Atch L-4 - WBS Dictionary Template

View the file

Other files

File Type Posted
FIA2T_RFP_Questions_and_Answers_20160217r.docx DOCX document
Amend_0004.pdf PDF
FIA2T_RFP_Questions_and_Answers_20160210.docx DOCX document
FIA2T_Section_M_20160202.docx DOCX document
FIA2T_AtchL-11_PastPerf_ClientAuthLtr_20160208.docx DOCX document
FIA2T_AtchL-5_Sample_Task_1_IMSTemplate_20160202.mpp MPP file
FIA2T_AtchL-4_Sample_Task_1_WBSDictionaryTemplate_20160202.xlsx XLSX spreadsheet
FIA2T_Atch_J-7_Section_L_20160208.docx DOCX document
FIA2T_AtchL-13_Cost-Price_V1_20160202.xlsx XLSX spreadsheet
FIA2T_AtchL-10_PastPerfRatingForm_20160202.docx DOCX document
Amend_0003.pdf PDF
FIA2T_AtchL-9_Tailored_FIA2T_EZSource__PPI_Tool_20160208.docx DOCX document
FIA2T_RFP_Questions_and_Answers_20160208.docx DOCX document
FIA2T_Section_L_Admin_Changes_20160127.docx DOCX document
FIA2T_RFP_Questions_and_Answers_20160127.docx DOCX document
FIA2T_Atch_J-7_Section_L_20160129.docx DOCX document
Amend_002.pdf PDF
FIA2TT_AtchL-4-Sample-Task_1_WBSDictionaryTemplate_20160129.xlsx XLSX spreadsheet
Amend_0001_26_Jan_16.pdf PDF
ppi_tool.accdb —
PPI_Character_Limit.docx DOCX document
FIA2T_AtchL-11_PastPerf_ClientAuthLtr_20160126.docx DOCX document
FIA2T_AtchL-10_PastPerfRatingForm_20160126.docx DOCX document
FIA2T_AtchL-1_GlossaryAcronyms_20150728.docx DOCX document
FIA2T_AtchL-7_Sample_Task_2_PartsScheduleTemplate_20150728.xlsx XLSX spreadsheet
FIA2T_AtchL-12_BOE_RationaleForm_20150728.docx DOCX document
FIA2T_AtchL-2_Offerors_Library_Reference_Table_20150728.xlsx XLSX spreadsheet
FA8307-16-R-0049.pdf PDF
RFP_COver_Letter_20_Jan_16.pdf PDF
FIA2T_AtchL-11_PastPerf_ClientAuthLtr_20150728.docx DOCX document
FIA2T_AtchL-6_Sample_Task_2_ECCCA-ProductionDescription_20150728.docx DOCX document
FIA2T_AtchL-13_Cost-Price_V1_20151006.xlsx XLSX spreadsheet
FIA2T_AtchL-9_Tailored_FIA2T_EZSource__PPI_Tool_20151019.docx DOCX document
FIA2T_AtchL-8_Sample_Task_2_Production_Task_Timeline_20150728.pptx PPTX presentation
FIA2T_AtchL-SB_Sample_Task_for_Set-Aside_20150923.rtf RTF text file
FIA2T_AtchL-3_Sample_Task_1_S-SRD_20150728.docx DOCX document
FIA2T_AtchL-10_PastPerfRatingForm_20150728.docx DOCX document
FIA2T_AtchL-14_SB_Choice_of_Competition_Form_20150915.docx DOCX document
FIA2T_AtchL-5_Sample_Task_1_IMSTemplate_20150728.mpp MPP file
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIA2T Sample Task 1 WBS

FA8307-16-R-0049 FIA2T Section L Attachment L-4 - WBS Dictionary Template 28 July 2015
Instructions:

Complete table by providing Level 4 and Level 5 WBS elements, as appropriate, based on Offeror's proposed design approach and applicable certified processes for FIA2T-Unlimited Sample Task 1. Elements must be consistent with MIL-STD-881C, DEPARTMENT OF DEFENSE STANDARD: WORK BREAKDOWN STRUCTURES (WBS) FOR DEFENSE MATERIEL ITEMS (03-OCT-2011) instructions and higher level WBS elements as defined herein.

Offeror shall provide unique WBS # consistent with provided numbering scheme, a descriptive title and a detailed definition sufficient for the Government to understand the unique work associated to the element, its relation to higher level WBS level and its difference from other elements at the same hierarchical level. Offeror may insert rows into table as necessary to be consistent with their design approach and accounting system. All WBS elements must be consistent and traceable to summary tasks within Offeror's proposed IMS.

WBS #Level 1Level 2Level 3Level 4Level 5Definition
1Sample Task 1 - Universal Cryptographic Module (UCM) Development and CertificationThe complex of equipment (hardware/software), test and evaluation, and security validation required to develop, verify/qualify and validate an electronic cryptographic module, aka the Universal Cryptographic Module (UCM), capability that will be embedded into data communications subsystems of fixed (both permanent and transportable) and mobile (i.e., human-portable, vehicular, ship-borne, airborne, and space-borne) platforms requiring security for mission data communications links. The electronic cryptographic module's performance, physical and security requirements are defined in the System and Security Requirements Document (S/SRD) for Sample Task 1 UCM.
1.1UCM Design and DevelopmentThe direct labor associated with the hardware, software and documentation associated with design and development of performance, physical and and security features/functions of a complete UCM (i.e., the prototype configured unit(s) which satisfy UCM requirements defined in the S/SRD for Sample Task 1). This WBS element includes the design and development of complete UCMs (i.e., the prototype or operationally configured units, which satisfy the requirements of their applicable specifications, regardless of end use) and is comprised of the sub element activities listed below.

Includes, for example:

a. All integration, assembly, test and checkout, as well as all technical activities associated with individual hardware/software elements

b. Integration test preparations, conduct and teardown and review, analysis and documentation of integration results.

c. All whole and partial prime contractor, direct labor for breadboards, brass boards, and qualification test units

d. Design trade analyses, risk mitigation, and design specification activities, including documentation, of the UCM development

Excludes, for example:

a. "Less than whole" units (e.g., test, spares, etc.) consumed or planned to be consumed in support of UCM Design and Development

b. Factory special test equipment and special tooling required to fabricate UCM components

c. Component, subassembly, test fixtures materials

1.1.1UCM Performance Design and DevelopmentThe direct labor associated with performance and physical features/functions design and development of a complete UCM (i.e., the prototype configured unit(s)), which satisfy UCM requirements defined in the S/SRD for Sample Task 1) as well as design trade analyses and documentation of the UCM physical features/functions design.
[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]
1.1.2UCM Security Design and DevelopmentThe direct labor associated with security features/functions design and development of a complete UCM (i.e., the prototype configured unit(s)), which satisfy the FIPS 140-2, Security Level 4 requirements as well as design trade analyses and documentation of the UCM security features/functions design.
[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]
1.1.3UCM Microelectronic Component(s)The non-recurring engineering services and supplies contracted by the prime for the UCM active hardware component (e.g., Integrated Circuit, Programmable Logic Device or Multi-Chip Module). This WBS element includes fabrication design and/or delivery of UCM active component (i.e., the prototype or operationally configured units, which satisfy the requirements of their applicable specifications, regardless of end use) and is comprised of the sub element activities listed below.

Includes, for example:

a. All whole and partial subcontractor, and vendor labor and/or supplies for breadboards, brass boards, proof of design, and/or qualification test units

Excludes, for example:

a. "Less than whole" units (e.g., test, spares, etc.) consumed or planned to be consumed in support of UCM Design and Development

b. Factory special test equipment and special tooling required to fabricate UCM components

c. Component, subassembly, test fixtures materials

[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]
1.2UCM Test and EvaluationThe direct labor and/or testing services associated with conducting performance and security qualification/verification and security validation testing of complete UCM prototype unit(s) in accordance with, but not limited to:

- MIL-STD-883J, Change 5 Draft,

- Derived Test Requirements for FIPS 140-2, Draft, and

- National Information Assurance Partnership (NIAP) Common Criteria

Includes, for example:

a. All, where applicable: models, tests and associated simulations, covering such areas as:

1. UCM embedment integration/interoperability;

2. performance and design margin verfication;

3. security threat evaluation;

4. operating life; and,

5. environmental effects

b. All whole and partial prime contractor, subcontractor, and vendor direct labor for test preparations, conduct and teardown and review, analysis and documentation of qualification/verification and validation test results.

Excludes, for example:

a. UCM test units consumed or planned to be consumed in support of UCM development/qualification and security validation testing

b. Special test equipment, fixtures and facilities required to perform qualification/verification and security validation testing

c. All formal and informal testing which can be associated with the lower level UCM hardware/software element integration acceptance testing

1.2.1UCM Performance Development/Qualification TestingThe direct labor associated with modeling, tests and simulations conducted to qualify/verify UCM performance features/functions, design margins, interfaces and interoperations specified in the S/SRD for Sample Task 1.
[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]
1.2.2UCM Cryptographic Module Validation TestingThe direct labor and/or testing services associated with security validation testing of a complete UCM in accordance with Derived Test Requirements for FIPS 140-2, Draft, and National Information Assurance Partnership (NIAP) Common Criteria at Evaluation Assurance Level 7 (EAL7) as well as NIST review, analysis and documentation for validation certification.
[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]
1.3UCM Program Management and Quality AssuranceThe direct labor for UCM Design, Development, Test and Evaluation, and, Certification associated with the business and administrative planning, organizing, directing, coordinating, controlling, and approval actions designated to accomplish overall program objectives, which are not associated with specific hardware elements and are not included in systems engineering with the exception of efforts related to the quality assurance program.

Includes, for example:

a. Cost, schedule, performance measurement management, warranty administration, contract management, data management, vendor liaison, subcontract management, etc.

b. Systems Engineering efforts associated with quality assurance program

1.3.1 UCM Program Management The direct labor associated with the business and administrative planning, organizing, directing, coordinating, controlling, and approval actions designated to accomplish overall program objectives, which are not associated with specific hardware elements and are not included in systems engineering.

Includes, for example:

a. Cost, schedule, performance measurement management, warranty administration, contract management, data management, vendor liaison, subcontract management, etc.

[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]
1.3.2UCM Quality AssuranceThe direct labor systems engineering efforts associated with quality assurance program.

Includes, for example:

a. Quality planning and control

[offeror enter WBS Level 4 number here][offeror enter Level 4 Title here][offeror enter Level 4 Definition here]
[offeror enter WBS Level 5 number here][offeror enter Level 5 Title here][offeror enter Level 5 Definition here]