ISC Section L Attachment 3 - Past Performance Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Integration Support Contract, newest first.
File Type Posted
FA821412R0001_______0004.pdf PDF
FA8214-12-R-0001-0003.pdf PDF
ISC Q A 6.pdf PDF
ISC Q A 5.pdf PDF
ISC PWS Rev 01.docx DOCX document
Section K - Attachment 1.docx DOCX document
FA8214-12-R-0001-0002.pdf PDF
CDRLs 10 Feb.pdf PDF
ISC DD 254-01.pdf PDF
FA8214-12-R-0001-0001.pdf PDF
Fixed-Price Labor Hour Rate Matrix Rev 01.xlsx XLSX spreadsheet
Corrected CDRLs.pdf PDF
CLIN Pricing Matrix Rev 01.xlsx XLSX spreadsheet
ISC Q A 4.pdf PDF
ISC Q A 3.pdf PDF
ISC Q A 2.pdf PDF
ISC Questions and Answers 1.pdf PDF
Section L ATTACHMENT 1 PPIS.docx DOCX document
Section L ATTACHMENT 4 Consent Form.doc DOC document
ISC Consolidated GFP List.xlsx XLSX spreadsheet
Section L ATTACHMENT 7 - Cross Reference Matrix.xlsx XLSX spreadsheet
CDRL Package Final 20Dec11 reduced file size.pdf PDF
CLIN Pricing Matrix.xlsx XLSX spreadsheet
Fixed-Price Labor Hour Rate Matrix.xlsx XLSX spreadsheet
ISC DD254.pdf PDF
ISC PWS Draft 20120109 final.docx DOCX document
Section L ATTACHMENT 5 Commercial Client Authorization.doc DOC document
Section L ATTACHMENT 2 Quest Cover Letter.doc DOC document
FA821412R0001.pdf PDF
ISC Problem Only 5Jan2012.docx DOCX document
Labor Category Descriptions.docx DOCX document
Section L ATTACHMENT 6 Roles Responsibilities.xlsx XLSX spreadsheet
FISAC Bidders Library Update Posted 20111215.docx DOCX document
Excerpt from ISC Section L with ramp-up.docx DOCX document
Fixed-Price Labor Hour Rate Matrix.xlsx XLSX spreadsheet
FISAC Mix Adjustment Clause Draft.docx DOCX document
Labor Category Descriptions.docx DOCX document
CLIN Pricing Matrix.xlsx XLSX spreadsheet
Draft ISC Fixed-Price Labor Hour Rates Worksheet_Posted 20111121.pdf PDF
Draft ISC RFP FA821412R0001_Posted 20111121_1.pdf PDF
Draft ISC Section L Attachments Consolidated_Posted 20111121.pdf PDF
Draft ISC CDRL Package_Posted 20111121.pdf PDF
FBO_blurb_on_Data_Library_Posted 20111121.docx DOCX document
Draft ISC PWS Dated 18 Nov_Posted 20111121.pdf PDF
Draft ISC Fixed-Price Labor Hour Rates.pdf PDF
Draft ISC CDRL Package Revised 8 Nov 2011.pdf PDF
Draft ISC RFP FA821412R0001.pdf PDF
Draft ISC RFP FA821412R0001.pdf PDF
FBO_blurb_on_Data_Library_-_Posted_21_Nov_2011.docx DOCX document
Draft ISC PWS 2011118.pdf PDF
Show all 50

Integration Support Contract has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 3

PAST PERFORMANCE QUESTIONNAIRE

Offeror: Complete Section 1, then e-mail questionnaire to the customer points of contact listed on the Past Performance Information Sheet.

Offeror’s Evaluator: Complete Sections 2-5 and e-mail to: Kirk.Dean@hill.af.mil and David.Lovett@hill.af.mil .

DO NOT PROVIDE A COPY BACK TO THE OFFEROR.

When filled in, this document is source selection sensitive information IAW FAR 2.101 and 3.104.

SECTION 1: CONTRACT IDENTIFICATION

A. Contractor:

B. Cage Code of contractor contract was awarded to:

C. Contract number:

D. Contract type:

E. Was this a competitive contract? Yes _____ No _____

F. Period of performance:

G. Initial contract cost:

H. Current/final contract cost:

I. Reasons for differences between initial contract cost and final contract costs: (enter below) J. Description of service provided (enter below):

SECTION 2: CUSTOMER OR AGENCY IDENTIFICATION

A. Customer or agency name:

B. Customer or agency description (if applicable):

C. Geographic description of services under this contract (enter below)

Local_____ Nationwide_____ Worldwide_____ Other Command(s) _____

SECTION 3: EVALUATOR IDENTIFICATION

A. Evaluator's name:

B. Evaluator's title:

C. Evaluator's phone/fax number:

D. Number of years evaluator worked on subject contract:

SECTION 4: EVALUATION

1. Please indicate your satisfaction with the contractor’s performance by placing an “X” in the appropriate block using the scale provided to the right of each question. This scale is defined as follows:

CODE

PERFORMANCE LEVEL

B BLUE/EXCEPTIONAL - The contractor’s performance meets contractual requirements and exceeds many (requirements) to the Government’s benefit. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

P PURPLE/VERY GOOD- The contractor’s performance meets contractual requirements and exceeds some (requirements) to the Government’s benefit. The contractual performance was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

G GREEN/SATISFACTORY – The contractor’s performance meets contractual requirements. The contractual performance contained some minor problems for which corrective actions taken by the contractor appear or was satisfactory.

Y YELLOW/MARGINAL – Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

R RED/UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

N NOT APPLICABLE - Unable to provide a score

Technical Performance (General)
B
P
G
Y
R
N

T1. Ability to support Weapon System Sustainment.

T2. Ability to support System Engineering & Integration (SE&I)

T3. Ability to maintain configuration control and baseline management.

T4. Ability to maintain adequate tools and internal practices to effectively plan, execute, track, and report on test, evaluation and other activities.

T5. Demonstrated the technical capabilities and expertise required in the contract.

T6. Ability to deliver accurate technical data packages and Technical Orders, effectiveness in performing Data Management

T7. Ability to identify and handle Diminishing Manufacturing Sources and Material Shortages (DMSMS) issues.

Technical Performance (Systems Engineering)
B
P
G
Y
R
N

T8. Overall effectiveness in performing Program Schedule Management.

T9. Overall effectiveness in performing Acquisition Program Documentation Preparation

T10. Overall effectiveness in performing Program Risk Management

T11. Overall effectiveness in performing Strategic Planning

T12. Overall effectiveness in performing Earned Value Management

T13. Overall effectiveness in performing Quality Assurance

T14. Overall effectiveness in performing Logistics Planning

T15. Overall effectiveness in performing Manufacturing and Production Support

T16. Overall effectiveness in performing Business and Financial Management

T17. Overall effectiveness in performing Systems Engineering and Integration for Modification and Replacement Programs

T18. Overall effectiveness in performing Test Support

T19. Overall effectiveness in development and implementation of training materials

T20. Ability to effectively transition responsibilities and functions

Program Management
B
P
G
Y
R
N

P1. Effectiveness of overall contract management (including ability to effectively lead, manage, and control the program).

P2. Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes).

P3. Ability to understand/comply with customer objectives and technical requirements.

P4. Effectiveness of material management (including Government Furnished Property or Material).

P5. Contractor proposed alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the customer.

P6. Ability to meet contract schedule

P7. Contractor was cooperative/successful dealing with other contractors (through an ACA) that weren’t subcontractors

Organization, Staff & Subcontractor Management
B
P
G
Y
R
N

O1. Ability to hire a qualified workforce for this effort.

O2. Ability to retain a qualified workforce on this effort.

O3. Contractor effectiveness in maintaining continuity of mission support while transitioning/ phasing in resources and personnel to support other efforts.

O4. Effective management of its subcontractors/ teaming partners

Small and Small Disadvantaged Business Participation
B
P
G
Y
R
N

S1. Ability to meet or exceed small business and small disadvantaged business goals set forth in the approved subcontracting plan

S2. Ability to effectively manage small business participation to meet technical performance.

Cost Performance
B
P
G
Y
R
N

C1 Accuracy in forecasting contract costs

C2 Ability to meet forecasted costs and perform within contract costs

C3 Ability to alert Government of unforeseen costs before they occur

C4 Sufficiency and timeliness of cost reporting

2. Please discuss each and every response for which you indicated B/E (Blue/Exceptional), Y/M (Yellow/Marginal), or R/U (Red/Unsatisfactory) in response to the questions above (use additional sheets, if necessary).

3. Government Contracts Only: Has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations?

Yes___ Default___ Convenience___ Pending Terminations___ No ___

If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules, etc).

SECTION 5: OVERALL PERFORMANCE SUMMARY

1. Describe the contractor’s greatest strong points in the performance of the contract.

2. Describe the contractor’s greatest shortcomings in the performance of the contract.

3. Would you have any reservations about soliciting this contractor in the future or having them perform one of your critical and demanding programs?

Yes ____ No ____ (If yes, provide details/comments)

Evaluator’s Signature

Date

Thank you for your prompt response and assistance!

Please e-mail this completed questionnaire to: Kirk.Dean@hill.af.mil and David.Lovett@hill.af.mil .

Questions or Comments can be directed to Kirk.Dean@hill.af.mil at (801) 777-5668 or David.Lovett@hill.af.mil at (801) 777-5956.

File details come from the government source that posted it. Updated .