Attach. 1a SOW addendum.pdf
PDF 151 KB Posted
- Attached to
- Design and Build Repair Facade and Roof B707
- Solicitation number
- FA663326R0002
About this file
This is a Statement of Work (SOW) Addendum issued by the Department of the Air Force, Air Force Reserve Command, dated 26 February 2026, that amends the original SOW for project QJKL 24-0014 (dated 24 November 2025). The addendum removes all references to "Bid Option 1" from the document.
The work involves conducting a comprehensive site investigation and repair of Building 707 Lodging at an Air Force Reserve facility. The base bid work includes 13 primary repair tasks: roof replacement, skylight repair, brick façade and masonry joint repairs, aluminum window trim repairs, fenestration investigation and repair, metal panel joint repairs, brick control joint repairs, and sheetrock wall repairs and painting. The remaining bid options (Nos. 2-6) are completed concurrently with base bid work and include: sheetrock repairs (28 days), skylight damage repairs (21 days), miscellaneous repairs such as popcorn ceiling repairs, wainscot installation, and stairwell railing restoration (14 days), parking lot repairs including crack sealing and re-surfacing (7 days), and elevator fire sprinkler and fire alarm modifications for three elevators with installation of check valves, inspector's test valves, flow switches, and shunt trips (28 days). No additional performance days are offered for the optional work tasks.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR FORCE RESERVE COMMAND
STATEMENT OF WORK (SOW) ADDENDUM
SUBJECT: This addendum amends the Statement of Work (SOW) for project QJKL 24-0014, dated 24 November 2025. The purpose of this addendum is to remove all references to "Bid Option 1".
Date: 26 February 2026
Amended Part 3 - PROJECT DESCRIPTION AND REQUIREMENTS
3.01 DESCRIPTION OF WORK
A. Conduct site investigation of B707 Lodging to determine extent of repairs. The known repairs are as follows:
1. Replace Roof, B707, see SOW Drawings
2. Repair Skylight (Area A), see SOW Drawings
3. Repair brick façade, see SOW Drawings
4. Repair masonry joints, see SOW Drawings
5. Repair aluminum window trim compressed by collapsed control joints, see SOW Drawings
6. Investigate fenestration where glazing gaskets are not sealing the glazing to the window frame.
Specific locations are not identified on the SOW drawings. Elevator lobby windows and 1st Floor connectors have multiple incidents, see SOW drawings for window locations.
7. Repair metal panel joints, see SOW Drawings
8. Repair brick control joints, see SOW Drawings
9. Repair sheetrock walls, prepare surfaces for new paint, prime, and paint (match existing color) to change in wall direction, see Bid Option Drawings for locations. Sand and skimp coat sheetrock walls. Clean and prepare surface for primer and paint (Bid Option 2).
10. Repair sheetrock water damaged from leaking skylight, ceiling and west wall, prepare surfaces for new paint, prime, and paint (match existing color) to change in wall direction, see Bid Option Drawings for locations (Bid Option 3).
11. Miscellaneous repairs (Bid Option 4), see Bid Option Drawings.
a. Repair popcorn ceiling, Rooms 456 & 458.
b. Add wainscot to First Floor hallway where carts are stored.
c. Restore corroded stairwell railing in Southwest stairwell.
d. Paint Main Lobby, 1st Floor.
12. Parking Lot repairs (Bid Option 5)
a. Crack seal where asphalt surface is stable, approximately 1,200 ft.
b. Mill and re-surface where asphalt surface is alligatored, approximately 400 square yards.
c. Restripe all parking lots, approximately 3,200 linear feet.
13. Elevator Fire Sprinkler and Fire Alarm Changes (Bid Option 6)
a. East Elevator: Install check valve, inspector's test valve and piping for the flow switch.
Direct water flow to exterior. Provide low point drain if needed to ensure inspector's test piping fully drains.
b. Center Elevator: Install flow switch, shunt trip, check valve, Install check valve, inspector's test valve and piping for the flow switch. Direct water flow to exterior.
Provide low point drain if needed to ensure inspector's test piping fully drains.
c. Install check valve, inspector's test valve and piping for the flow switch. Direct water flow to exterior. Provide low point drain if needed to ensure inspector's test piping fully drains.
Amended Part 4 - PERFORMANCE
Period of Performance for Bid Options
Option Task Days
No. 2 Sheetrock Repairs 28
No. 3 Skylight Damage 21
No. 4 Miscellaneous Repairs 14
No. 5 Parking Lot Repairs 7
No. 6 Elevator Life Safety 28
Bid Options completed concurrently with Base Bid work. No additional days are offered.
THEODORE TIO
Engineering Flight Chief 934th CE/CEC
File details come from the government source that posted it. Updated .