FIA2T RFP Questions and Answers

View the file

Other files

File Type Posted
FIA2T_RFP_Questions_and_Answers_20160217r.docx DOCX document
Amend_0004.pdf PDF
FIA2T_RFP_Questions_and_Answers_20160210.docx DOCX document
FIA2T_Section_M_20160202.docx DOCX document
FIA2T_AtchL-11_PastPerf_ClientAuthLtr_20160208.docx DOCX document
FIA2T_AtchL-5_Sample_Task_1_IMSTemplate_20160202.mpp MPP file
FIA2T_AtchL-4_Sample_Task_1_WBSDictionaryTemplate_20160202.xlsx XLSX spreadsheet
FIA2T_Atch_J-7_Section_L_20160208.docx DOCX document
FIA2T_AtchL-13_Cost-Price_V1_20160202.xlsx XLSX spreadsheet
FIA2T_AtchL-10_PastPerfRatingForm_20160202.docx DOCX document
Amend_0003.pdf PDF
FIA2T_AtchL-9_Tailored_FIA2T_EZSource__PPI_Tool_20160208.docx DOCX document
FIA2T_RFP_Questions_and_Answers_20160208.docx DOCX document
FIA2T_Section_L_Admin_Changes_20160127.docx DOCX document
FIA2T_Atch_J-7_Section_L_20160129.docx DOCX document
Amend_002.pdf PDF
FIA2TT_AtchL-4-Sample-Task_1_WBSDictionaryTemplate_20160129.xlsx XLSX spreadsheet
Amend_0001_26_Jan_16.pdf PDF
ppi_tool.accdb —
PPI_Character_Limit.docx DOCX document
FIA2T_AtchL-11_PastPerf_ClientAuthLtr_20160126.docx DOCX document
FIA2T_AtchL-10_PastPerfRatingForm_20160126.docx DOCX document
FIA2T_AtchL-1_GlossaryAcronyms_20150728.docx DOCX document
FIA2T_AtchL-7_Sample_Task_2_PartsScheduleTemplate_20150728.xlsx XLSX spreadsheet
FIA2T_AtchL-12_BOE_RationaleForm_20150728.docx DOCX document
FIA2T_AtchL-2_Offerors_Library_Reference_Table_20150728.xlsx XLSX spreadsheet
FA8307-16-R-0049.pdf PDF
RFP_COver_Letter_20_Jan_16.pdf PDF
FIA2T_AtchL-11_PastPerf_ClientAuthLtr_20150728.docx DOCX document
FIA2T_AtchL-6_Sample_Task_2_ECCCA-ProductionDescription_20150728.docx DOCX document
FIA2T_AtchL-13_Cost-Price_V1_20151006.xlsx XLSX spreadsheet
FIA2T_AtchL-9_Tailored_FIA2T_EZSource__PPI_Tool_20151019.docx DOCX document
FIA2T_AtchL-8_Sample_Task_2_Production_Task_Timeline_20150728.pptx PPTX presentation
FIA2T_AtchL-SB_Sample_Task_for_Set-Aside_20150923.rtf RTF text file
FIA2T_AtchL-3_Sample_Task_1_S-SRD_20150728.docx DOCX document
FIA2T_AtchL-10_PastPerfRatingForm_20150728.docx DOCX document
FIA2T_AtchL-14_SB_Choice_of_Competition_Form_20150915.docx DOCX document
FIA2T_AtchL-5_Sample_Task_1_IMSTemplate_20150728.mpp MPP file
FIA2T_AtchL-4_Sample_Task_1_WBSDictionaryTemplate_20150728.xlsx XLSX spreadsheet
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIA2T RFP FA830716R0049 - Questions and Answers 29 January 2016

Question #
Doc Ref
Question
Answer
1.
FIA2T_AtchL-3_Sample_Task_1_S-SRD_20150728

Section 1.4.1.5, 3.1.1.2.3 The ST1 SRD Sections 1.4.1.5 and 3.1.1.2.3 state that:

1. The UCM unwraps the black Over-The-Air Rekey (OTAR) key using the operational algorithm.

1. The UCM Cryptographic Key Material Input shall provide the signals needed to load a single cryptographically protected key from authorized external source.

1. The UCM only contains the current key it is using to process data.

Will the key encryption key (KEK) be provided through the Cryptographic Key Material Input as part of the keying/rekeying process from the higher assembly?

Sample Task 1 UCM S/SRD provides sufficient description of keying behavior. Implementation specifics are part of potential Offeror's design approach, based on trade-offs in approaches to meet all requirements specified. Descriptive rationale for trade-offs (required in Section L of the RFP) should include rationale behind trade-offs in cryptographic key material input based on other design parameters in the design approach.

2.
FIA2T_AtchL-3_Sample_Task_1_S-SRD_20150728

Section 3.1.2.2 The ST1 SRD Section 3.1.2.2 states:

· The UCM package size shall not exceed 40 x 40 mm

We are assuming this is the measurement for the ceramic package or perhaps the pin layout dimensions and not the final package footprint size on a circuit card. Is this assumption correct?

Offeror must interpret the requirements of the RFP using his best judgment and knowledge of relevant industry terms and methods.

3.
FIA2T_AtchL-3_Sample_Task_1_S-SRD_20150728

Section 1.4.1.5 The ST1 SRD Sections 1.4.1.5 state:

1) The UCM unwraps the black Over-The-Air Rekey (OTAR) key using the operational algorithm.

May we assume the operational algorithm refers to the AES algorithm and contains the information and ability to decrypt and extract the encryption key?

The operational algorithm refers to the AES algorithm. However, any assumptions about the specific functions of the algorithm are part of potential Offeror's design approach, based on trade-offs in approaches to meet all requirements specified. Descriptive rationale for trade-offs (required in Section L of the RFP) should include rationale behind trade-offs in operational aspects based on other design parameters in the design approach.

4.
FIA2T_AtchL-7_Sample_Task_2_PartsScheduleTemplate_20150728
Several line items in Sample Task 2, parts schedule are obsolete and unavailable. Will the Government please confirm offerors can submit alternate parts numbers that are 100% compatible?
Offerors can submit alternate part numbers, providing substantiating justification for doing so and that the existing parts are unavailable.
5.
FIA2T_AtchL-7_Sample_Task_2_PartsScheduleTemplate_20150728
Will the Government allow the offerors to include additional columns of information typically included in BOMs, such as Total Quantity Needed for Production, Alternate Part Number, Notes, etc.
Offerors may include additional columns as necessary to fulfill the requirements and justification indicated for the sample task.
6.
L.1.5
In L.1.5,

Para (5) states:

The proposal shall provide cross-referencing between volumes.

Para (6) states Each volume shall be written on a stand-alone basis so that its contents may be evaluated without cross-referencing to other volumes of the proposal.

Para (7) states Each response to each subfactor shall be self-contained. No cross-referencing between subfactor responses is allowed.

Para (5) and (6) are contradictory while Para (7) is in agreement with Para (6).

Question:Please clarify if cross referencing is requested or disallowed.

Each volume and each response to subfactors shall be self-contained, without requiring the reader to actually go to a different volume/subfactor. However, cross-referencing is requested to indicate content that are duplicated for these self-containment purposes, with their locations.

7.
L.3.3.2 & L.3.3.3
In section L, L.3.3.2. Sample Task 2 Schedule Constraints

Offeror shall plan final delivery of ECCCA quantity specified in (1) nine (9) months from the planning start date indicated in Section L.3.1.3. Assume receipt of all parts prior to planning start date. An alternative final delivery schedule may be proposed if sound rationale for the delivery schedule is provided by Offeror.

While in L 3.3.3

(2) Provide a delivery schedule associated with each part in the Bill of Materials (BOM), along with the open source confirmation of availability of said part. Identify the ten (10) items with the longest lead times. Schedule shall state the total time from part order to part delivery from supplier. All parts shall be considered as not on hand by the Offeror. The Offeror shall fill in the template provided in (2)

Question:

L.3.3.2 requires that all parts are on hand prior to 1 January 2017 the assumed start date of Sample Task 2. while L.3.3.3 specifies providing a delivery schedule for the parts on the BOM. Is the assumption that providing an alternative delivery schedule (L.3.3.2) with appropriate rationale will suffice to remove the contradiction between strict following of these two paragraphs?

No. The two schedules are not dependent on each other. For L.3.3.2. the parts are considered on hand and the schedule is for the production. For L.3.3.3., the schedule is simply an exercise with regard to parts obtainment and does not have bearing on L.3.3.2. schedule for production, since all parts are to be considered as on hand for that. Treat the schedule answer to L.3.3.3. as separate from L.3.3.2.

8.
RFP Cover Letter & L.3.1.3
The RFP Cover letter specifies an anticipated award date of 19 January 2017, while the RFP states in Section L:

L.3.1.3. Sample Tasks Start Date for Planning Schedule planning for all Sample Tasks shall assume a start date of 1 January 2017. This parameter has been included in all schedule related templates.

Question: While it is understood that the Sample Tasks are notional, will the sample task start date be adjusted in the RFP so as to begin after contract award?

No. The anticipated award date of the RFP and the sample tasks start date are not related. The 1 January 2017 sample tasks start date is used for convenience.

9.
RFP Cover Letter
The RFP Cover Letter specifies a process for requesting copies of sensitive GFI, with requests due by 25 January 2016… Delivery address to accept sensitive or classified information GFI will be delivered within 5 working days after request.

Offeror submitted its signed request 01/22/15, but has not received an acknowledgment of the request.

Question: Would the Government be able to provide an estimated schedule for providing the requested documents to Offerors since those documents may be used in the Offeror’s proposal response? If there is a delay due to weather events on the East Coast, will the Government extend the response due date?

The PCO will acknowledge receipt of the request for GFI with the potential offeror. A verification to receive sensitive GFI will be accomplished with the offeror, then the documents are provided.

With respect to weather delays and RFP extension, that would be contingent the circumstance closer to the proposal due date.

10.
RFP Cover Letter & L.1.1
RFP Cover Letter: In accordance with FAR 15.201(f), after release of the solicitation, the Contracting Officer is the sole focal point for any exchange with potential offerors. Therefore, all correspondence related to FIA2T RFP will be addressed to the undersigned at ralph.urias@us.af.mil.

L.1.1. The contracting officer (CO) is the sole point of contact for this acquisition.

Question: Does the Government wish for Offerors to continue to copy Ms. Hattie Peay, Contract Specialist, on questions, concerns or other communication submitted to the CO via email as in earlier versions of the draft RFP (for redundancy) or should we submit only to the CO going forward?

Government requests Offerors continue to copy Ms. Hattie Peay on all correspondence to the PCO.

11.
L.2.4, L.2.7, L.7.1, L.7.2.2, L.7.6.13
Multiple references to teaming agreement partners, subcontractors, major subcontractors without inclusion of these terms in the definitions.

L.7.2.2 Separate Cost/Price Volumes, including cost formats (see Microsoft Excel workbook referenced at Section L.7.6.13) for FIA2T Sample Tasks shall be submitted by each major subcontractor and interdivisional transfer (IDT) (including subsidiaries) that exceeds a dollar threshold of 10 percent of the overall effort. Various undefined terms have been included without specific guidance on what is intended by their inclusion.

Question:

If we have other sister divisions of our company participating with us on FIA2T effort (or potentially future efforts) should each division submit a FFP Rate Table (inclusive of fee) AND their own escalation rate?

What specifically does the Government mean by “10 percent of the overall effort”? In asking, we would like to confirm that the Government is NOT requiring that Offerors include proposed “teaming arrangement partners’”, and/or “subcontractors” (as opposed to “major subcontractors”) submit detailed rate information unless they are proposed to perform more than 10% of the overall effort as opposed to 10% of the effort on either sample task order. Please confirm what the Government means by “overall effort” and any required distinction between teaming arrangement partners and subcontractors.

Can our subs have a different escalation rate than the Offeror?

Yes, if your company has a sister division or subcontractor that is participating in FIA2T effort or potentially future efforts, each division should submit an FFP Rate Table (inclusive of profit) and their own escalation rate.

The Government intends no distinction made between teaming arrangement partners and subcontractors, either major or minor. All usage of businesses or divisions/subsidiaries other than that of the Offeror that results in 10% or more of the effort on EITHER sample task shall include detailed rate information.

The Government is NOT requiring Offerors include proposed teaming arrangement partners as part of the proposals.

“10% of the overall effort” refers to 10% of the total proposed price of the sample task.

Subcontractors may have different escalation rates than the offeror.

12.
FIA2T Section L Volume 2-A. para. L.4.3 and L.4.4
For the Small Business Set Aside, is the CMMI - ISO 9001 - or SAE AS9100C required for the small business participants under the Small Business Set Aside
These certifications requirements are not applicable to the SB Set-aside.
13.
FIA2T_AtchL-4_Sample_Task_1_WBSDictionaryTemplate_20150728.xlsx

Para 1.1.2 According to line item 1.1.2 of the sample WBS file (FIA2T_AtchL-4_Sample_Task_1_WBSDictionaryTemplate_20150728.xlsx), there's a reference to satisfying "the FIPS 140-2, Security Level 4 requirements". Should the reference to FIPS 140-2 in the WBS file be changed to NSA Type 1?

Answer: Yes, the reference to FIPS 140-2 should instead refer to NSA Type 1 requirements.

14.
FIA2T Atch L-6 Task 2 ECCCA

Production Description, Attachment L-2, GPE and GFI (Page 2) According to Sample Task 2 - ECCCA-Production Description, "Sample Task #2 consists in producing a cryptographic CCA from an overall parts list and top level drawings to meet the production requirements for this kind of item".

There's also a reference to Source files (schematics, Gerber, etc. in all relevant formats and tool setup) being provided as GFI.

Does the Govt. intend to provide Source files / top level drawings in support of Sample Task 2?

The GFI is referenced for pricing purposes only (so the Offeror does not price the task as if they had to build the layout themselves), but the GFI will not actually be provided. The Offeror must work with what is provided to estimate a price based on the parts and the board size, making reasonable judgments about layout complexity.

15.
Section M Para 3.2 (1)
Our understanding is that the government is requesting the Offeror to provide a sound and substantiated design approach in our response. Section M3.2 (1) requests substantiation that our design meet all the requirements as stated in the UCM Systems/Security Requirements Document. Will a proposed description of the design approach (containing the steps, processes, procedures, and data to ensure that all requirements are met) be sufficient to meet the evaluation criteria? Note that FIA2T Section L Attachment L-3, Sample Task 1- S/SRD - Table 4 1 Requirements Verification Cross Reference Matrix, implies that successful requirements fulfillment will require verification and validation of the actual device as noted in the SRD.
Offeror must use his best judgment when determining what will substantiate and provide a sound approach to the requirements of the RFP, within the stated page limits.

This is a fictional task and no prototype should be built. All requirements are stated for the Offeror to propose to meet with a design approach. No actual device verification by the Offeror is meant to be implied by the requirements.

16.
FOUO

Documents, IASRD page 21

The IASRD has sections 20 and 21 listed twice with removal of section 22 at the very end of the document (pages 21,22). Just wanted to confirm that this was correct for the final release as it differs from the previously released version.
Page 21 should be ignored.

The difference between previously released and the final version, other than admin changes, was the removal of section 22 and of TEM-2 of Section 20.

17.

The RFP references the EVMS requirements under FAR 52.234-02, 52.234-03, DFAR 252.234-7001 (Deviation), 252.234-7001, 252.234-7002 (Deviation), and 252.234-7002. Since the proposal will be less than $100 million there is a conflict in the requirements between the FAR and DFAR clauses. If a contractor or subcontractor currently does not have an ANSI/EIA-748 fully compliant EVMS system, do they need to submit a plan for compliance in the proposal per the FAR clauses or does the DFAR clause 252.234-7002 apply and a plan is not required.

A plan would only apply at the DO/TO if the value of the effort is above the $100 Million threshold.