Hill AFB Bldg 518 - TC Drilling Log.pdf

PDF 15 KB Posted

Attached to
Multiple Award Construction Contract (MACC)
Solicitation number
FA8201-11-R-0008
Issued by

About this file

Test borehole drilling log (In response to Question 74)

View the file

Other files

File Type Posted
FA8201-11-R-0008 Amendment 8 SF30.pdf PDF
Attachment 11 - B-517 Contractor Cost Schedule Updated 11 May 2012.xlsx XLSX spreadsheet
MACC II Questions and Answers updated 3 May 2012.pdf PDF
FA8201-11-R-0008 Amendment 7 SF30.pdf PDF
FA8201-11-R-0008 Amendment 6 Conformed Copy.pdf PDF
FA8201-11-R-0008 Amendment 6 SF30.pdf PDF
FA8201-11-R-0008 Amendment 5 SF30.pdf PDF
Attachment 1 - MACC II SOW 26 April 2012.pdf PDF
MACC II Questions and Answers updated 27 April 2012.pdf PDF
Hill AFB Bldg 518_5-7-10_Conductivity report.pdf PDF
FA8201-11-R-0008 Amendment 4 SF30.pdf PDF
Attachment 14 - UFGS 01 45 00.00 10.pdf PDF
Attachment 20 - B-517 SOW 20120119 Revised 23 April 2012.pdf PDF
MACC II Questions and Answers updated 23 April 2012.pdf PDF
FA8201-11-R-0008 Amendment 3 SF30.pdf PDF
FA8201-11-R-0008 Amendment 2 Conformed Copy.pdf PDF
FA8201-11-R-0008 Amendment 2 SF30.pdf PDF
Attachment 32 - B-517 Utility Map.pdf PDF
MACC II Questions and Answers updated 17 April 2012.pdf PDF
FA8201-11-R-0008 Amendment 1 SF30.pdf PDF
FA8201-11-R-0008 Amendment 1.pdf PDF
MACC II Questions and Answers updated 12 April 2012.pdf PDF
Attachment 9 - Architectural Compatibility Standard.pdf PDF
Attachment 1 - MACC II SOW 9 Feb 2012.pdf PDF
Attachment 15 - MACC II Past Performance Information Sheet.docx DOCX document
Attachment 18 - Davis County - General Decision No. UT20100037 - 6 Jan 2012.pdf PDF
Attachment 8 - LEED_af_sdd_impl_guidance.pdf PDF
Attachment 6 - 01 57 20 Environmental Protection.pdf PDF
Attachment 26 - B-518 Plans Civil.pdf PDF
Solicitation FA8201-11-R-0008.pdf PDF
Attachment 10 - AFI32-10141.pdf PDF
Attachment 22 - B-518 Specs Div 01.pdf PDF
Attachment 11 - B-517 Contractor Cost Schedule.xlsx XLSX spreadsheet
Attachment 2 - 01 00 00 General Requirements.pdf PDF
Attachment 23 - B-518 Specs Div 02 thru Div 23.pdf PDF
Attachment 19 - Weber County - General Decision No. UT20100046 - 6 Jan 2012.pdf PDF
Attachment 20 - B-517 SOW 20120119.pdf PDF
Attachment 25 - B-518 Plans General.pdf PDF
Attachment 5 - 01 45 04 CQC.pdf PDF
Attachment 21 - Index of Drawings.pdf PDF
Attachment 4 - 01 35 26 Government Safety Requirements.pdf PDF
Attachment 29 - B-518 Plans Mechanical.pdf PDF
Attachment 16 - Standard Form 330.pdf PDF
Attachment 14 - UFGS 01 45 00.00 20.pdf PDF
Attachment 27 - B-518 Plans Structural.pdf PDF
Attachment 24 - B-518 Specs Div 26 thru Div 33.pdf PDF
Attachment 28 - B-518 Plans Architectural.pdf PDF
Attachment 30 - B-518 Plans Electrical.pdf PDF
Attachment 17 - Box Elder County - General Decision No. UT20100048 - 6 Jan 2012.pdf PDF
Attachment 3 - 01 32 00 Project Schedule.pdf PDF
Show 40 more

Latest 50 of 140 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hill Air Force Base, Building 518 Ogden, UT

Geothermal Soil Analysis

DRILLING LOG - Test Borehole #1

Location: Legal N 1708' W 361' from S4 S05 T4N R1W SLB&M Approx. Address:

GPS 41° 6' 29.71" N, 111° 58' 46.64" W, WGS84 E. of Bldg. 518 Elevation 4809' SW of D Ave. and 8th St.

Hill Air Force Base, Ogden, UT Driller: Bertram Drilling, Inc - Kevin Smidt

State License #: 227 Rig: #392 (Mayhew 11) Joints on rig: 19

Drilling Fluid: Cetco Super Gel X with some T100 Polymer Length of Joints: 20' Loop: Centennial 1.25" x 810' Length of Kelly: 20'

Grout: GeoPro Thermal Grout Select (TGS) 1.07 (6:1)

SPUD/TD: 9:26 4/27/2010 - 13:31 4/27/2010

Spud with: 5-1/8" re-tipped milltooth tricone bit

Surface Water: None

NOTE: Time gaps represent connections or unrelated activity.

Time Duration Start End Activity Minutes Depth Comments

4/27/2010 9:26 9:34 D 8 0-10 9:34 9:38 D 4 10-20 9:38 9:44 9:44 9:48 D 4 20-30 9:48 9:51 D 3 30-40 9:57 10:01 D 4 40-50

10:01 10:05 D 4 50-60 10:09 10:12 D 3 60-70 10:12 10:16 D 4 70-80 10:19 10:23 D 4 80-90 10:23 10:25 D 2 90-100 10:27 10:30 D 3 100-110 10:30 10:32 D 2 110-120 10:34 10:38 D 4 120-130 10:38 10:40 D 2 130-140 Gvl.

10:42 10:45 D 3 140-150 10:45 10:47 D 2 150-160 10:50 10:53 D 3 160-170 10:53 10:55 D 2 170-180 10:58 11:02 D 4 180-190 11:02 11:05 D 3 190-200 11:05 11:15 11:15 11:18 D 3 200-210 11:18 11:20 D 2 210-220 11:23 11:25 D 2 220-230 11:25 11:28 D 3 230-240 11:30 11:33 D 3 240-250 11:33 11:35 D 2 250-260 11:39 11:45 D 6 260-270 11:45 11:50 D 5 270-280 11:54 12:03 D 9 280-290 12:03 12:09 D 6 290-300

30-35': silty brown clay; 35-40: brown clay

AA

Brown clay

AA

AA

Sandy brown clay, tr black sand, tr fine gravel

AA

Brown silty sand w/ trace gravels

Rig up

Light brown / dark brown sandy clay

0-3': topsoil; 3-10': brown silty/sandy clay

Brown silty sand w/ trace gravels

AA

AA

AA

AA

Sandy brown clay w/ fine gravels

AA

Brown clay, tr coarse sand

Sandy brown clay, tr fine gravel

4/27-29/2010

Replace kelly guide bearing

AA

AA

Sandy brown clay, tr gravel, tr, black sand

AA

AA

Sandy brown clay, tr blk sand - getting sticky - red. pulldown

Fine gravels w sandy brown clay

Sandy brown clay, tr fine black gravel Sandy brown clay, large gravel Sandy brown clay, large gravel, tr fine black gravel

Mud thick, circulate & thin mud

AA

B ro w n

S an dy C la y w / G ra ve ls B ro w n S an dy

C la y w

/ G ra ve ls

DRILLING LOG - Test Borehole

12:13 12:24 D 11 300-310 12:24 12:31 D 7 310-320 12:35 12:41 D 6 320-330 12:41 12:45 D 4 330-340 12:49 12:52 D 3 340-350 12:52 12:58 D 6 350-360 13:04 13:12 D 8 360-370 13:12 13:16 D 4 370-380 13:20 13:27 D 7 380-390 13:27 13:31 D 4 390-400 13:31 14:00 Ream & Circ.

SDFN - Run for grouting materials.

4/28/2010

10:20 10:55 Rig up. RIH to 400'. Water ~80'. Ream & Circ. Last 40' 10:55 11:08 POOH - no problems

Total Drilling Time: 169.00 Minutes Drilling 0 - 400'

2.82 Hours

4/28/2010 11:08 11:12 RIH HDPE loop to 400' 11:33 11:37 RIH flexible hose tremie to 380' 11:37 13:05 Pump 11 units TGS 1.07 with returns to surface 14:10 14:18 Grout subsided 20'. RIH tremie to tag grout - pump 1 more unit TGS 1.07 with returns.

4/29/2010 Top off with approx. 6 gallons TGS 1.07

COMMENTS:

Frequent reaming and circulation between joints to clear sticky clay.

Total units grout used: 12 units TGS 1.07 Estimated water used to drill borehole: approx. 1500 gal.

HDPE loop pressure tested to 108 PSI overnight.

From 0-140': Drilling observed and samples logged by Van Riding of Earthfax Engineering.

From 140-400': Drilling observed and samples logged by David Eckels of Sound Geothermal.

AA

AA

Gray brown clay, tr black sand

AA

AA

AA

Sandy brown clay, tr black sand, tr fine gravel

AA

AA - sticky Sandy brown clay, tr black sand, tr L gravel ~315'

G ry

-B rn

C la y

Geothermal Soil Analysis

Colors: Descriptors: Lithology: Drilling:

blk - black ang - angular bas - basalt AA - As Above blu - blue cmt - cement bdl - boulder PU - Pick Up brn - brown crs - coarse cbl - cobble POOH - Pull out of hole bu - buff dk - dark cche - caliche RIH - Run in hole clr - clear f - fine cgl - conglomerate RU - Rig Up crm - cream frm - firm cl - clay SDFN - Shut down for night gn - green hd - hard dol - dolomite TD - Total Depth gry - gray L - Large grt - granite pk - pink lt - light grv - gravel rd - red M - Medium ls - limestone tn - tan mtrx - matrix qtz - quartzite trnsl - translucent S - Small sd - sand wh - white sbang - sub angular sh - shale yel - yellow sft - soft slt - silt tr - trace slts - siltstone uncons - unconsolidated ss - sandstone volc - volcanics

LEGEND

File details come from the government source that posted it. Updated .