This Statement of Objectives describes the relocation of a Noise Suppressor Hush House from Robins Air Force Base in Georgia to Holloman Air Force Base in New Mexico. Services required include site assessments, transportation, disassembly and packaging, loading and unloading, repair and refurbishment of components, reassembly and installation, and verification testing. Specific tasks identified are inspection and repair of all components to restore full functionality according to technical orders and drawings, corrosion control of intake and cooling baffles, removal and disposal of the fire suppression system including returned Halon, and replacement of main door components and systems with engineering change proposals and notices of revision. Applicable technical orders, drawings, engineering change proposals and notices of revision are provided in appendices.
Attachment 9, Statement of Objectives for Sample Task 1
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES
FOR
Hush House RElocation
VERSION A
10 May 2017 Location:
from ROBINS AFB, GA to HOLLOMAN AFB, NM
NOMENCLATURE: A/F37T-10 NOISE SUPPRESSOR/HUSH HOUSE
MODEL: A/F32T-10
NSN: 4920-01-127-4640
Prepared by:
MICK RANDEL
AFLCMC/WN-SEV
Warner Robins Air Logistics Complex (WR-ALC)
The marking requirements of DoDD 5230.24 do not apply to this document.
No data/documents incorporated by reference are export controlled.
STATEMENT OF OBJECTIVES
Hush House relocation
1.0 DESCRIPTION OF SERVICES
The purpose of this Statement of Objectives (SOO) is to provide relocation of a Noise Suppressor including, but not limited to, (a) Original site assessments to include a full functional test, (b) Coordination and inspection of predetermined gaining site, (c) Transportation including planning and scheduling, (d) Disassembly and packaging for shipment, (e) Removal of material and debris from original site (not including the foundation and slab or utility entry points/stub-ins,) (f) Loading, (g) Potential storage of components, (h) Coordination of required utility installation and activation for new site through the Noise Suppressor Program Office (the Noise Suppressor Program Office will coordinate the requirement with the local Base Civil Engineer,) (i) Unloading at new site, (j) Repair/Refurbishment of sub-components, (k) Reassembly/Installation to restore to full operating capability, and (l) Verification testing/inspections.
2.0 SERVICES SUMMARY
| Objective |
| SOO paragraph |
| Performance Threshold |
Inspect and repair all components listed within the SOO in order to provide fully functional Hush Houses with all repaired components operating as originally designed and repaired in accordance with the standard Hush House configuration.
| SOO section 3 |
| The Government will reject the workmanship or installation quality of the repaired components if one or more major flaws or two or more minor flaws are discovered by Government personnel during final inspections. A major flaw is defined as any inoperable components or systems repaired, or systems/components not repaired in accordance with the standard configuration. A minor flaw is defined as functional and operable systems not fully meeting the standard configuration, as defined by the Hush House drawing package. All major and minor flaws identified during the Government’s final inspection shall be corrected within 7 days of Government disapproval. |
3.0 GENERAL INFORMATION
The standard configurations for the Hush Houses in this document are defined by the Hush House Technical Orders, drawings, and approved engineering change proposals (ECPs) and notices of revision (NORs,) within the Appendix (section 4.0) of this document.
The standard Hush House configuration and original design for all of the T-10 Hush Houses covered in this SOO are defined by the T-10/11 drawing package – top level 8045881 (T-10) and all applicable sub drawings.
3.1 Hush House Relocation: The Hush House to be relocated shall be considered a -30 configuration by the contractor. The Contractor shall disassemble the Hush House located at Robins AFB, GA, repair/refurbish/replace parts/systems/subsystems as necessary, and reassemble the Hush House at Holloman AFB, NM. The contractor shall be responsible for all associated shipping. Refurbishment/Refurbish, where used, shall be defined as all the repair work necessary to restore an item or component to “like new” condition. Also, the Contractor shall support engine installation, preparation and testing to confirm all parts of the Hush House are functioning properly. Support of system calibration during the preparation phase is also required.
3.2
Corrosion Control: Delaminating corrosion is present in the lower sections of the intake and cooling baffles. The contractor shall perform corrosion control as required to return the baffles to a like-new condition.
3.3
Fire Suppression System (FSS): The Hush House is equipped with a Halon-based FSS. The contractor shall remove and properly dispose of the FSS, including return of Halon to DLA.
3.4 Required Configuration Updates: To bring the Hush House within the current configuration, the following components and subsystems require replacement:
· In addition to general refurbishment, the main door system require application of ECPs 166, 167, 168, and 172
4.0 APPENDICES
4.1 Air Force Technical Orders (TOs): The following documents are applicable to this PWS to the extent specified herein.
| Tech Order |
| Description |
| Applicable |
| 33D4-6-645-1 |
| Operation and Maintenance Instructions, Enclosed Noise Suppressor System Aircraft/Engine (Hush House), A/F37T-10/11 |
| Entire Technical Order is applicable. |
| 33D4-6-645-4 |
| Illustrated Parts Breakdown, Enclosed Noise Suppressor System Aircraft/Engine (Hush House), A/F37T-10/11 |
| Entire Technical Order is applicable. |
4.2 Air Force Drawings: The T-10 drawings package is defined by the T-10/11 Top Level drawing 8045881 and all subsequent drawings.
4.3 ECPs and NORs: The following documents are applicable to this PWS to the extent specified herein.
| ECP/NOR |
| Description |
| Applicable |
| 166 |
| Main Door Motors - 2hp Motor Replacement |
| Entire ECP/NOR is applicable. |
| 167 |
| Main Door Drive Boxes |
| Entire ECP/NOR is applicable. |
| 168 |
| Illustrated Parts Breakdown, Enclosed Noise Suppressor System Aircraft/Engine (Hush House), A/F37T-10/11 |
| Entire ECP/NOR is applicable. |
| 172 |
| Main Door Festoon Cable & Track Material Upgrade |
| Entire ECP/NOR is applicable. |