Attachment 03 Award Fee Plan 20260820.pdf

PDF 297 KB Posted

Attached to
HADES (Hybrid Architecture and Development for Experimental Systems) Request for Proposal Federal contract opportunity
Solicitation number
FA8809-26-R-B002
Issued by
Department of the Air Force

About this file

This is an Award Fee Plan for the Hybrid Architecture and Development for Experimental Systems (HADES) contract, solicitation number FA8809-26-R-B002, issued by the U.S. Air Force Space Systems Command (SSC/SYD89/SD). The plan establishes the framework for evaluating contractor performance and determining award fee compensation over fourteen six-month evaluation periods running from February 10, 2027 through February 9, 2034.

The HADES contract procures prototype and operational satellite ground systems, satellite operations centers (SOCs), and associated support services primarily at the Research, Development, Test, and Evaluation Support Complex (RSC) at Kirtland Air Force Base, Albuquerque, New Mexico. Contractor performance is evaluated across three weighted areas: Management (40%), Quality of Technical Services (40%), and Cost Control (20%). Award fee pool amounts are established at task order award with at least 40 percent allocated to the final award fee event. Performance ratings range from Unsatisfactory (0%-49%) to Excellent (91%-100%), with corresponding award fee earnings. Any contractor effort rated Unsatisfactory in a particular area receives zero award fee dollars for that area; if overall performance is Unsatisfactory, the entire award fee for the period is forfeited. The Award-Fee Review Board, chaired by the Chief of Innovation and Prototyping Division Ground, comprises seven voting members representing contracting, technical, budget, and operations functions. Monthly surveillance meetings provide feedback to the contractor, while formal end-of-period evaluations conducted by the AFRB inform the Fee Determining Official's final award determination within 30-60 days of period close. Additional criteria address health and safety violations and significant security violations, either of which may result in reduction or denial of earned award fee.

View the file

Other files for this federal contract opportunity

Other files attached to HADES (Hybrid Architecture and Development for Experimental Systems) Request for Proposal, newest first.
File Type Posted
Attachment 02 Ordering Instructions 20260901.pdf PDF
Attachment 08 Rights in Data 20260901.pdf PDF
(U) 00. HADES_Section L_20260901_v4.4.pdf PDF
HADES Q_A Amend 2.xlsx XLSX spreadsheet
Proposal_Manager_Functions.pdf PDF
FA880926RB002 Amendment 0002.pdf PDF
(U) 00. HADES_Section M_20260901_v4.4.pdf PDF
(U) 04. Jaguar_PWS_v4.0_20260901.pdf PDF
Attachment 01 HADES BASIC IDIQ_PWS 20260901.pdf PDF
Attachment 03 Award Fee Plan 20260901.pdf PDF
Exhibit A - HADES IDIQ CDRLs v.3.pdf PDF
(U) 03. Ground Support_PWS_v4.0_20260901.pdf PDF
25 Jun 26 - RSC Tour Sign In_Redacted.pdf PDF
Posting_Offer.pdf PDF
Exhibit A - HADES IDIQ CDRLs 20260820.pdf PDF
(U) 00. HADES_Section L_20260820_v4.3 Final.pdf PDF
(U) Section L Attach F Ground Support PWS 20260820.pdf PDF
Bidders Library Update 20 August 2026.pdf PDF
HADES RFP Q and A Amendment 0001 20 Aug 26.xlsx XLSX spreadsheet
Solicitation Amendment - FA880926RB0020001.pdf PDF
Solicitation Amendment FA8809-26-R-B002 0001 SF30.pdf PDF
Attachment 01 HADES Basic IDIQ PWS 20260820.pdf PDF
(U) Section L Attach D Ground Control PWS 20260820.pdf PDF
(U) Attachment 1 HADES_BASIC_IDIQ_PWS_20260724_v3.8.pdf PDF
Attachment 02 - Ordering Instructions.pdf PDF
Attachment 3 - Award Fee Plan.pdf PDF
(U) Section L Attch E Jaguar_PWS_v3.8_20260724.pdf PDF
(U) Section L Attch F Ground Support_PWS_v3.8_20260724.pdf PDF
(U) 00. HADES_Section L_20260721_v4.1_Appendix-A.docx DOCX document
(U) 00. HADES_Section L_20260721_v3.9_Attach-1.docx DOCX document
Attachment 04 - Base Support Agreement.pdf PDF
Attachment 08 - Rights in Data.pdf PDF
Attachment 10 - Small Business Subcontracting Plan.pdf PDF
(U) 00. HADES_Section L_20260731_v4.2-final.pdf PDF
(U) 00. HADES_Section L_20260721_v3.9_Attach-2.docx DOCX document
(U) 00. HADES_Section L_20260721_v3.9_Attach 6 OCI Mitigation Plan Checklist.pdf PDF
(U) 00. HADES_Section M_20260804_v4.2.1.pdf PDF
Vendor_Registration.pdf PDF
Solicitation - FA880926RB002.pdf PDF
Attachment 05 - OCI Mitigation Plan.pdf PDF
Attachment 07 - GFP and Inventory List.xlsx XLSX spreadsheet
Attachment 09 - Rates and Fees.pdf PDF
Attachment 12 - Associate Contractor Agreements.pdf PDF
(U) 05. Future Ground Sys_Dev_PWS_v2.0_20260731.pdf PDF
(U) 00. HADES_Section L_20260721_v3.9_Attach-4.docx DOCX document
(U) 00. HADES_Section L_20260721_v3.9_Attach-5.docx DOCX document
Attachment 06 - DD 254 for HADES Solicitation.pdf PDF
Attachment 11 - Small Business Participation.pdf PDF
Exhibit A - HADES IDIQ CDRLs.pdf PDF
(U) Section L Attch D Ground Control_PWS_v3.8_20260724.pdf PDF
Show all 50

HADES (Hybrid Architecture and Development for Experimental Systems) Request for Proposal has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION J FA8809-26-R-B001

ATTACHMENT 3

SECTION J – ATTACHMENT 3

AWARD FEE PLAN

AWARD-FEE PLAN

FOR

Hybrid Architecture and Development for Experimental Systems (HADES)

Contractor: TBD

Solicitation Number:

FA8809-26-R-B002

APPROVED:

Fee Determining Official

SSC SYD 89/SD Director Date

SECTION J FA8809-26-R-B001, ATTACHMENT 3

Contents Hybrid Architecture and Development for Experimental Systems

(HADES)

1.0 INTRODUCTION

2.0 ORGANIZATION AND RESPONSIBILITIES

2.1 Fee-Determining Official

2.2 Award-Fee Review Board

2.3 Award-Fee Review Board Chair

2.4 Government Program Manager

2.5 Procurement Contracting Officer

2.6 Area Leads

2.7 Performance Monitors

2.8 AFRB Advisors

2.9 AFRB Recorder

3.0 AWARD-FEE PROCESS

3.1 Award-Fee Process Overview

3.2 Award-Fee Evaluation Periods

3.3 Available Award-Fee Amount for Each Evaluation Period. 6

3.4 Evaluation Areas

3.5 Award-Fee Ratings

3.6 Evaluation Criteria

3.7 Monthly Surveillance Meetings

3.8 End-of-Period Evaluations

4.0 AWARD-FEE PLAN CHANGE PROCEDURE

5.0 CONTRACT TERMINATION

5.1 Termination for Convenience

5.1 Termination for Default

6 Annexes:

ANNEX 1: AWARD-FEE REVIEW BOARD

ANNEX 2: AWARD FEE EVALUATION CRITERIA

ANNEX 3: SAMPLE AWARD-FEE COMPUTATION

ANNEX 4: SAMPLE AVAILABLE AWARD FEE POOLS

AND EARNINGS

1.0 INTRODUCTION

1.1 The Hybrid Architecture and Development for Experimental Systems (HADES) contract is a procurement for prototype and operational satellite ground systems, satellite operations centers (SOCs), and support services. The contractor shall perform satellite ground system and satellite operations center engineering, development, integration, and sustainment, and associated support services primarily at, but not limited to, the Research, Development, Test, and Evaluation (RDT&E) Support Complex (RSC) at Kirtland Air Force Base, Albuquerque, New Mexico. The organization’s goal is to accelerate mission design and ground integration, launch and on-orbit operations, ground system tests, and rapid fielding to provide reliable, low-cost access to space in support of the warfighter.

1.2 This award-fee plan is the basis for SYD 89/SD’s evaluation of the Contractor's performance on the HADES contract and for presenting an assessment of that performance to the Fee Determining Official (FDO). As such, this award-fee plan serves as the quality assurance surveillance plan IAW FAR Part 46. It describes specific criteria and procedures used to assess the Contractor’s performance and to determine the amount of award fee earned.

1.3 The FDO will determine the award fee earned and payable to the Contractor based upon review of the Contractor’s performance against the criteria set forth in this plan. The award-fee determination is subjective in nature and is solely at the discretion of the Government;

however, the determination is subject to the Disputes clause of the contract. The award amount is intended to motivate excellence in contract performance; the Government will not reward unsatisfactory performance.

1.4 The award fee payment will be provided to the Contractor through contract modifications.

1.5 Before an evaluation period begins, the Government may unilaterally modify the award fee plan including technical or performance award fee events, evaluation criteria, and distribution of award fee dollars. All significant changes will be coordinated with the Award- Fee Review Board (AFRB and must be approved by the FDO. The Procurement Contracting Officer (PCO must provide written notice to the Contractor once any changes are approved.

Changes will not take effect if written notice is not given to the Contractor prior to the start of the next evaluation period. Changes affecting the current evaluation period may be implemented only by mutual agreement of the parties.

2.0 ORGANIZATION AND RESPONSIBILITIES

The award-fee organization consists of the FDO, an AFRB, which consists of a Chair and members, the Government Program Manager (GPM, PCO, Recorder, Area Leads, and performance monitors. These participants are listed in Annex 1, and responsibilities are outlined below:

2.1 Fee-Determining Official. The FDO is the designated Agency official who reviews the recommendations of the AFRB in determining the amount of award fee to be earned by the Contractor for each evaluation period. The FDO reviews the recommendations of the AFRB, considers all pertinent data, and independently determines the award-fee amount for each evaluation period. The FDO also approves the award-fee plan and any significant changes.

2.2 Award-Fee Review Board. The AFRB is a team of individuals identified in the award-fee plan who evaluate the Contractor’s overall performance for the award-fee evaluation period and recommends the earned award fee amount to the FDO. The AFRB will convene at the time, date, and place established by the AFRB Chair. The AFRB shall consider evaluations documented by the performance monitors and input from other sources that have observed the Contractor’s performance during the evaluation period.

After reviewing and discussing the information relating to the Contractor’s performance, the AFRB voting members shall individually vote on each evaluation area by signed ballot, with each member having only one vote. The AFRB may also recommend changes to this plan. The AFRB does not include Performance Monitors.

2.3 Award-Fee Review Board Chair. The AFRB Chairs is responsible for the overall functioning of the AFRB and will present the recommendation of the AFRB to the FDO.

2.4 Government Program Manager. The GPM is responsible for the overall management of the contract, including the award-fee process. The GPM will receive periodic performance evaluation reports from the Area Leads and may also provide his or her own performance reports. The GPM will ensure that the Recorder compiles these reports, obtains approval from the GPM, and provides the reports to the PCO for distribution to the Contractor.

2.5 Procurement Contracting Officer. The PCO is the liaison between contractor and Government personnel. The PCO transmits the FDO’s award-fee determination letter to the Contractor, prepares and distributes the contract actions to award the award fee or implement changes authorized by the FDO, and maintains appropriate award-fee documentation in the official contract file.

2.6 Area Leads. The Area Leads are the Branch Chiefs who are the users/customers for this contract. They appoint performance monitors to observe and evaluate contractor performance over all evaluation areas. The Performance Monitors write and provide the quarterly performance monitor evaluation reports and end-of-period performance evaluation reports to the Area Leads. The Area Leads review and provide the reports to the

GPM.

2.7 Performance Monitors. The Performance Monitors provide the continuous evaluation of the Contractor’s performance in specific assigned areas of responsibility.

Performance monitors are appointed by the Area Leads but are usually the mission managers for each task order. Performance monitors are responsible for assessing contractor performance in their appointed area(s) of responsibility and for maintaining written records of that performance. Performance monitors submit their evaluations to the Area Leads.

2.8 AFRB Advisors. AFRB advisors are Subject Matter Experts (SME, such as legal counsel, who provide guidance to the board and FDO but are not voting members of the board.

2.9 AFRB Recorder. The AFRB recorder is a non-voting member of the AFRB and is responsible for coordinating the administrative actions required by the Area Leads, AFRB members, AFRB Chair, and the FDO. The recorder may help assemble the briefing, schedule the board meeting, take minutes, etc.

3.0 AWARD-FEE PROCESS

3.1 Award-Fee Process Overview. The Government will determine the amount of fee awarded for a given evaluation period based on continuous performance monitoring and periodic performance reporting, which includes quarterly and end-of-period evaluations. In order to meet the minimum requirements of the PWS, the Contracting Officer Representative’s (COR) inputs will be utilized as part of the AF plan process. The role of the COR will be delegated to the Government Program Manager (GPM). The AFRB will use these evaluations to make a performance rating and award-fee recommendation to the FDO, who will then make the final determination. The process consists of the following steps:

3.1.1 During an evaluation period, Performance monitors continuously observe contractor performance and compare that performance to the criteria included in this award-fee plan (see Annex 2). Performance monitors then document the performance details, the manner in which the performance compares to the criteria, and the impact of the performance.

Performance monitors submit these performance reports to the Area Leads for review and submission to the GPM. The GPM regularly consolidates these submissions and presents them at quarterly surveillance meetings (see section 3.7). The PCO may also issue letters at any other time when it is deemed necessary to highlight areas of Government concern. Additionally, the Government will provide informal feedback during monthly status meetings with the Contractor; discussion of any significant issues will be documented. The PCO will provide these quarterly surveillance interim reports as documented under paragraph 3.7.

3.1.2 At the end of an evaluation period, Area Leads review the performance monitor reports from the entire period and determine whether the impact to the mission is positive or negative and to what degree (see section 3.8). The Area Leads then compile the performance reports in their area into briefing charts and send to the GPM for review.

The GPM will ensure that the Recorder collects these inputs, prepares a consolidated briefing to the AFRB, re-distributes the briefing to the Area Leads for review, and makes any necessary edits. Next, the GPM and Area Leads conduct the briefing to the AFRB, and the AFRB evaluates the Contractor’s performance and provides the award-fee recommendation to the FDO (see section 3.8).

The GPM will ensure that the Recorder prepares the FDO briefing and the AFRB chair leads the presentation of the AFRB recommendation to the FDO. The FDO then makes the final performance and award-fee determination and signs a letter communicating this determination to the Contractor. Finally, the PCO awards the fee to the Contractor via contract modifications.

3.2 Award-Fee Evaluation Periods. The following table shows the award-fee evaluation periods covered by the contract.

Evaluation Period From To One (Includes Transition) 10 FEB 27 9 AUG 27 Two 10 AUG 27 9 FEB 28 Three 10 FEB 28 9 AUG 28 Four 10 AUG 28 9 FEB 29 Five 10 FEB 29 9 AUG 29 Six 10 AUG 29 9 FEB 30 Seven 10 FEB 30 9 AUG 30 Eight 10 AUG 30 9 FEB 31 Nine 10 FEB 31 9 AUG 31 Ten 10 AUG 31 9 FEB 32 Eleven 10 FEB 32 9 AUG 32 Twelve 10 AUG 32 9 FEB 33 Thirteen 10 FEB 33 9 AUG 33 Fourteen 10 AUG 33 9 FEB 34

3.3 Available Award-Fee Amount for Each Evaluation Period.

3.3.1 Establishment of the Available Award Fee Pool Amount. The award fee pool amounts will be established at the time of the award of the task order. Each task order will establish the estimated cost (for the CLIN value) and the available award fee pool dollars. The available award fee pool dollars are allocated to award fee events (task completion milestones or deliverables). The available award fee pool dollars with the corresponding award fee events will be inserted into a model similar to that in Annex 4. This model will be maintained and updated throughout the life of the contract. The model will be maintained separate from the contract document. The Government will share the model with the Contractor following any updates and/or changes, and additionally distribute the document upon any formal or informal request.

This model will be presented at all Award Fee Review Boards. For each award fee event, exit criteria will be established. IAW DFARS 216.405-2(1), for each task order, the PCO must ensure that at least 40 percent of the available award fee is assigned to the last award fee event.

3.3.2 Evaluation of Award Fee Events for Award Fee Earnings. At the end of each evaluation period, as defined in Paragraph 3.2, all events completed within that timeframe (met exit criteria) will be evaluated to determine the award fee earnings. The available award fee pools for the completed award fee events will be summed to constitute the available award fee pool for the period. See Annex 3 for sample computation. This total available award fee pool for the period will be subjected to the AFRB evaluation for the FDO’s determination of how much of the pool will be awarded to the Contractor. Note that some award fee events may have performance spanning across multiple award fee periods. These events are not evaluated until the period in which they are completed.

3.4 Evaluation Areas. The following table outlines the areas and the weighting of each area upon which the Government will evaluate the award fee events completed during the period.

The Government will use Annex 2 to assess the Contractor’s performance. The assessments will roll- up into a single adjectival rating and a single award fee percent earned (if any) for the period, as shown in Paragraph 3.5.

Evaluation Areas Evaluation Area Weighting

Area A: Management 40% Area B: Quality of Technical Services 40% Area C: Cost Control 20%

3.5 Award-Fee Ratings. The results of the AFRB will roll up into a single adjectival rating.

The following table defines the possible ratings for the evaluation period. Each rating indicates a range of potential award fee the Contractor can earn. The FDO will make a determination as to the percentage earned for the period.

Award-Fee Adjectival Rating

Award-Fee Pool Available To Be

Earned Description

Excellent 91% - 100%

Contractor has exceeded almost all of the significant award-fee criteria and has met overall cost, schedule, and technical performance requirements of the contract in the aggregate as defined and evaluated against the criteria in the award-fee plan for the award-fee evaluation period.

Very Good 76% - 90%

Contractor has exceeded many of the significant award-fee criteria and has met overall cost, schedule, and technical performance requirements of the contract in the aggregate as defined and evaluated against the criteria in the award-fee plan for the award-fee evaluation period.

Good 51% - 75%

Contractor has exceeded some of the significant award-fee criteria and has met overall cost, schedule, and technical performance requirements of the contract in the aggregate as defined and evaluated against the criteria in the award-fee plan for the award-fee evaluation period.

Satisfactory 50%

Contractor has met overall cost, schedule, and technical performance requirements of the contract in the aggregate as defined and evaluated against the criteria in the award-fee plan for the award-fee evaluation period.

Unsatisfactory 0% - 49%

Contractor has failed to meet overall cost, schedule, and technical performance requirements of the contract in the aggregate as defined and evaluated against the criteria in the award-fee plan for the award-fee evaluation period.

3.6 Evaluation Criteria. Performance monitors will use the evaluation criteria in Annex 2 to assess contractor performance. The Contractor is considered to have performed as Unsatisfactory for performance outputs as shown in Column 1 of each evaluation area of Annex

2. The Contractor is considered to have performed in the range of Satisfactory if their performance meets the criteria in Column 2 of each evaluation area of Annex 2. The Contractor is considered to have performed as Good if their performance meets the criteria in Column 3 of each evaluation area of Annex 2. The Contractor is considered to have performed as Very Good if their performance meets the criteria in Column 4 of each evaluation area of Annex 2. The extent to which the Contractor has exceeded all the requirements is determined as Excellent against the criteria in Column 5 of each evaluation area of Annex 2.

3.7 Monthly Surveillance Meetings. Periodic feedback will be provided to the Contractor to ensure problems are identified and addressed as early as possible (see 3.1.1). These surveillance meetings will take place each month of the evaluation period. Performance monitors will identify in their evaluations those areas where improved contractor performance is necessary or required and areas of strengths.

If the Contractor fails to show improvement in problem areas, the Contracting Officer may communicate an area of concern, after coordinating with the AFRB, emphasizing areas needing improvement. For each letter issued, the Contractor is required to provide a written response within 15 calendar days. The response should, at minimum, set forth plans for improving performance in the areas noted or explain why it is not feasible to do so.

When requested by the Contractor, the Government will provide a briefing on strengths, weaknesses, and areas for improvement or special emphasis based on the AFRB evaluation. The PCO will provide quarterly surveillance reports which will serve as an interim evaluation report. If the end-of-the-quarter period coincides with the end-of-the-award fee evaluation period, the end-of-period evaluation will be provided in lieu of the quarterly interim reports.

3.8 End-of-Period Evaluations. The AFRB Recorder notifies each AFRB member and Area Leads 30 calendar days before the end of the evaluation period. At the end of an evaluation period, the Area Leads and GPM will (1) review all the performance reports from the evaluation period and (2) identify the relative impact of contractor performance using the metrics provided in the chart below.

Excellent Major or Potentially Major Positive Program Impact Very Good Moderate or Potentially Moderate Positive Program

Impact Good Minor Positive Program Impact Satisfactory Met Mission Requirements

Unsatisfactory Negative Program Impact

AFRB voting members will then review the significant reports for each evaluation area to determine a rating for each area in accordance with the Award Fee Evaluation Criteria, Annex 2.

The AFRB members will be provided access to all CDRLs, deliverables and performance evaluation reports. Additionally, AFRB voting members will provide their ratings for each performance evaluation area (see 3.4). The AFRB Chair will then lead the briefing to the FDO on the board’s recommendation for the percentage of fee to be awarded. At the end of the briefing, the FDO will make the award-fee determination. The PCO will forward a letter from the FDO informing the Contractor of the award-fee determination. A Memorandum for Record (MFR) will be drafted for FDO signature documenting the rationale for any variations between the AFRB recommendation and the FDO determination. The PCO will perform the necessary contractual actions to provide the award fee to the Contractor. See Annex 3 for a sample award-fee computation.

The Contractor shall participate in the award fee process up to the point of AFRB and FDO briefing/discussions but will not be present during the Government deliberations or voting. The Contractor will brief the AFRB for a period not to exceed 30 minutes. Written contractor self-assessment of performance shall be submitted to the AFRB through the PCO for each evaluation period under consideration. Self-assessments shall be no more than 10 pages in length and should be submitted no later than 10 business days following the close of an evaluation period.

FDO briefings should be completed within 30 days of the end of the evaluation period but not later than 60 days after the end of the period. The PCO will subsequently send the FDO signed letter to the Contractor, informing the Contractor of the amount of award fee earned and the overall associated performance rating.

4.0 AWARD-FEE PLAN CHANGE PROCEDURE

During the first month of the award fee period, the GPM will provide the AFRB members a copy of the award fee plan. The AFRB members will be asked to review the plan with a focus on the award fee criteria. When the AFRB meets at the end of an evaluation period, board members will be asked to verify that the evaluation criteria are still a valid description of the level of performance expected. Any recommended adjustments may initiate an award-fee plan change.

Additionally, other necessary changes may be discovered during the implementation of this plan. The Contractor may recommend changes to the PCO no later than 30 calendar days prior to the beginning of the new evaluation period.

All significant changes to this award-fee plan must be approved by the FDO; the AFRB Chair may approve other changes. Examples of significant changes include changing evaluation criteria, adjusting weights associated with the evaluation area, changing AFRB membership, or revising the distribution of the award-fee dollars.

After approval by the FDO or the delegated AFRB Chair, the PCO shall notify the Contractor in writing of any changes to this plan. If the Contractor is so notified at least 15 calendar days before the start of a new evaluation period, the changes will be incorporated into the contract unilaterally for the upcoming period. Changes made within 15 days of a new evaluation period or changes affecting a current evaluation period must be made by bilateral agreement.

5.0 CONTRACT TERMINATION

5.1 Termination for Convenience. In the event that the contract is terminated for the convenience of the Government, the amount of award fee to which the Contractor is entitled shall be determined as follows:

(1) Award-fee earned or earnable by the Contractor for award fee evaluation periods completed prior to the effective date of the termination will not be affected by the termination.

(2) Award-fee deemed earned and to be paid for performance during the period before the termination becomes effective will be determined by the FDO in accordance with the approved award fee criteria and will not be subject to negotiation as part of the equitable adjustment in accordance with the termination clause of the contract.

For purposes of fee determination, contractor performance evaluation will end as of the date of termination.

(3) The remaining award-fee dollars for all periods subsequent to the effective date of the termination will not be considered earned or earnable and, therefore, will not be paid.

5.1 Termination for Default. In the event of a termination for default, the award fee is payable only to the extent earned through the last period prior to termination. The Contractor shall not earn award fee for the period in which the default occurred. Consequently, no additional award fee shall be paid during the termination settlement of the contract. Award-fee earned or earnable by the Contractor for award-fee evaluation periods completed prior to the effective date of the termination will not be affected by the termination, unless other provisions of the contract and/or award –fee plan (e.g., negative incentive) require payback of previously earned fee.

6.0 Annexes:

1. Award-Fee Review Board Participants

2. Award-Fee Evaluation Criteria

3. Sample Award-Fee Computation

4. Sample Available Award Fee Pools and Earnings

ANNEX 1: AWARD-FEE REVIEW BOARD

Fee Determining Official:

Director, Innovation and Prototyping Delta

SSC/SYD89/SD

Award-Fee Review Core Board Members:

Chair, Innovation and Prototyping Division Ground SSC/SYD89/SDG

Voting Members:

Chief, Innovation and Prototyping Division Ground

Chief of Contracting, Innovation and Prototyping Delta

SSC/SYD89/SDG

SSC/SYD89/SFPEO-

SCP/PK

Technical Director, Innovation and Prototyping Delta SSC/SYD89/SD

Contracting Officer SSC/SYD89/SFPEO-

SCP/PK

Budget Chief, Innovation and Prototyping Delta SSC/SYD89/SDF

Chief, Innovation and Prototyping Division Operations SSC/SYD89/SDX

Government Program Manager SSC/SYD89/SDG

Non-Voting Members:

Recorder SSC/SYD89/SD

Program Attorney

SSC/JA

Performance Monitors: Personnel in the Innovation and Prototyping Delta Divisions, as appointed by Area Leads.

ANNEX 2: AWARD FEE EVALUATION CRITERIA

Area A: Management

1: Unsatisfactory 2: Satisfactory 3: Good 4: Very Good 5: Excellent Manage mission tasks within program schedule constraints based on a variance of 60% deviation of monthly schedules compared to master IMS per evaluation period.

Key positions remain vacant or filled with other than a qualified or cleared person for more than 20 business days (interim filling of key positions acceptable as long as permanently fill is in place within 30 days).

Necessary human resources with the appropriate clearances to fill positions at a rate of 70% for non-key personnel.

The overall small business utilization for the evaluation period’s total subcontracted contract value is less than 25%.

Provide Program management across the contract as evaluated based on the monthly program status reports for an overall grade of unsatisfactory.

Manage mission tasks within program schedule constraints based on a variance of 50% deviation of monthly schedules compared to master IMS per evaluation period.

Ensure all key positions are filled with qualified and cleared personnel and do not remain vacant or filled with other than a qualified or cleared person no more than 20 business days (interim filling of key positions acceptable as long as permanently fill is in place within 30 days).

Necessary human resources with the appropriate clearances to fill positions at the rate of 75% for non-key personnel.

The overall small business utilization for the evaluation period’s total subcontracted contract value is between 25% and 27%.

Provide Program management across the contract as evaluated based on the monthly program status reports for an overall grade of satisfactory.

Manage mission tasks within program schedule constraints based on a variance of 40% deviation of monthly schedules compared to master IMS per evaluation period.

Ensure all key positions are filled with qualified and cleared personnel and do not remain vacant or filled with other than a qualified or cleared person no more than 15 business days (interim filling of key positions acceptable as long as permanently fill is in place within 30 days).

Necessary human resources with the appropriate clearances to fill positions at a rate of 80% for non-key personnel.

The overall small business utilization for the evaluation period’s total subcontracted contract value is between 28% and 30% Provide Program management across the contract as evaluated based on the monthly program status reports for an overall grade of good.

Manage mission tasks within program schedule constraints based on a variance of 30% deviation of monthly schedules compared to master IMS per evaluation period.

Ensure all key positions are filled with qualified and cleared personnel and do not remain vacant or filled with other than a qualified or cleared person no more than 10 business days (interim filling of key positions acceptable as long as permanently fill is in place within 30 days).

Necessary human resources with the appropriate clearances to fill positions at a rate of 85% for non-key personnel.

The overall small business utilization for the evaluation period’s total subcontracted contract value is between 31% and 33%.

Provide Program management across the contract as evaluated based on the monthly program status reports for an overall grade of very good.

Manage mission tasks within program schedule constraints based on a variance of 20% deviation of monthly schedules compared to master IMS per evaluation period.

Ensure all key positions are filled with qualified and cleared personnel and do not remain vacant or filled with other than a qualified or cleared person no more than 5 business days (interim filling of key positions acceptable as long as permanently fill is in place within 30 days).

Necessary human resources with the appropriate clearances to fill positions at the rate of 90%.

Demonstrates flexibility in reach back ensuring that all task order requirements are met and that no mission is adversely impacted due to lack of resources.

The overall small business utilization for the evaluation period’s total subcontracted contract value is 34% or more.

Provide Program management across the contract as evaluated based on the monthly program status reports for an overall grade of excellent.

Take initiative to incorporate lessons learned and act as a mission partner to identify issues and opportunities for the Government, customers, and Government associate contractors that will minimize impact to mission operations.

Area B: Quality of Technical Services

1: Unsatisfactory 2: Satisfactory 3: Good 4: Very Good 5: Excellent

More than three unapproved deviations of 20% or more from cost/schedule/perform ance metrics for any activity as reported in the monthly task order status report.

More than three non- critical mission operation failures or one mission critical operation failure per evaluation period when conducting sustainment, maintenance, and system management functions.

Processes and system experience negative cost/schedule/perform ance impact when cybersecurity or mission processes change.

Average (over the period) problem resolution time greater than two hours (8/5).

Three unapproved deviations of 20% or more from cost/schedule/perform ance metrics for any activity as reported in the monthly task order status report.

Conduct sustainment, maintenance, and system management functions, with no mission critical operation failures and no more than three non-critical mission operation failures per evaluation period.

Processes and system experience no cost/schedule/perform ance impact when cybersecurity or mission processes change.

Average (over the period) problem resolution time equal to two hours.

Two unapproved deviations of 20% or more from cost/schedule/perform ance metrics for any activity as reported in the monthly task order status report.

Conduct sustainment, maintenance, and system management functions, with no mission critical operation failures and no more than two non-critical mission operation failures per evaluation period.

Processes and system experience up to 5% improvement in cost/schedule/perform ance impact when cybersecurity or mission processes change.

Average (over the period) problem resolution time greater than 90 minutes, less than 120 minutes.

One unapproved deviation of 20% or more from cost/schedule/perform ance metrics for any activity as reported in the task order monthly status report.

Conduct sustainment, maintenance, and system management functions, with no mission critical operation failures and no more than one non-critical mission operation failures per evaluation period.

Processes and system experience from 5% to 10% improvement in cost/schedule/perform ance impact when cybersecurity or mission processes change.

Average (over the period) problem resolution time greater than 60 minutes, less than 90

No unapproved deviations of 20% or more from cost/schedule/performance metrics for any activity as reported in the task order monthly status report.

Conduct sustainment, maintenance, and system management functions without impact to mission operations.

Processes and system experience from 5% to 10% improvement in cost/schedule/performance impact when cybersecurity or mission processes change.

Average (over the period) problem resolution time less than 60

SECTION J FA8818-20-D-0009

ATTACHMENT 3

Area C: Cost Control

1: Unsatisfactory 2: Satisfactory 3: Good 4: Very Good 5: Excellent Accurately execute cost type task orders with more than 3 task orders above 10% or below 20% of the task order’s cost on any monthly report during the evaluation period.

Fail to anticipate cost growth on change to operational requirements.

Accurately execute cost type task orders with no more than 3 task orders above 10% or below 20% of the task order’s cost on any monthly report during the evaluation period except as indicated in the criteria below.

Correctly anticipate cost changes (plus/minus) on change to operational requirements, with no associated recommendations.

Accurately execute cost type task orders with no more than 2 task order above 10% or below 20% of the task order’s cost on any monthly report during the evaluation period except as indicated in the criteria below.

Proactively recommend changes to achieve cost savings of from 1% to 5%, with associated rationale.

Accurately execute cost type task orders with no more than 1 task order above 10% or below 150% of the task order’s cost on any monthly report during the evaluation period except as indicated in the criteria below.

Proactively recommend changes to achieve cost savings of from 6% to 10%, with associated rationale.

Accurately execute cost type task orders with no task orders above the task order cost and no task orders below 10% of task order’s cost on any monthly report during the evaluation period except as indicated in the criteria below.

Proactively recommend changes to achieve cost savings of greater than 10%, with associated rational.

Note: Overruns and underruns shall be assessed objectively.

NOTE:

1. Any contractor effort rated “Unsatisfactory” in a particular area shall receive zero award- fee dollars ($0) for that area. In addition, if the Contractor’s overall performance is rated “Unsatisfactory,” the Contractor shall receive zero award-fee dollars ($0) for the award- fee period.

ADDITIONAL CRITERIA:

1. IAW R-DFARS 216.402-470, the PCO must evaluate contractor and subcontractor actions that may jeopardize the health or safety of Government personnel, through gross negligence or reckless disregard for the safety of such personnel. The PCO shall consider reducing or denying award fee for the evaluation period that such actions occurred. These actions are determined through either a conviction in a criminal proceeding, or finding of fault and liability in a civil or administrative proceeding. If the Contractor or a subcontractor at any tier is not subject to the jurisdiction of the U.S. courts, a final determination of contractor or subcontractor fault will result from a DoD investigation.

2. If the Contractor or subcontractor is responsible for a security violation and is determined significant by the FDO, the award fee may be reduced up to 100% of the earned award fee for the evaluation period in which the action occurred.

ANNEX 3: SAMPLE AWARD-FEE COMPUTATION

Award Fee Pool Calculation

Award-Fee Events Completed During Evaluation Period Award-Fee Pool Task Order 1, Award-Fee Event 4 $400,000 Task Order 2, Award-Fee Event 2 $500,000 Task Order 4, Award-Fee Event 1 $100,000 Total Available Award-Fee Pool $1,000,000

Evaluation Areas

Total Available Award-Fee Pool $1,000,000

Management 40% $400,000 Quality of Technical Services 40% $400,000 Cost Control 20% $200,000

Award Fee Earned – Sample 1

Evaluation Areas Weight Available Award Fee

Evaluation Point

Award-Fee % Earned

Award-Fee Amt Earned

Management 40% $400,000 100 100% $400,000 Quality of Technical Services 40% $400,000 90 90% $360,000 Cost Control 20% $200,000 80 80% $160,000 Total Award-Fee Amount Calculation $920,000

Percent Award-Fee Earned Calculation 92%

Overall Performance Rating Excellent

Determination of Award Fee Earned $920,000

Award Fee Earned – Sample 2 Evaluation Areas Weight Available

Award Fee Evaluation

Point Award-Fee % Earned

Award-Fee Amt Earned

Management 40% $400,000 60 60% $240,000 Quality of Technical Services 40% $400,000 40 0% $0 Cost Control 20% $200,000 80 80% $160,000 Total Award-Fee Amount Calculation $400,000

Percent Award-Fee Earned Calculation 40%

Overall Performance Rating Unsatisfactory

Determination of Award Fee Earned $0

Note: Award-fee pool figures are fictitious and are only meant to illustrate award-fee pool computations.

ANNEX 4: SAMPLE AVAILABLE AWARD FEE POOLS AND EARNINGS

Task Order, Mod Number, Milestone #

Available Award Fee Pools

Period Evaluated

Percent Earned

Dollars Earned

Award Fee Payment Mod

TO#1, Mod#12, Milestone 1 $200,000 1 80% $160,000 xxx TO#1, Mod#12, Milestone 2 $300,000

Totals

Hybrid Architecture and Development for Experimental Systems (HADES)
1.0 INTRODUCTION
2.0 ORGANIZATION AND RESPONSIBILITIES
3.0 AWARD-FEE PROCESS
3.3 Available Award-Fee Amount for Each Evaluation Period.
4.0 AWARD-FEE PLAN CHANGE PROCEDURE
5.0 CONTRACT TERMINATION
6.0 Annexes:
ANNEX 1: AWARD-FEE REVIEW BOARD
ANNEX 2: AWARD FEE EVALUATION CRITERIA
ANNEX 3: SAMPLE AWARD-FEE COMPUTATION
ANNEX 4: SAMPLE AVAILABLE AWARD FEE POOLS AND EARNINGS

File details come from the government source that posted it. Updated .