This Statement of Objectives outlines requirements for the conversion of a T-10 noise suppressor fire suppression system from halon to NOVEC 1230 at Robins Air Force Base in Georgia. Key requirements include removing the existing halon system, installing a new pneumatically actuated NOVEC 1230 system that interfaces with the existing PLC controls and meets NFPA 2001 concentration standards, and proper disposal of halon. The contractor must test the new system and ensure integration with hush house doors, alarms, controls and aircraft. Technical orders and drawings define the standard T-10 configuration.
The related federal contract opportunity is a draft Request for Proposal to repair and install fire suppression systems on various noise suppressors using NOVEC 1230, and deliver technical data. Repairs and installations are required for systems on the A-18, T-4, T-9, T-10, T-11, T-12, and T-10 enclosure for T-56 engines. The Department of the Air Force is the issuing agency.
Attachment 10, Statement of Objectives for Sample Task 2
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES
FOR
t-10 fire suppression system conversion
VERSION A
10 May 2017 Location:
ROBINS AFB, GA
NOMENCLATURE: A/F37T-10 NOISE SUPPRESSOR/HUSH HOUSE
MODEL: A/F32T-10
NSN: 4920-01-127-4640
Prepared by:
MICK RANDEL
AFLCMC/WN-SEV
Warner Robins Air Logistics Complex (WR-ALC)
The marking requirements of DoDD 5230.24 do not apply to this document.
No data/documents incorporated by reference are export controlled.
STATEMENT OF OBJECTIVES
T-10 FIRE SUPPRESSION SYSTEM CONVERSION
1.0 DESCRIPTION OF SERVICES
The purpose of this Statement of Objectives (SOO) is to provide conversion of a Noise Suppressor from Halon to Novec including, but not limited to, (a) Site assessment to determine full scope of work, (b) Removal of existing Halon Fire Suppression System (FSS,) (c) Installation of new Novec FSS, (d) Modifications to noise suppressor as required in support of Novec FSS installation, and (e) Verification testing/inspections.
2.0 SERVICES SUMMARY
| Objective |
| SOO paragraph |
| Performance Threshold |
Inspect and repair all components listed within the SOO in order to provide fully functional Hush Houses with all repaired components operating as originally designed and repaired in accordance with the standard Hush House configuration.
| SOO section 3 |
| The Government will reject the workmanship or installation quality of the repaired components if one or more major flaws or two or more minor flaws are discovered by Government personnel during final inspections. A major flaw is defined as any inoperable components or systems repaired, or systems/components not repaired in accordance with the standard configuration. A minor flaw is defined as functional and operable systems not fully meeting the standard configuration, as defined by the Hush House drawing package. All major and minor flaws identified during the Government’s final inspection shall be corrected within 7 days of Government disapproval. |
3.0 GENERAL INFORMATION
The standard configurations for the Hush Houses in this document are defined by the Hush House Technical Orders, drawings, and approved engineering change proposals (ECPs) and notices of revision (NORs,) within the Appendix (section 4.0) of this document.
The standard Hush House configuration and original design for all of the T-10 Hush Houses covered in this SOO are defined by the T-10/11 drawing package – top level 8045881 (T-10) and all applicable sub drawings.
3.1 FSS Conversion: The contractor shall install a total flooding agent FSS using 3M Novec 1230 as the extinguishing agent. The FSS shall be functionally equivalent to other Novec FSSs already installed in USAF T-10s. The contractor may propose a new configuration as long as functional equivalency is maintained. Functional equivalency is defined as follows:
· The FSS must interface with the existing Gold Plate Programmable Logic Control (PLC) Facility Control System (FSC)
· The system must be pneumatically actuated
· The system must be designed such that periodic maintenance, such as bottle weighing, agent measurement, and agent agitation, may be performed by the local unit
· Must meet the same performance requirements as currently installed FSSs
· The new Novec 1230 system components must be installed in accordance with approved drawings. The contractor must operationally test the fire suppression system to ensure integration with existing Hush House system doors, alarms, control console, and T20 cab. Two sensing probes will be mounted in the hazard area (engine/aircraft location;) one at 2 ft elevation and one at 6 ft elevation. A full discharge of the fire suppression system shall be conducted. Using Tripoint analyzer used to measuring mixed gas concentration levels, verify concentration levels meet or exceed requirements as identified in 2012 NFPA 2001. Data shall also be compared against data collected during previous tests that established efficacy of 3M Novec 1230, to ensure that concentration levels in the field test are consistent with the results predicted by the scaled tests conducted at 3M laboratories. Concentration data will be collected over a 10 minute period of time to ensure adequate levels are maintained throughout this period.
3.2
Halon Disposal: The contractor shall properly package all Halon and return to DLA.
4.0 APPENDICES
4.1 Air Force Technical Orders (TOs): The following documents are applicable to this PWS to the extent specified herein.
| Tech Order |
| Description |
| Applicable |
| 33D4-6-645-1 |
| Operation and Maintenance Instructions, Enclosed Noise Suppressor System Aircraft/Engine (Hush House), A/F37T-10/11 |
| Entire Technical Order is applicable. |
| 33D4-6-645-4 |
| Illustrated Parts Breakdown, Enclosed Noise Suppressor System Aircraft/Engine (Hush House), A/F37T-10/11 |
| Entire Technical Order is applicable. |
4.2 Air Force Drawings: The T-10 drawings package is defined by the T-10/11 Top Level drawing 8045881 and all subsequent drawings.