The file is a Project Requirement Price Schedule for a Design-Build contract to repair Palau Dorm B25016 at Andersen Air Force Base in Guam. The comprehensive renovation project includes extensive interior and exterior repairs, full system replacements, and infrastructure upgrades. Key scope elements involve complete renovation of floors, walls, ceilings, restrooms, HVAC, plumbing, electrical distribution, and fire protection systems. Specific requirements include replacing the central chiller plant (with Dunham Bush or Odyne chillers preferred), updating electrical distribution from the pad mount transformer, installing a wet-pipe sprinkler system, and implementing a mass notification system.
The solicitation (FA524025R0002) is issued by the Department of the Air Force Pacific Air Forces for project AJJY 25-1072M, with the contract structured as a single line item (Lot) for the entire renovation. The project requires re-grading to ensure proper drainage, clearing storm sewer inlets, and updating code compliance for energy and life safety. Specific brand preferences are noted for critical components, such as fire alarm panels (Monaco or EST brands). The project aims to comprehensively restore and modernize the dormitory facility, addressing structural, mechanical, electrical, and safety system deficiencies.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| CUI | FA524025R0002 | |
| Attachment 02 |
PROJECT REQUIREMENT PRICE SCHEDULE
Project #: AJJY 25-1072M
Project Name: Repair Palau Dorm B25016 Andersen Air Force Base, GU
Project Description: The Contractor is tasked with a Design-Build requirement to design and fully repair Palau Dorm B25016 which includes renovation of interiors including floors, walls, ceiling, finishes, full restroom renovation, updating code for Energy and Life Safety, exterior renovations resulting from recent storm damage. Walkway slabs and spandrel beams will be repaired. Repairs will also include a complete update to the HVAC and Plumbing systems in the Palau dorm. Palau is conditioned by a chilled water and a central chiller plant, both will be replaced. A complete replacement of air handlers, ductwork, grilles, variable air volume boxes, and chilled water piping will be replaced. AAFB Justification and Approval (J&A) specifies Dunham Bush as the preferred chiller. Odyne Chillers are also acceptable. The chilled water pump will be replaced. All existing plumbing utilities will be replaced and updated. The existing heat pump water heaters will be replaced with standard electric water heaters with large storage tanks. Electrical updates include an update to the entire electrical distribution system. The system updates will include a complete replacement of electrical distribution from the pad mount transformer secondary conductors to the entire downstream building distribution system. Fire protection updates include sprinkler protection throughout, installation of a mass notification system, and a wet-pipe sprinkler system throughout the dorm. AAFB J&A for the Fire Alarm Panel specifies either Monaco or EST brands. The Palau dorm must be re-graded to maintain positive drainage away from the building. Existing storm sewer inlets are buried with debris, dirt, and grass- these are to be cleared. Work shall be performed in accordance with the Statement of Work and all associated attachments.
| ITEM |
| DESCRIPTION |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| TOTAL EVALUATED PRICE (TEP) |
| 0001 |
| AJJY 25-1072M Repair Palau Dorm B25016 Andersen Air Force Base, GU |
| 1 |
| LOT |
| CONTRACTOR/OFFEROR NAME |
| ADDRESS |
Proposal Valid Through (Date): ____________