5. USAG DPW PAINT AND COATING - Statement of Work (27NOV24).pdf

PDF 198 KB Posted

Attached to
Okinawa Interior/Exterior Paint IDIQ Federal contract opportunity
Solicitation number
FA527023R0018
Issued by
Department of the Air Force Pacific Air Forces

About this file

This is a Statement of Work for an IDIQ contract to repair interior and exterior paint at various Army facilities in Okinawa, Japan including Torii Station, Kuwae and Chimuwan Tank Farm, Naha Port, Bolo Point, Hill 450, and Buckner Communication Site, with a project date of November 27, 2024.

The contractor shall repaint all exterior surfaces with surface preparation, partial interior paint areas, crack and spall repairs, and ACM & LBP abatement work. Key requirements include providing temporary barricades during construction, weather prevention for exterior areas, protection of government equipment and furniture, and comprehensive cleanup. The work involves removing and disposing of peeling paint, corrosion on structural beams, pipes and junction boxes, replacing sealants, repairing cracks with epoxy mortar, and repainting concrete building walls, roof eaves, piping, and roof parapets. The contractor must follow Installation Design Guide standards for Army facilities, use water-based exterior paint with 10-year durability, and comply with extensive safety, environmental, and security requirements including AT Level I training, iWATCH Army training, and various security protocols for facility access.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

IDIQ- Repair Interior & Exterior Paint, Various Building, Torii Station, Kuwae and Chimuwan Tank Farm, Naha Port, Bolo Point, Hill 450 and

Buckner Communication Site, Okinawa, Japan.

(27 November 2024)

GENERAL: This Statement of Work supplements the General Statement work for above mentioned project and more specifically defines the subject project.

I. GENERAL PROJECT SCOPE: IDIQ- Repair Interior & Exterior Paint, Army Facilities, Okinawa, Japan.

The contractor shall repaint of all exterior surfaces including surface preparation & partial area of interior paint, crack & spalls repair and ACM & LBP abatement work.

II. STATEMENT OF WORK:

A. REPAIR WORK (K); Work shall include but not limited to:

GENERAL

1. Restoration work must be conducted on the site affected by this project.

2. Temporary barricade shall be provided by the contractor during the construction to prevent other occupancy area from construction dust and security. per accepted Accident Hazard Analysis.

3. Provide weather prevention work for exterior opening area during the construction.

4. The Contractor shall protect the government equipment, furniture, carpet and other items. For the items that will be kept in work areas must be protected with approved materials during construction.

5. Clean-up all room affected by this project throughout the whole building prior to final inspection.

ARCHITECTURAL

The project shall include as a minimum but not be limited to the following work.

Interior & Exterior Paint:

1. Provide shop drawings & Material Submittal must be coordinated with the using agency and other agencies involved in Exterior & Interior paint project review.

Submittal documents:

- Safety Plan (based on UFGS 01010)

- Activity Hazard Analysis (based on UFGS 01010)

- Accident Prevention Plan (based on UFGS 01010)

- Quality Control Plan (based on UFGS 01010)

- Environmental Protection Plan (based on UFGS 01 56 00)

- Joint sealants (based on UFGS 07 92 00)

- Paint & Coating (based on UFGS 09 90 00)

- Disposal Manifest

- Warranty management plan

- Anti-rust Material-Catalog, SDS, Certificate

- etc…

Shop drawings:

- Phasing plan

- ACM & LBP abatement plan

- Scaffolding & Barricade plan

- etc…

2. Conduct ACM & LBP abatement work.

3. Remove and dispose the exterior surface peeling paint and prepare or repair surface prior to repainting.

4. Remove and dispose corrosion on exposed structural beams and prepare surface prior to repainting.

5. Remove and dispose corrosion on pipes, junction boxes and prepare surface prior to repainting.

6. Remove and dispose existing sealant w/ Back-up material and Bond breakers.

7. Repair existing defective cracks with epoxy mortar to much existing condition.

8. Repaint existing exterior concrete building walls, roof eaves, various piping and roof parapet.

9. Provide new sealant work with Back-up material and Bond breakers.

10. Repaint building number with paint year/month, signage to match existing.

11. Repaint interior ceilings, walls, floors or other area.

Note:

- Follow Installation Design Guide (IDG) for Army facilities.

- Exterior paint material (water based) should be over 10 year’s durability.

III. LOCATION AND BUILDINGS:

1. Torii Station

2. Kuwae & Chimuwan Tank Farm POL Facilities

3. Naha Port

4. Bolo Point

5. Hill 450 (Bldg.591)

6. Buckner Communication Site

IV. CONSTRUCTION REQUIREMENTS: The contractor shall be responsible to obtain

As-built drawings from the government. The drawings information is for contractor reference only. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information from the contractor.

A. Construction method must conform, as applicable, to the latest OSHA (Occupational

Safety & Health Administration) standards, UL (Underwriters Laboratories), TI (Technical Instructions), Unified Facilities Guide Specifications (UFGS), AR (Army Regulation), JEGS (Japan Environmental Governing Standards), JIS(Japanese Industrial Standards), JASS (Japanese Architectural Standard Specification), Military Construction Guide Specifications, Torii Standard and all applicable Act, policies, regulations and publications.

B. Responsibility of the Contractor for Construction:

1. The contractor shall be responsible for the professional quality, technical accuracy.

The Contractor shall, without additional compensation, correct or revise any errors or deficiency in perform any necessary rework, including any damage to real or personal property. It is the contractor’s responsibility to notify the Government representative of any errors, omissions, or code violations upon discovery either on the construction documents or upon discovery in the process of construction.

2. The Governments’ review, approval, acceptance, or payment for the services required under this contract shall not be constructed as a waiver of any responsibility and liability of the Contractor under this contract or any cause of action arising out of the performance of this contract. The Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor’s negligent performance (include but not limited to construction) of any of these services furnished under this contract.

3. The contractor must submit submittal documents accompanied by KTR’s technical justification and documented approval to the DPW before construction work can commence. The construction work will not be permitted to proceed without the submission of construction shop drawings in advance.

C. Construction Time: The contractor shall be allowed to work 0800 to 1700 hours, Monday through Friday, except the US Legal holidays & the user’s work schedule.

D. Contractor shall restore to the original condition all facilities damaged or temporarily removed during construction.

E. All exterior materials and materials to be used in wet, moisture location shall be corrosion, rust, and mold resistant.

F. Exterior paint material (water based) should be over 10 year’s durability.

- Exterior and interior color selections shall be in conformance with Army color schemes and standards.

- Paint new exposed surfaces of all pipes, fittings, brackets, supports, hangers, metal surfaces and other accessories

G. All damages affected by the project shall be restored to match with existing adjacent condition.

H. All 3-week detail schedules must be submitted on or before 1 week the scheduled start date to COR. Quality assurance inspection must be coordinated before schedule starts.

V. Asbestos Containing Material (ACM) and Lead Base Paint (LBP)

A. The contractor shall be responsible to identify & test of any asbestos and LBP associated with the work performed in accordance with EPA, OSHA, JEGS and applicable regulations and specification and Army Environmental Protection Section 01560 (Latest Version). The contractor’s asbestos and LBP inspector shall conduct survey for the project work area to identify homogeneous materials. If sampling is deemed necessary for ACM & LBP test results other than those provided by DPW or no information, the contractor shall submit the additional/ new sampling plan with CD, obtain the government safety and environmental approval and coordinate the sampling schedule with the government prior to taking any samples.

B. The contractor shall be provide ACM & LBP abatement work plan.

C. The manifest for the asbestos and LBP shall be submitted to the government immediately after disposal.

VI. DOCUMENTS REQUIRED: All documents required under this Contract, including but not limited to, safety hazard analysis plans, all correspondence of any nature whatsoever and all other written communications, documents, drawings, reports, etc.

of every description shall be written in English or translated in English before being provided to the Government by the Contractor. Delays encountered because a translated copy was not submitted shall be the Contractor’s expense.

A. AF Form 66, Material submittal Log: The contractor shall provide and responsible for

AF Form 66, Material submittal Log.

B. Warranty Management Plan must be submitted per the UFGS 01 78 00 General

Requirements Closeout submittals.

VII. GOVERNMENT FURNISHED UTILITY: Government Furnished Utilities will be provided where available at no cost to the contractor.

VIII. AVAILABILITY OF LATRINE: The contractor shall coordinate with the government for the availability of latrine.

IX. FACILITY AVAILABILITY: Facility is available during the construction. The impact caused by this project shall be at minimum. The contractor shall coordinate the construction schedule with the government prior to the construction start. All rooms and the utility system except for the construction floor/phase shall be kept in useable condition during the construction. The contractor shall establish work procedures and methods to avoid interference with the business operations or adjacent to the construction area.

X. ENVIRONMENTAL REQUIREMENTS:

A. The contractor shall provide construction and demolition waste information including the costs to the Government immediately after the disposal.

a) Solid Waste manifests (Page A and E) shall be submitted to Environmental Office within 30 days or sooner of each disposal if solid waste disposal would be conducted for this project.

b) Hazardous Waste manifests (Page A and E) shall be submitted to Environmental

Office within 30 days or sooner of each disposal if hazardous waste disposal would be conducted for this project.

B. For new constructions materials, ensure all are free of asbestos and lead-based paint (LBP) in accordance with the Japan Environmental Governing Standards (JEGS) or other laws and regulations. The contractor shall provide manufacture’s certification that materials contain no asbestos (≦ 0.1%) and no lead. If certification is not available, the contractor shall conduct sampling and analysis of the materials.

The analysis results must show no asbestos and no lead.

XI. SAFETY REQUIREMENT:

A. The contractor shall provide and submit a site-specific safety plan prior to start work for approval from the government. The contractor shall be responsible to obtain the approval in timely manner considering the government’s review time and the contractor’s review time.

B. The contract location is a multi-employer workplace. The contractor is required to provide information regarding hazardous materials being brought to this workplace and hazardous conditions produced by construction activities, and to provide information to the US Government how Human Health will be protected.

C. The contractor shall submit Safety Data Sheets and other information from contractor regarding protecting Human Health of US Government personnel. Since 1 June 2015, 29 CFR 1910.1200 (OSHA) requires that a Safety Data Sheet (SDS) be provided for each hazardous material used in the workplace.

D. Provide rope off/barricade at disturbed area in accordance with standard construction procedures, to include Japanese and English Bilingual hazardous/warning signs.

E. Perform traffic and pedestrian control with watchman as required at daytime and provide lighting system at night time.

F. Provide the steel plate across the board for secure to safety access existing parking lots, roadways as required.

G. Provide scaffolding and shoring including, sheet piling to protect workmen, banks, adjacent paving, structures, in accordance with Corps of Engineers manual EM 385- 1-1 as required.

XII. FIRE SAFETY REGULATION:

The Contractor shall obtain a permit from the USAG-O Fire Chief prior to conducting any welding or soldering or whenever the use of open flame is necessary during the construction phase. The Contractor and his employees will be required to adhere to AR 420-1, dated 12 February 2008.

XIII. OPERATION SECURITY (OPSEC) AND SOCIAL NETWORKING:

A. The contractor personnel that will work under this contract shall review and sign the

Contractor OPSEC Training Completion Verification Sheet within 30 calendar days after contract awarded. The DPW will provide the OPSEC Training slides to the contractor to take this training. Once the contractor’s training is completed the DPW shall file the signed Contractor OPSEC Training Completion Verification Sheet in the contract file.

B. Upon completion of contract, the contractor shall return any photos taken, along with all maps, sketched, other images to DPW.

C. The contractor shall not discuss and provide any information, documents, photos, maps, sketched and other images to any outside agency.

D. The contractor will not require access to US Government computers.

E. AT/OP SEC requirement

a) Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training before contract start date. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to DPW or the COR or to the contracting officer, if a COR is not assigned, after completion of training by all employees and subcontractor personnel. The AT Level I training will be completed either on the Joint Knowledge Online at http://jko.jten.mil (CAC Required) or contractor employees will complete the locally developed AT Level I training translated into Japanese. The contractor personnel that will work under this contract shall review and sign the Contractor AT- iWATCH-OPSEC Training Roster. Provide the training roster to DPTMS.

b) iWATCH Army Training. DPW or the COR or the contracting officer will brief the contractor and all associated subcontractors on the local iWATCH Army program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed, and the results reported to the COR before the start date of the contract. The locally developed training is translated into Japanese. The contractor personnel that will work under this contract shall review and sign the Contractor AT-iWATCH-OPSEC Training Roster. Provide the training roster to DPTMS.

c) Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors’ employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9 or NAF Clause BI.142, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

d) For contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

e) Contractors will receive AT Level 1 and iWATCH training using the locally developed training translated into Japanese. Training will be updated on the AT/iWATCH/OPSEC Training Roster and provided to DPTMS when training is completed. All new construction must be in accordance with the Unified Facilities Code 4-010-01 Minimum Antiterrorism Standards for Buildings.

f) Contractors are not authorized the use of any small UAS/UAVs during this project. Ensure all OPSEC training is completed, and contractors sign the AT/IWATCH/OPSEC training roster, which is subject to inspection at any time during the contract.

STATEMENT OF WORK
IDIQ- Repair Interior & Exterior Paint, Various Building,
Torii Station, Kuwae and Chimuwan Tank Farm, Naha Port, Bolo Point, Hill 450 and Buckner Communication Site, Okinawa, Japan.
GENERAL: This Statement of Work supplements the General Statement work for above mentioned project and more specifically defines the subject project.
I. GENERAL PROJECT SCOPE: IDIQ- Repair Interior & Exterior Paint, Army Facilities, Okinawa, Japan.
II. STATEMENT OF WORK:

File details come from the government source that posted it. Updated .