This document is a summary table from the Department of Defense (DoD) displaying data on the time required to definitize Change Order Defnitization Proposals under Construction Contracts.

The table presents the distribution of 247 total Change Order Proposals across various timeframes for definitization. The data shows that 45 proposals were definitized within 30 days or less, 36 proposals took 31 to 60 days, 24 proposals required 61 to 90 days, 49 proposals took 91 to 180 days, 49 proposals took 181 to 365 days, and 44 proposals required greater than 365 days for definitization. Additionally, 151 proposals were definitized after completion of contract performance via contract modification, addressing all undefinitized equitable adjustments received during contract performance. The document is provided in Version 6.4.0 and includes export functionality for CSV and PDF formats for use in Contract Opportunity notices.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .