Construction Services for Repair USAFA Cadet Chapel, United States Air Force Academy, CO
Solicitation No.
FA8903-17-R-0071
Pre-Solicitation Site Visit
Air Force Civil Engineer Center Battle Ready … Built Right!
Agenda
MEGAN ROBARE
AFCEC/CFSC
SALLY KITE
772 ESS PKA
ELIZABETH GRIFFITH
AFCEC/CFTP, Contractor
WELCOME OVERVIEW
CONTRACTING
TECHNICAL
SUPPORT
Welcome/Opening Remarks Contractor Sign-in Introductions: Project Team
Closing Remarks Site Walk Solicitation Summary 2-Step Evaluation Process Rules of Engagement Anticipated Milestones Project Synopsis Cadet Chapel History and Performance Current Construction Effort Scope Project Goals
Rules of Engagement
Purpose of the project
The Air Force Academy Cadet Chapel carries profound meaning to the Air Force Academy, the Air Force, and the American people.
The chapel serves an inspiring place of worship for the faculty, cadets, alumni, and guests.
This important landmark continues to be one of the most visited landmarks in the state of Colorado, representing the Air Force, the Academy, and the distinctive architectural heritage of the academy campus.
The chapel is widely renowned as a celebrated example of mid-century modern architecture, justifying a place on any list of architectural treasures, earning it’s place as a National Historic Landmark.
We are here today not to alter the visit of the architect Walter Netch, but to repair damage and protect this building for future generations of Cadets and Americans.
We have set aside time today for a guided tour of the chapel, but be aware that the chapel is accessible during public visitation hours, and further site visit is welcomed.
Project Team Procuring Contracting Officer (PCO):
Ms. Sally Kite, 772 ESS/PKA
Contract Specialist:
Mr. Matthew Robey, 772 ESS/PKA
Contracting Officer Representative (COR):
Ms. Megan Robare, AFCEC/CFSC
Technical Support:
Ms. Elizabeth Griffith, AFCEC/CFTP Contractor
AFCEC/CFSC
SALLY KITE
772 ESS PKA
TECHNICAL
SUPPORT
Solicitation Summary 2-Step Evaluation Process Rules of Engagement Anticipated Milestones Project Synopsis Cadet Chapel History and Performance Current Construction Effort Scope Project Goals Welcome/Opening Remarks
Solicitation Summary Full and Open solicitation
Magnitude of Construction Project – The estimated price range for this Design-Bid-Build (DBB) construction project is between $25,000,000 and $100,000,000
Bid Guarantee – Requires 20% of contract price or $3,000,000 (whichever is less).
Performance and Payment Bonds (Construction/Insurance Certificates) – Contractor will not commence performance until Performance/Payment Bonds (100%) have been received by the Government and all work plans have been approved by the PCO
Anticipated Period of Performance is 48 months from date of award including final cleanup of the premises
2-Step Evaluation Process Step 1 is a prequalification of sources in accordance with DFARS 236.272 Project design documentation (drawings and specifications) are draft until Step 2 but representative of project scope Evaluation based on technical qualifications and past performance Price will not be evaluated in Step 1 Up to 5 most highly qualified Step 1 offerors will receive an amendment to compete for contract award in Step 2 Step 1 offerors will receive a pre-award debriefing (if requested) at conclusion of prequalification decision; no further debriefing opportunities will be offered to the Step 1 offerors Step 2 is a formal Request for Proposal (RFP) in accordance with DOD Source Selection Procedures Final design documentation will be released in the Step 2 amendment Most highly qualified offerors will submit technical, small business participation commitment, and pricing proposal in Step 2 Will utilize subjective tradeoff to determine best value in accordance with solicitation criteria
Draft Solicitation Documents Released 21 JUL 17
Offerors are cautioned– ALL questions are to be submitted in writing to the PCO
Contractors to submit all questions in writing to the PCO at sally.kite@us.af.mil and Contracting Specialist at matthew.robey.3@us.af.mil no later than 21 AUG 17
Submit questions to the Draft Solicitation Documents on the Q&A Spreadsheet Attachment (available on www.fbo.gov)
Ensure questions are specific and include reference to documents when at all possible and applicable
Contractors MUST FILL IN ALL SPACES OF THE SPREADSHEET
No Technical Questions will be answered during the site visit
The Chapel is open to the public during regular visiting hours
All contractor’s questions and Government’s responses will be posted on www.fbo.gov
These slides will be posted on www.fbo.gov
Site visit sign in sheet will be made available on www.fbo.gov
For conflict with any information provided during this site visit, versus any information released with the Draft Solicitation Documents, the Draft Solicitation Documents are the binding authority
Design documents released in the Draft Solicitation Documents, including specifications and drawings, will not be finalized until the release of Step 2 Request for Proposal (RFP)
Anticipated Milestones
Draft Solicitation Questions Due: 21 AUG 17
Government Responses: 1 SEP 17
Step 1, Release of RFP (Prequalification): 18 OCT 17
Step 1, Proposals Due: 20 NOV 17
Step 1, Prequalification Decision: 26 JAN 18
Step 2, Release of Amendment: 23 MAR 18
Step 2, Proposals Due: 29 MAY 18
Award: 9 JAN 19
AFCEC/CFSC
SALLY KITE
772 ESS PKA
TECHNICAL
SUPPORT
Welcome/Opening Remarks
Closing Remarks
Solicitation Summary 2-Step Evaluation Process Rules of Engagement Anticipated Milestones Project Synopsis Performance History Current Construction Effort Scope
Chapel Layout Protestant Level Terrace Level (Catholic, Jewish, Buddhist)
Basement Level (Muslim, Choir Practice, Mechanical Rooms)
The unique structure of the chapel is worthy of commentary prior to discussing the technical requirements for this construction project.
This three story building contains three separate levels of worship. The top floor, referred to as the protestant level, contains the protestant chapel, and a protestant level balcony for choir and organ. The exterior of this level is enclosed independently from the bottom two floors, with 14 aluminum clad spires.
The terrace level beneath the protestant level contains the catholic, jewish, and Buddhist chapel areas. The catholic chapel also contains a balcony for the choir and organ.
Finally the basement level contains a muslim chapel and other support rooms, including a larger mechanical room and choir practice room.
While the protestant level is clad in aluminum and glass with a structural steel lateral and gravity support system, the floors below are structurally supported by concrete framing and concrete walls. Removal of the aluminum clad enclosure at the protestant level does not open the catholic or chapel areas to the exterior.
Design Modifications
The roof of the chapel began leaking almost immediately upon completion of the original construction. The Academy performed a multitude of design retrofits and repairs to the 1959 design, in attempts to arrest and prevent leaking. Numerous modifications were made beginning as early as 1963, including the addition of storm windows, gutters, and numerous reapplication of sealants. None of these surface level changes have arrested the leaking.
Current Design Effort
In 2015, the Air Force programmed a project to design a comprehensive retrofit of the chapel cladding to repair, retrofit, or rebuild the exterior to the extent necessary to stop the leaking. AFCEC and AFICA
The design team is led by AECOM, selected for their longstanding history of design for the Academy campus and for their extensive expertise in Air Force and DoD design and construction requirements. AECOM was joined by teaming partners Wiss Janey Elstner and Hartman Cox Architects.
AECOM teamed with Wiss Janey Elstner, a firm of engineers, architects and material scientists who work on solving building problems in the built-world, specializing in the retrofit and repair of building envelopes. WJE participated as architectural and structural engineers on this project, designing the entire envelope repair solution.
AECOM teamed with Hartman Cox Architects is a renowned Washington D.C.-based architectural firm, experienced with complex institutional projects with an expertise in managements of renovation requirements of historic buildings. Hartman Cox participated as the Historical Preservation Architect for this project.
Construction Scope
Enhance Fire and Anti-Terrorism Protection
Install Weather Resistant Panels Replace Exterior Cladding and Trim Replace Side and End Wall Glazing Restore Dalles de Verre Replace Lighting and Lath/Plaster
Repair by Replacement Elements of Facility Envelope
The primary construction scope of this project is to repair by replacement the protestant level building envelope. Options utilizing the original panels were evaluated in this design process, but were eliminated early in the design process to do challenges that were insurmountable by both cost and complexity.
Construction Scope
Restore Protestant and Catholic Organs Restore Protestant Chapel Pews Modify Electrical Systems Restore/Replace some Doors/Hardware Enhance Fire Protection
Install Fire Alarm and Mass Notification
Other Project Scope
In addition to the primary scope of replacing the walls in the protestant chapel, other more minor scope areas are included in this project.
Building Protection Ref. 3/G-310
South Entrance Protestant Choir Loft Protestant Organ Support Structure Exterior Interior
Extents of building protection to be designed and constructed by Contractor
The protestant level of the chapel will be exposed following the removal of the exterior envelope and the existing facility must be protected in its entirety prior to demolition. The contract drawings illustrate the concept of protection anticipated by the Government, but ultimately the Contractor will be required to design and install weatherproof protection for the structurally designed as indicated in the contract. Temporary HVAC, humidity control, and egress will be included in this temporary protection design.
Exterior Envelope – Side Walls
Ref. 3/A-502
SIDEWALLS –
The scope of the exterior renovation impacts all of the envelope at the protestant level chapel and above; none of the Catholic level envelope will be modified in this project other than minor door renovation. All of the existing aluminum panels and interiors will be removed from the Protestant chapel.
Asbestos-Containing Materials Abatement
LEGEND
INDICATES INTERIOR SPACES KNOWN TO CONTAIN ASBESTOS CONTAINING MATERIALS (ACM). SEE ABATEMENT NOTES.
Ref. HA-201
Removal of the side walls will necessitate abatement of hazardous materials encountered there. The grey shaded areas indicate where the hazardous materials assessment indicates that asbestos will be encountered, and assumed quantities are included in the design.
Dalles de Verre
Ref. 1/AI-313
The dalles de verre colored block glazing require careful treatment and protection during this project, and are the only visual element to be retained in the side walls. This glazing was fabricated in cassettes of 9 blocks. Approximately 1% of the blocks within the cassettes require replacement with blocks matching the original colors. All cassettes will be cataloged, labeled, and removed for storage during the renovation. The contract drawings indicate which blocks are known to require replacement or repair, and the treatment required. All of the cassettes will require restoration to clean and remove excess sealant.
Side Wall Glazing
Ref. 2/A-522
Ref. 1/A-526 Strip Windows Side Windows
Unlike the specialty preservation work required for the dalles de verre, the side wall vision glazing will be replaced in its entirety. Two glazing systems exist, the side windows in a triangular shape between lower tetrahedrons and strip windows which cover the exterior face of the dalles de verre. All new glazing will be laminated for blast resistance.
Cladding Panels and Trim and Weather-Resistant Panel
Ref. 3/A-502
Ref. 1/A-502
CLADDING PANELS AND TRIM and WEATHER – RESISTANT PANEL:
Returning back to the view of the cross section of the middle tetrahedron and focusing on a single detail connection, the new elements of the wall system can be seen. The new wall systems consists of custom extruded aluminum trim and aluminum plank wall system. Both must match the aesthetic qualities of the original wall system, in both color and texture. Historically accurate replication of the aluminum rainscreen elements visible on the exterior will be paramount to the success of this project. Construction of the cladding panels and trim will require careful coordination with the SHPO Section 106 consulting parties and the Academy.
A weather resistant panel will be behind the aluminum panels. This panel system will contain insulation sealed within. One the panel has been installed, sealant will be installed along the edges to make the panel watertight. Custom extruded pipe sleeves will connect the panels to the existing structural steel frame.
Plaster, Speakers, and Lighting
Ref. 1/A-501
Ref. 3/A-202
The project will replace all lighting and controls in the protestant chapel exterior walls, at the interior and exterior. Only the lighting in the protestant level walls is being replaced; all other lighting is to remain.
Existing Steel Structure
Ref. 1/A-502 Existing Structural Steel
The existing structural steel will remain in its entirety. The steel is covered in its entirety in lead based paint, but no welding will disturb the paint. Intumescent paint must be applied on the entire steel system for fire protection.
Exterior Envelope – End Walls
Ref. 2/A-202
GLAZING:
Replace all glazing and aluminum storefront system with blast resistant glazing, retaining the existing steel structure.
DOORS AND METAL PANELS:
Restore the doors, hardware, and metal panels at the south entry to Protestant chapel. Very limited door repair and cac reader installation at one Catholic Level entrance as well.
(2/A-202) blow up
Fire Protection Current Scope:
Replace Fire Alarm System Install Mass Notification System Apply intumescent paint to structural steel Remainder of Scope to be finalized prior to DEC 17:
Modifications to some existing stairs Construction of fire-rated vestibule in the Catholic level Limited fire suppression
The project will replace all lighting and controls in the walls, both exterior and interior. Only the lighting in the protestant level walls is being replaced; all other lighting is to remain.
Pew and Organ Restoration
Pending Design Construction of performance testing mockup
Fabrication of aesthetic samples of aluminum panels and trim
Scoping investigation for organs and pews
Finalization of fire protection design
Replacement of speaker system
To assure performance characteristics and reduce risk of construability and performance issues, the Air Force in conjunction with AECOM and WJE are producing a full-scale mockup of the envelope design solution. This mockup will be tested for water and air intrusion, to validate performance. The mockup is also intended to validate constructability, and any encountered challenges will be addressed prior to release of the final design package.
In addition, a project to fabricate and anodize samples of the aluminum cladding and trim is currently underway. These samples will be made available to the awarded Contractor, as an aesthetic benchmark.
CTR Name is performing an investigation of both organs to define the restoration scope for the project; Pew restoration scope is also currently being finalized
Some additional fire protection design elements not currently shown in the Draft Final design submittal may be included in the final design submittal
The Draft Final design submittal shows reinstallation of the existing speaker system, but the final design submittal may include full replacement of that system.
PRODUCE QUALITY CONSTRUCTION
PROTECT EXISTING BUILDING AND CAMPUS
COOPERATION TO ACHIEVE MUTUAL BENEFIT
ENSURE JOB-SITE AND CAMPUS SAFETY
Produce quality construction Achieve the desired exterior envelope performance Accurately aesthetically accurate replicate of historic finishes Preservation the building for future generations of visitors
Protecting the existing building – preserve the out of scope interior and exterior finishes that are difficult to replicate with accuracy
Assure successful cooperation between Contractor and Air Force parties to complete the project as planned, Construct safely
Maintain high standards of job-site and campus safety, with sensitivity to the safety requirements of construction in an operating university campus
Closing Process for questions: Contractors to submit questions to the Contracting Officer at sally.kite@us.af.mil and Contracting Specialist at matthew.robey.3@us.af.mil image3.png image4.png image5.jpg image7.png image8.png image6.png image9.png image10.png image11.png image18.jpg image19.png image12.png image13.png image14.png image15.jpg image16.png image17.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.jpg image30.png image31.png image32.jpeg image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.png image51.emf image1.png image2.png