The document contains a Data Item Description (DID) for a Contractor's Risk Management Plan and information about a related federal contract opportunity for Training Systems Acquisition (TSA) IV. The DID specifies the required format and content for a Contractor's Risk Management Plan, including a cover page, revision control, table of contents, and sections addressing the introduction, scope, program summary, risk management strategy and process, responsible organizational component, risk management procedures, risk identification, analysis, mitigation planning and implementation, tracking, and figures/tables. The plan must be submitted electronically in MS Word 2010 or later format.
The federal contract opportunity notice indicates the Air Force Life Cycle Management Center plans to competitively award multiple TSA IV ID/IQ contracts to streamline training system acquisition and support procurement processes. The majority of work will involve sustainment activities like contractor logistics support, technical support services, and software upgrades for existing training systems. TSA IV will also include courseware development and instruction, as well as development of new training systems.
View the file
Other files for this federal contract opportunity
Show all 50
Training Systems Acquisition (TSA) IV has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
Title: Contractor’s Risk Management Plan
Number: DI-MGMT-81808 Approval Date: 20100421 AMSC Number: N9131 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility: SH/PMS 408 Applicable Forms: N/A
Use/Relationship: The Contractor’s Risk Management Plan will be used to monitor management, cost and schedule of the contract efforts relative to a system and equipment. This information will provide the government with risk data for all risks associated with the system/equipment.
This Data Item Description (DID) contains the format, content, and preparation instructions for the data product resulting from the work task specified in the contract.
Requirements:
1. Format. The plan shall be in contractor’s format.
2. Content. The plan shall contain a cover and title page identifying the following:
a. Plan date of issue.
b. Plan document number/revision number or letter.
c. Contract number.
d. Contractor name and address.
e. Title of plan.
f. Program title.
g. Security classification, if classified.
h. Distribution statement.
i. Destruction notice.
2.1. Revision Control . The plan shall contain a list of all revisions identifying the following information:
a. Each revision number or letter.
b. Date of each revision.
c. Pages affected by each revision.
2.2. Table of Contents. The table of contents shall identify each major section title, paragraph number, and starting page number for each major section.
Page 1 of 2 Pages
Source: http://assist.dla.mil -- Downloaded: 2020-08-31T18:23Z Check the source to verify that this is the current version before use.
DI-MGMT-81808 (Continued)
2.3. Contents. The plan shall address in depth each major section identified below:
a. Introduction
b. Scope.
c. Program Summary
d. Risk Management Strategy and Process
e. Responsible /Executing Organizational Component
f. Risk Management Process and Procedures
g. Risk Identification
h. Risk Analysis
i. Risk Mitigation Planning
j. Risk Mitigation Implementation
k. Risk Tracking
l. Figure(s) and Table (s)
2.4 Media requirements. The plan shall be presented in electronic format MS Word version 2010 or later.
3. END OF DI-MGMT-81808.