Responses to Questions FA8201-08-B-0002.docx

DOCX document 20 KB Posted

Attached to
BUILT UP ROOF IDIQ Federal contract opportunity
Solicitation number
FA8201-08-B-0002
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Responses to Questions FA8201-08-B-0002

View the file

Other files for this federal contract opportunity

Other files attached to BUILT UP ROOF IDIQ, newest first.
File Type Posted
Amendment 5.docx DOCX document
Supplemental Line Item Description.pdf PDF
Sup Schedule B Hill AFB.pdf PDF
Sup Sched B UTTR.pdf PDF
Sup Sched B Little Mountain.pdf PDF
Amendment 4.doc DOC document
Amendment 3.doc DOC document
Amendment.doc DOC document
16610 Lightning Protection.doc DOC document
Box Elder County Wage Decision.doc DOC document
07510 Built-up Bituminous Roofing.doc DOC document
Supplemental Line Item Description.xls XLS spreadsheet
List of Specifications.doc DOC document
Supplemental Schedule B.xlsx XLSX spreadsheet
FA8201-08-B-0002.doc DOC document
01000 General Requirements Bur.doc DOC document
Weber County Wage Decision.doc DOC document
16859 Heating Cable.doc DOC document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTERESTED PARTY QUESTIONS AND GOVERNMENT ANSWERS IN RESPONSE TO SOLICITATION FA8201-08-B-0002

BUILD UP ROOFING IDIQ

FA8201-08-B-0002

Q&A RESPONSES

17 SEP 2008

1. Question: With the unstable oil market, pricing has also been very unstable. Is there a provision in the contract to cover this escalation over and above the original estimate of work?

Answer: No there is not. We do not want you to operate at a loss. Please provide your best judgments of what the items will cost with a proper buffer, however, you will be held to the prices you propose but remember that the award is still based on the lowest bid.

2. Question: Will the award be based on the combined total sum of each of the three spreadsheets HAFB, Little Mountain and UTTR? If not what will the basis be?

Answer: Yes, your bottom line is what determines who receives the award.

3. Question: On the spreadsheets you’re asking for an amount and total. Does the amount then become unit price basis for the rest of the contract?

Answer: The unit prices that you propose are what we will hold you to for the remainder of the contract. This is why you can propose different unit prices for each of the three years because we understand that it will probably change from year to year.

4. Question: I don’t understand the supplemental line item schedule that was posted 9/16/2008. There are a number of blank pages and it is not formatted the way the other three Sup Schedules are.

Answer: This was put out there because some contractors could not open the Excel spreadsheet.