Clarifications_WEC_Matrix_15_May_15.pdf
PDF 10 KB Posted
- Attached to
- WORLDWIDE ENGINEERING & CONSTRUCTION (WE&C) Federal contract opportunity
- Solicitation number
- FA8903-15-R-0001
About this file
Clarifications from industry
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Worldwide Engineering & Construction (WE & C) RFP Solicitation - FA8903-15-R-0001
Question/Clarifications Matrix Dated 15 May 2015
1 Section L, 3.9.2 In reading Section L.3.9.2.a, since the FAR Clause discusses cost-reimbursement contracts, we interpret this to mean that a Prospective Contractor can be selected for the IDIQ prior to DCAA approval of their Accounting System. Can you confirm that our interpretation is correct?
This contract will be awarded with both FFP and CPFF CLINs, since both pricing arrangements will be available at the task order level. Therefore, DCAA approval of an offeror's accounting system is required prior to award required.
2 General Will a Integrated Priority List be published for the WE&C? There is no specific Integrated Priority List (IPL) for WE&C. However, a comprehensive fiscal 2015-2016 IPL for all Air Force requirements was published on 8 May 2015 and can be found on the AFCEC main webpage at http://www.afcec.af.mil/shared/media/document/AF D-140805-023.pdf