered to 8(a) awardees (if two or more are available in the region) and orders >$250,000 open to all regional awardees or set aside for small business competition. Contractors must maintain key personnel including a Project Manager (available within one hour of notification during business hours), a Contractor's Project Superintendent with minimum five years' roofing construction experience (two years as superintendent), and a Contractor's Quality Control Manager responsible for daily site inspections, material compliance verification, and submittal coordination.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Roofing Repair, Replacement Follow-on (R3F) Statement of Work
Air Force Installation and Mission Support Center (AFIMSC) / Air Force Installation Contracting Center (AFICC) / Air Force Civil Engineering Center (AFCEC)
April 2026
| Version |
| Date |
| Author |
| Changes |
| 1.0 |
| 25 Sep 2024 |
| 772 ESS Team |
| Requirement owner updates and validation |
| 2.0 |
| 26 Mar 2025 |
| 772 ESS Team |
| Requirement owner updates and validation |
| 3.0 |
| 09 Apr 2026 |
| AFICC/AQB |
| Requirement Owner Updates for Source Selection |
Table of Contents
| ROOFING STATEMENT OF WORK (SOW) | 2 |
| Purpose | 2 |
| Scope | 2 |
| Specific Base Construction Projects – Awarded as Task Orders (TO (s)) | 3 |
| Contractor Requirements – Management Capacity/Capability | 4 |
| Contractor Requirements – Self Performance Capability | 6 |
| Contractor Requirements – Subcontract Management | 7 |
| Applicable Documents | 7 |
| Government Furnished Information, Equipment, and Property (GFI,GFE, GFP) | 8 |
| Provisions on Contracting Officer’s Authority | 8 |
| Worksite Activities and Coordination | 8 |
ROOFING STATEMENT OF WORK (SOW)
1.0 Purpose
The purpose of this program is to acquire commercial roof replacement, and corrective repair for Department of the Air Force (DAF); with optional use (non-mandatory) for DAF ‘Guard and Reserve, U.S. Army (USA) and U.S. Navy (USN) Active, Guard and Reserve installations within the Continental United States (CONUS) and Alaska (only areas reachable by ground transportation). The program will acquire such services for existing DAF facilities on a recurring basis. The program may acquire such services for USA, USN, and other agencies on an as-requested basis.
2.0 Scope
2.1 The scope of this effort is to perform roof repair and replacement (thermal and moisture protection) for low-slope (weatherproof membrane types of roof systems installed on slopes at or less than 3:12 or 14 degrees), steep slope (water-shedding types of roof coverings installed on slopes greater than 3:12 or 14 degrees), and metal (hydrostatic and hydrokinetic systems) roofing projects. Roof assemblies include all items of work included in the elemental classification of the American Society for Testing and Materials (ASTM) UNIFORMAT II B30. The thermal insulation, vapor retarder, membrane, drainage components, flashings, and details (roof edges, scuppers, parapets, curbs, drains, coping systems, shingles and roofing tiles, etc.) are included in the scope of this effort. The features of work that are part of the structural roof assembly (framing (steel, wood, etc.), structural diaphragm, decking, purlins, parapets, roof joists, beams, associated hardware and fixtures, etc.) regardless of material are in scope of this project. While inspections are included in the scope of this effort, the specific assessment techniques, e.g. thermal imaging or Unmanned Aerial System (UAS)/drone usage, to include the decision/approvals to use these techniques, will be made at the base/task order level in accordance with (IAW) relevant Air Force guidance.
2.2 The scope of this effort also includes the installation, and replacement of roof-mounted appurtenances in accordance with DoD and Air Force criteria.
2.3 The ASTM UNIFORMAT IIB30 features of work incidental (in terms of dollar amount related to the direct roofing cost (labor, equipment, materials and subcontractor mark- up)) construction activities such as asbestos abatement, HVAC disconnect/movement, plaza decks, lightning protection, and walking pads, etc. which arise as a result of the roofing project are in scope of this contract. The estimated value of this incidental work should not exceed 30% of the direct roofing costs.
2.4 All roof types, systems, materials, membranes, and services listed in UFC 3-110-03 are included. Roof types not listed must be approved by AFCEC Roofing SME.
2.5 The Government may elect to replace a roof with a different in-scope roof type (for example: Asphalt Built-Up Roof to Metal (Hydrostatic) Membrane, etc.).
2.6 The project delivery methods shall include design-bid-build and/or design-build.
3.0 Specific Base Construction Projects – Awarded as Task Orders (TO (s))
3.1 Specific roofing construction projects will be awarded at the task order level against the basic IDIQ contract on an “as needed” basis. Civil Engineering (CE) and contracting personnel will prepare design-build, design-bid-build, specifications, and related requirements documents for specific roofing projects and will solicit only those Contractors awarded IDIQ contracts in the geographic region in which the base is located.
3.2 Each requiring activity, when furnishing their individual requirements for TO competition, may include base-specific terms and conditions as well as master specifications.
3.3 TOs < or = $250K will first consider set-aside for competition among 8(a) awardees only (if the region has two or more 8(a) firms). All orders over $250K will be open for competition amongst all awardees in the regional awardee pool; or may be set-aside for further competition if there are two or more small businesses representing as the same socio-economic concern in the geographic region where the work will be performed.
3.4 The Contractor shall notify the Government in writing of any conflicts between the proposed roofing system, the design documents, and the scheduling of work/workers (trades) to assure a watertight roofing installation. All the conflict decisions shall be obtained in writing from the Government prior to the start of roofing work.
4.0 Contractor Requirements – Key Personnel and Management Capacity/Capability
4.1 The Contractor shall be required to furnish all materials, equipment, and personnel necessary to manage, and accomplish the orders issued under the contract. Throughout the life of this contract, whenever there are active TO’s (i.e., work is actively underway on-site), the Contractor shall have a project manager available during normal business hours to meet with the Contracting Officer or his/her representative at a location specified in the TO within one hour after notification. The Contractor shall also accomplish quality control management for all active projects.
4.2 Whenever there are awarded active TO’s, Contractor personnel with the following management/technical support capabilities must be available to properly manage/superintend all TO work under construction:
4.3 Contractor's Project Superintendent (CPS) - Provides on-site supervision of active TO's. The CPS shall visit each active project site daily, submit detailed progress reports (AF Form 3065) as required by each TO, schedule and coordinate subcontractors and material suppliers, and attend all weekly status meetings, site visit, and pre-final/final inspections. Superintendents shall have a minimum of five years' combined experience within the last 10 years in roofing construction with at least two of those years as a Superintendent of similar size and complexity.
4.4 Contractor's Quality Control Manager (QCM) - Provide quality control management for all active TO's and execute the Contractor’s QC plan. The QCM shall visit each active project site daily to ensure full compliance with all safety requirements and verify that the materials and workmanship are in accordance with approved construction drawings, shop drawings, material submittals and technical specifications. The QCM shall prepare and coordinate material submittal sheets and shop drawing submittals, prepare QC reports, schedule and coordinate testing procedures and attend all weekly status meetings, site visits, and pre-final/final inspections. The QCM shall be someone other than the CPS except in TOs which are small (<$150K) in which case the CPS may, also, serve as the QCM. QCM shall have a minimum of five years’ experience within the last 10 years in Quality Control in commercial roofing. The individual shall have at least two years of experience as a QCM and be familiar with the requirements of UFGS 01 45 00, para. 1.6.2.2, EM 385-1-1.
4.5 Contractor’s Project Manager - Must be specialized contractors, required to be manufacturer-approved, authorized, or licensed in writing to install specific roofing systems. The PM must demonstrate a minimum of five years combined experience in the last 10 years. The individual must have a minimum of five years of experience with the manufacturer certification to ensure they can provide the specified warranty. Two years must be specifically as a project manager. They are required to abide by UFGS requirements for all roofing systems.
4.6 The Contractor shall employ (or subcontract) a CPS and/or QCM and/or job foreman for each active TO who is a certified installer of a qualified manufacturer for all roofing systems being installed. The CPS and/or QCM and/or job foreman is required on site at all times (100% of the time) when roofing work is being accomplished.
4.7 The Contractor shall be capable of performing on all roof types within the entire region. Performance of roofing work must be accomplished by a firm (prime/sub/teaming partner) which holds a current applicator agreement for the product(s) they are installing through contract TO performance. The Contractor shall comply with the Period of Performance (PoP) established in the TOs. After notification, the Contractor must be capable of responding to emergency situations as stated in the TO and complete the emergency work by the end of the PoP. The Contractor must be capable of participating in TO level site-visits at all locations in the geographic region. Site visit procedures will be established at the task order level.
4.8 The Contractor must provide accurate progress payment estimates, accommodate a potential number of concurrent “active” projects at different bases or states, provide flexibility of staff and subcontractor pool to handle surges in work volume, meet the Government schedule, mobilizing equipment necessary to complete work in a timely and cost effective manner, provide on-time completion process submittals in a timely manner, and present a professional demeanor.
4.9 The Contractor shall participate in an annual Program Management Review (PMR) meeting with the DAF Roofing Program Team (Program Manager, Contracting Officer, etc.) and other stakeholders (Air Force Civil Engineering Center, Base Civil Engineers, etc.). This meeting may be accomplished virtually, via teleconference or by other electronic means. The purpose of the PMR will be to discuss Contractor performance, quality, competitiveness, and/or any other topic the Government or Contractor deem necessary to reduce costs, increase quality, or resolve issues.
4.10 The Contractor must provide to the DAF Contracting Officer an annual PMR report, in the format provided by the Government. The report must be submitted to the Government no later than 90 calendar days prior to the end of the ordering period and contain the following information:
4.11 Bonding Capacity: In whole dollars, provide the aggregate bonding capacity and unreleased bonding at the end of the reporting period. Also describe any increase in bonding capacity received during the reporting period.
4.12 Self-Performance: For all DAF projects conducted during the reporting period, list the TO number, the total cost of the materials, the total subcontractor cost and the total price TO amount.
4.13 Warranty Work: Identify by TO project number the date contacted by the Government for the warranty call and the nature of the warranty call. Describe the corrective action taken or planned if the issue was in- warranty, or explanatory comments if the issue was out of warranty.
4.13.1 Warranty Work Plan. Contractor shall provide a warranty plan that includes: manufacturer’s warranty, response time, personnel assigned, and coordination with subcontractor.
4.13.1.1 Warranty Response Time. The required response time for routine calls shall be within two weeks and emergency calls within 72 hours, IAW the UFGS.
4.14 The Contractor must be capable of collecting, maintaining, and reporting this data to the Government for discussion at the annual PMR meetings as specified.
4.15 Throughout the period of performance the Contractor may be asked to provide to the Contracting Officer, upon 10 business days’ notice, various additional data related to performance, quality, schedule, or other related contract elements.
4.16 The project roofing work warranty will be in accordance with FAR 46.710, Warranties And DFARS 246.7, Warranties referenced in the Department of Defense Warranty Guide dated 30 October 2020 which all work performed under this contract shall conform to the contract requirements and be free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subfactor or supplier at any tier for a period of one year from the date of Government acceptance of the work.” In addition, the Contractor must be able to provide the warranty types as defined in appendix D of UFC 3- 110-03. Typical included requirements are: has “no dollar limit”, covers full system water- tightness, is from the single source manufacturer, and has minimum duration of 20 years.
4.17 The Offeror shall provide a single customer service hotline phone number that can be accessed during normal business hours, on all bases in the geographic region of the proposal, to be responsive to Government requests. The Offeror must describe how its customer service function is managed to ensure responsiveness. The Offeror must also log all calls received from AF installations and must identify the Offeror’s process for resolving AF installation concerns and following up on unresolved requests.
5.0 Contractor Requirements – Self Performance Capability
5.1 The Contractor must be capable of self-performing in accordance with 52.219-14 -- Limitations on Subcontracting (DEVIATION 2019-O0003).
5.2 The Contractor must maintain a safety plan that, at a minimum, demonstrates the employment of standard safety processes, Occupational Safety and Health Administration (OSHA) compliance, training, and inspection for all employees and subcontractors. The Contractor may be required to produce the Safety Plan for review at any time by the Government.
5.3 The Contractor must provide and maintain manufacturer applicator agreements demonstrating the capability of providing the warranties described in the Unified Facilities Criteria (UFC).
5.4 The Contractor must have 5 years of corporate experience performing, managing and subcontracting roofing and projects. The Contractor shall have recent experience (within 5 years) installing the roofing systems in the region in which they will perform work.
5.5 The Contractor shall have a roof system design capability in accordance with the design guidance in UFC 3-110-03 Roofing. The Contractor will have the capability to do roof systems design as demonstrated by including in their organization (may be a subcontractor) a Registered Roofing Consultant, Registered Professional Engineer or Registered Architect that derives his or her principal income from roofing design. A qualified architect or engineer shall design and oversee the preparation of contract documents. At the TO level, the Contractor shall have recent experience (within 5 years) designing the roofing systems in the ASHRAE climate zone of the region in which they will perform work. The Whole Building Design Guide (WBDG) Unified Facilities Guide Specifications (UFGS) and UFCs shall serve as the basis for all project specifications that the Contractor shall develop on design-build TO.
6.0 Contractor Requirements – Subcontract Management
6.1 The Contractor shall have established subcontractor relationships, have a subcontractor pre-qualification process, and maintain documentation of pre-qualification for the subcontractors used.
6.2 This pre-qualification process must consider the prospective subcontractors’ safety plans, quality control plans, financial capability, insurability, past performance, and applicator agreements, and must identify the minimum requirements the subcontractor must meet in each area to be determined acceptable.
6.3 The Contractor must maintain established criteria for determining the acceptability of the subcontractor areas described in 8.1.1.
6.4 This documentation may be requested by the Government, and the Contractor must provide within 10 business days.
6.5 The Contractor is responsible for managing subcontractor performance. The Contractor shall be directly responsible to the Government for all work allocated to its subcontractors. The Contractor must maintain metrics it will track on subcontractor performance, must monitor those metrics, and hold subcontractors accountable.
7.0 Applicable Documents
7.1 The Contractor shall comply with all applicable federal, state, and local statutes; Department of Defense Instructions, Air Force Instructions, manuals, handbooks, regulations, guidance, and policy letters, including but not limited to:
· Unified Facility Criteria (UFC) 1-200-01, DoD Building Code which brings uniformity to the military use of non-government model building codes such as the International Building Code (IBC) and the International Existing Building Code (IEBC)
· UFC 1-200-02, High Performance and Sustainable Building Requirements
· UFC 3-110-03, Roofing
· AFI 32-1001, Civil Engineer Operations or current AF policy
· DAFMAN 91-203, Air Force Consolidated Occupational Safety, Fire, and Health Standards
· National Fire Protection Association (NFPA)
· American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)
· Metal Building Manufacturers Association (MBMA)
· American Society of Civil Engineers (ASCE)
· ASTM International (formerly American Society for Testing and Materials)
· National Electrical Code (NEC)
· National Roofing Contractors Association (NRCA) Roofing Manuals to include all changes and amendments in effect on the date of issuance of each TO.
7.2 The Contractor must comply with guidance in each state issued by the State Historical Preservation Office (SHPO).
7.3 It is the Contractor’s responsibility to comply with all applicable requirements which will be called out in the TOs. Base-specific requirements will be identified in each TO. The Contractor shall obtain and maintain access to all these documents during the term of this contract.
8.0 Government Furnished Information, Equipment, and Property (GFI, GFE, GFP)
GFI, GFE, and GFP, if provided, will be specified in each TO.
9.0 Provisions on Contracting Officer’s Authority
9.1 No person other than the Air Force Installation Contracting Center (AFICC) Contracting Officer shall have authority to modify the terms and conditions of the IDIQ contract. For specific base level roofing projects awarded on TOs against the IDIQ, the ordering contracting officer specified on that TO is the only person with the authority to modify the terms of that TO. The Contractor shall not take direction from anyone other than the Contracting Officer. In the event the Contractor effects any such changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority, and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof. The Contracting Officer is the only person who can obligate the government; other input taken and acted upon that change the contract (other than health/life safety concerns) in any way is done at the sole financial and legal responsibility of the Contractor.
10.0 Worksite Activities and Coordination
10.1 The Contractor shall coordinate worksite activities with all applicable Government personnel (applicable personnel will be called out in the TO) to ensure the protection of human health and the environment; the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of Government work interruptions. The Contractor shall provide physical security to work areas with security equipment and personnel, as required by the TO. The Contractor shall cooperate with other contractor personnel working in the area. The Contractor must comply with OSHA safety and health regulations and local safety office requirements. The Contractor is required to provide the ordering Contracting Officer copies of any OSHA report(s) submitted during the duration of the TO. For areas not covered by OSHA, the Contractor shall comply with regulations regarding safety and health and the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM385-1-1, (https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_38 5-1-1.pdf)
10.2 The Contractor shall perform work as specified at project locations. The Contractor shall be responsible for all personnel, security, supplies, equipment, and infrastructure (including, but not limited to, potable water, utility systems, sanitation, housing, dining, transportation, and medical care) when there are no facilities and services indicated as available to the Contractor in the TO.