ISC Questions and Answers 1.pdf

PDF 189 KB Posted

Attached to
Integration Support Contract Federal contract opportunity
Solicitation number
FA8214-12-R-0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Integration Support Contract, newest first.
File Type Posted
FA821412R0001_______0004.pdf PDF
FA8214-12-R-0001-0003.pdf PDF
ISC Q A 6.pdf PDF
ISC Q A 5.pdf PDF
FA8214-12-R-0001-0002.pdf PDF
CDRLs 10 Feb.pdf PDF
ISC PWS Rev 01.docx DOCX document
Section K - Attachment 1.docx DOCX document
ISC DD 254-01.pdf PDF
CLIN Pricing Matrix Rev 01.xlsx XLSX spreadsheet
FA8214-12-R-0001-0001.pdf PDF
Fixed-Price Labor Hour Rate Matrix Rev 01.xlsx XLSX spreadsheet
Corrected CDRLs.pdf PDF
ISC Q A 4.pdf PDF
ISC Q A 3.pdf PDF
ISC Q A 2.pdf PDF
Section L ATTACHMENT 1 PPIS.docx DOCX document
Section L ATTACHMENT 4 Consent Form.doc DOC document
ISC Consolidated GFP List.xlsx XLSX spreadsheet
Section L ATTACHMENT 2 Quest Cover Letter.doc DOC document
FA821412R0001.pdf PDF
ISC Problem Only 5Jan2012.docx DOCX document
Labor Category Descriptions.docx DOCX document
Section L ATTACHMENT 6 Roles Responsibilities.xlsx XLSX spreadsheet
Section L ATTACHMENT 7 - Cross Reference Matrix.xlsx XLSX spreadsheet
CDRL Package Final 20Dec11 reduced file size.pdf PDF
Section L ATTACHMENT 3 Questionnaire20110808.doc DOC document
CLIN Pricing Matrix.xlsx XLSX spreadsheet
Fixed-Price Labor Hour Rate Matrix.xlsx XLSX spreadsheet
ISC DD254.pdf PDF
ISC PWS Draft 20120109 final.docx DOCX document
Section L ATTACHMENT 5 Commercial Client Authorization.doc DOC document
FISAC Bidders Library Update Posted 20111215.docx DOCX document
Excerpt from ISC Section L with ramp-up.docx DOCX document
Labor Category Descriptions.docx DOCX document
CLIN Pricing Matrix.xlsx XLSX spreadsheet
Fixed-Price Labor Hour Rate Matrix.xlsx XLSX spreadsheet
FISAC Mix Adjustment Clause Draft.docx DOCX document
Draft ISC Fixed-Price Labor Hour Rates Worksheet_Posted 20111121.pdf PDF
Draft ISC RFP FA821412R0001_Posted 20111121_1.pdf PDF
Draft ISC Section L Attachments Consolidated_Posted 20111121.pdf PDF
Draft ISC PWS Dated 18 Nov_Posted 20111121.pdf PDF
Draft ISC CDRL Package_Posted 20111121.pdf PDF
FBO_blurb_on_Data_Library_Posted 20111121.docx DOCX document
Draft ISC Fixed-Price Labor Hour Rates.pdf PDF
Draft ISC CDRL Package Revised 8 Nov 2011.pdf PDF
Draft ISC RFP FA821412R0001.pdf PDF
Draft ISC Section L Attachments Consolidated.pdf PDF
Draft ISC RFP FA821412R0001.pdf PDF
FBO_blurb_on_Data_Library_-_Posted_21_Nov_2011.docx DOCX document
Show all 50

Integration Support Contract has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ISC RFP Questions and Answers #1

ID Doc Page # Para # Line # Question / Comment Suggested Resolution Response

1 RFP Section

"B"

Pages 3, 4, 6, 8, and 12 (plus options)

CLIN 0001, 0020,

0040AC, 0040AG,

0101 (plus options)

Multiple Two places in the RFP indicate that Contractor Manpower Equivalents

(CMEs) are "estimated" by each bidder, however a third area refers to

“requested” CME’s indicating the number is fixed for all bidders.

Reference 1: Section B, CLINs 0001, 0020, 0040AC, 0040AG, and 0101 (plus options) state “Estimated CMEs" multiplied by 1,920 hours equal the "Total

Man Hours Per Year”. (underline added)

Reference 2: Section L, Subsection 6.6 states table is “for informational purposes only” with the “Government’s estimated CMEs required for each functional support category” and “is to serve as a guide to enable the contractor to scope the total effort and provide the optimal skill level and labor category mix required to effectively accomplish the required support.”

(underlines added)

Reference 3: RFP Attachment - CLIN_Pricing _Matrix.xlsx, Instruction 4 states “Total hours should reconcile with the requested CME’s X 1,920 by

CLIN”. (underline added)

Please clarify that the Total Man Hours Per Year and number of CMEs bid are fixed in Section B of the RFP and in the CLIN Pricing Matrix attachment.

The number of CMEs at the CLIN level which equate to the Total Man Hours Per Year are fixed. The estimated number of individuals within each functional support category is provided to help the contractor bid the optimal skill level and labor category mix to meet the requirement.

2 RFP Section

"L"/ Model

Contract

130-131 7.3 N/A The draft RFP, Section 7.3.4 "Attachments to the Solicitation/Model

Contract" had the requirement to provide the DD254 as well as CDRLS. This section has been removed in the final RFP. Is it the AF's intent for offerors to provide the DD254 and CDRLS in their proposals?

Please clarify, to ensure bidders provide CDRLs and

DD254 to the AF with their proposal. If it is the intent for Offerors to provide the CDRLs in their offering, please provide the document in Word or a pdf. version created from the native file. This will enable the

Offeror to complete boxes 17 and 18. In the alternative, please relive the requirement that the

CDRLs be submitted in a Word document.

The Government provided the DD Form 254 and

CDRL listing to the offeror in the final RFP posting.

This paragraph was deleted from Section L intentionally. The offerors will not need to provide copies of the DD254 or the CDRLs in their proposal.

3 PWS 79 - 80 4.11.3.1 and

4.11.3.2

3149, 3160 Minimum required engineering staff experience levels in PWS paragraphs

4.11.3.1 and 4.11.3.2 is ambiguous regarding the percent of personnel with under 10 years ICBM experience and requires clarification.

Recommend that the PWS paragraphs 4.11.3.1, and

4.11.3.2 on % experience be reworded for clarity:

"25% of the Engineering staff shall have 10+ years

ICBM weapon system experience, another 50% of the engineering staff shall have 5+ years ICBM weapon system experience, and the remaining 25% may have less than 5 years ICBM weapon system experience."

If you count a guy with 10 years experience in your 10+ year category, he can't be counted in the 25% 5+ years category unless you have already satisfied your requirements for 10+ years. Same applies for the less than 5 years category.

4 RFP

Schedule/

Section B

3 CLIN 0001 N/A Is it the AF's intent that the base year CLINs have a 9.5 month POP to align with fiscal year boundaries with the ISC period of performance (POP) estimated to begin 15 December 2012? If the AF intends that the base year be less than 12 months, there is a discrepancy between the number of hours listed on each CLIN (0001, 0020, 0040AC, 0040AG, and 0101) and the partial year POP.

Clarify that the AF's intent is to have offerors bid to the 9.5 month POP for the first year. Modify CME to be equal to 1520 hours in CLINs 0001, 0020, 0040AC, 0040AG, and 0101. This approach is consistent with how the AF modified the CME definitions in the final option year.

The 15 December 2012 is an estimated award date and could be subject to change. The TEP will be based on 12 months and offerors should propose to the 12 months. These CLINs may need to be adjusted at time of contract award.

5 DD254 Page 1 of the

DD254

10f N/A SAP should be marked yes. Mark Yes on 10 f and SAP requirements. (JAFAN 6/0 and other applicable manuals.)

The final DD Form 254 signed by the awardee will include changes as required by the contract.

6 DD254 Page 1 of the

DD254

10k N/A Needs to include other items NC2-ESI, PRP, NWRM JWICS, and SIPRNET.

Note: ICBM SCG was not listed under block 13 but listed on 10k

Mark Yes on 10k and add items. The final DD Form 254 signed by the awardee will include changes as required by the contract.