Bid Schedule Base Year
View the file
Other files for this federal contract opportunity
Show all 42
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ITEMS 0001 – BID SCHEDULE BASE YEAR | |||||
| Line Item | Description | Unit | Est Qty | Base Year | |
| Unit Price | Base Year |
Total Price
| 0001AA | Remove composition shingles and felts to deck | SF | 96000 |
| 0001AB | Remove standing seam metal roof fasteners. Includes removal of all clips and fasteners. | SF | 7200 |
| 0001AC | Remove roof pavers | SF | 60000 |
| 0001AD | Reinstall Roof pavers | SF | 10000 |
| 0001AE | Remove Lightguard insulation | SF | 6000 |
| 0001AF | Remove existing loose laid roof insulation, up to and including 4" average thickness | SF | 30000 |
| 0001AG | Remove existing loose laid roof insulation, over 4" average thickness | SF | 9000 |
| 0001AH | Remove existing adhered or mechanically attached roof insulation, up to and including 4" average thickness | SF | 30000 |
| 0001AI | Remove existing adhered or mechanically attached roof insulation, over 4" average thickness | SF | 9000 |
| 0001AJ | Remove Built-Up Roof (BUR) to the existing roof deck | SF | 12000 |
| 0001AK | Remove BUR containing asbestos to the existing deck, quantity <5,000 SF - work to be performed IAW 29 CFR 1910 and other applicable regulations | SF | 7200 |
| 0001AL | Remove asbestos containing BUR to the existing deck, quantity >5,000 SF - work to be performed IAW 29 CFR 1910 and other applicable regulations | SF | 24000 |
| 0001AM | Remove roof drain with insulation containing asbestos - work to be performed IAW 29 CFR 1910 and other applicable regulations | EA | 12 |
| 0001AN | Remove single-ply roof membrane, flashing, and sealant | SF | 66000 |
| 0001AO | Remove asphalt-based mastic containing asbestos - work to be performed IAW 29 CFR 1910 and other applicable regulations | SF | 120 |
| 0001AP | Remove existing plywood deck | SF | 12000 |
| 0001AQ | Remove curb, nailer, or parapet | BF | 14400 |
| 0001AR | Demo 2" x X" wood roof joist - flat deck only (<3% slope). Does not include mechanical or electric work | BF | 6000 |
| 0001AS | Remove existing metal flashing, drip edge and expansion joint, to include all associated clips and fasteners | SF | 48000 |
| 0001AT | Remove roof turbine vent | EA | 36 |
| 0001AU | Remove existing roof vent (gable, soffit, and/or ridge) | EA | 12 |
| 0001AV | Remove roof mechanical vent, excludes electrical and duct work (size calculated by metal area) | SF | 1800 |
| 0001AW | Remove existing metal ladder. Includes patching and painting of holes to match facility. | LF | 300 |
| 0001AX | Install IRMA roof insulated to R38, tapered insulation (1/4" per foot minimum), minimum 1" thickness, paver ballast only | SF | 24000 |
| 0001AY | Install exposed membrane roof on a wood or steel deck, insulated to R38, 1/4'' per foot taper, 1'' minimum thickness, UL Classification of A | SF | 18000 |
| 0001AZ | Install exposed membrane roof on a wood or steel deck, insulated to R38, flat stock, UL Classification of A | SF | 26000 |
| 0001BA | Install exposed membrane roof on a concrete deck, insulated to R38, 1/4'' per foot taper, 1'' minimum thickness, UL Classification of A | SF | 24000 |
| 0001BB | Install exposed membrane roof on a concrete deck, insulated to R38, flat stock, UL Classification of A | SF | 30000 |
| 0001BC | Extend membrane up (and over, if appropriate) wall, parapet or curb | SF | 30000 |
| 0001BD | Install tapered insulation for IRMA roof, SBS, BUR roof, crickets, and/or saddles | SF | 120000 |
| 0001BE | Install remanufactured flashing for VTRs | EA | 600 |
| 0001BF | Install manufacturer approved walk-pad | SF | 2400 |
| 0001BG | Install 4" roof drain. Includes bowl installation and components, patching, repairs and cleanup | EA | 12 |
| 0001BH | Install drain extension 2" to 4" | EA | 25 |
| 0001BI | Install 4" adjustable drain extension | EA | 10 |
| 0001BJ | Flash roof drain | EA | 120 |
| 0001BK | Flash scupper | EA | 120 |
| 0001BL | Strip in all EPDM to EPDM seams, Does not include removal/replacement of insulation or pavers | LF | 6000 |
| 0001BM | Install new SBS modified 4-ply BUR system, (1 base, 2-ply type IV glass ply sheets, SBS Modified mineral surfaced cap sheeting using ASTM D312 asphalt) | SF | 6000 |
| 0001BN | Install insulation for BUR system, R38, flat stock, 1/4 " per foot taper. 1'' minimum thickness | SF | 4800 |
| 0001BO | Install 3/4" perlite thermal barrier | SF | 6000 |
| 0001BP | Install 5/8" gypsheeting thermal barrier | SF | 6000 |
| 0001BQ | Install flashing for penetration less than 6" outside diameter | EA | 240 |
| 0001BR | Patch area of protected BUR with 2-ply and new 60lb flood coat. Does not include removal/replacement of insulation or pavers | SF | 2400 |
| 0001BS | Repair exposed BUR roof with flood coat(reflash, patch cut, reseal seams, etc). | SF | 600 |
| 0001BT | Repair exposed BUR roof with emulsion (reflash, patch cut, reseal, etc). | SF | 600 |
| 0001BU | Repair exposed BUR roof with silver coat (reflash, patch cut, reseal seams, etc,). | SF | 600 |
| 0001BV | Repair exposed BUR roof with cap sheet (reflash, patch cut, reseal seams, etc). | SF | 600 |
| 0001BW | Install ice and water shield | SF | 96000 |
| 0001BX | Install shingles, fiberglass, Class A 240#/Square | SQ | 3000 |
| 0001BY | Install roof vent, in MFH (gable, soffit and/or ridge), <36" x 36" | EA | 60 |
| 0001BZ | Install Clip Rib or equivalent standing seam metal roof. This item does not apply to pre-engineered buildings | SF | 12000 |
| 0001CA | Install premanufactured flashing for shingle roof | EA | 120 |
| 0001CB | Install premanufactured flashing for metal roof | EA | 36 |
| 0001CC | Install curbing, nailer, joist or parapet, treated wood | BF | 30000 |
| 0001CD | Install plywood decking, 1/2" OSB | SF | 14400 |
| 0001CE | Install plywood decking, 5/8" OSB | SF | 6000 |
| 0001CF | Install plywood decking, 3/4" OSB | SF | 6000 |
| 0001CG | Install plywood sheathing, 1/2" AWPA C9 treated wood | SF | 12000 |
| 0001CH | Install plywood sheathing, 5/8" AWPA C9 treated wood | SF | 6000 |
| 0001CI | Install plywood sheathing, 3/4" AWPA C9 treated wood | SF | 6000 |
| 0001CJ | Install metal flashing, expansion joint, etc in accordance with MFG recommendations and procedures less than or equal to 20ga | SF | 14000 |
| 0001CK | Install metal flashing, expansion joint, etc in accordance with MFG recommendations and procedures greater than or equal to 19ga | SF | 4000 |
| 0001CL | Install galvanized sheet metal for miscellaneous applications to include rooftop mechanical vent, etc less than or equal to 20 ga | SF | 500 |
| 0001CM | Install galvanized sheet metal for miscellaneous applications to include rooftop mechanical vent, etc greater than or equal to 19 ga | SF | 100 |
| 0001CN | Install OSHA approved safety ladder with top rails and cage. | LF | 120 |
| 0001CO | Install overflow scupper. Includes flashing and patching if necessary | EA | 24 |
| 0001CP | Install seamless prefinished steel gutters & downspouts | LF | 650 |
| 0001CQ | Install snow bars for sloped roof, includes flashing | LF | 480 |
| 0001CR | Install NORCLAD type fascia (min 16" extension) | SF | 12000 |
| 0001CS | Install caulking, silicon rubber, up to 1/2" joint | LF | 2400 |
| 0001CT | Clean and remove debris and ensure flow in existing roof drain | EA | 60 |
| 0001CU | Cut hole in steel or wood deck for vent, duct, or drain installation | SF | 120 |
| 0001CV | Cut hole in concrete deck for vent, duct or drain installation | SF | 120 |
| 0001CW | Core drill concrete block wall for roof drain piping, Includes sleeve, patching, fire caulking and clean up | EA | 10 |
| 0001CX | Install rubber expansion joint, up to 2" wide opening | LF | 12000 |
| 0001CY | Install rubber expansion joint, up to 4" wide opening | LF | 6000 |
| 0001CZ | Install new roof turbine vent | EA | 30 |
| 0001DA | Install roof warranty sign | EA | 60 |
| 0001DB | Install heat tape with braided wire on outside of pipe, maximum of 3 wats per foot, include termination kits(electrical connection done by others) | LF | 1200 |
| 0001DC | Install laminated rim joist, FFP - 9.5" tall, 1" wide (only for total roof replacement) | LF | 480 |
| 0001DD | Install laminated rim joist, FFP - 11.875" tall, 1" wide (only for total roof replacement) | LF | 480 |
| 0001DE | Install insulation, FFP - un-faced fiberglass batt, high density, R-30, 8.25" thick, 16" or 24" wide | SF | 4800 |
| 0001DF | Install vapor barrier, FFP - 8-mil polyethylene (only for total roof replacement) | SF | 4800 |
| 0001DG | Install wood I-joists, FFP - 11.875" tall, 2.5" wide flange, and all associated bracing, straps, and fasteners (only for total roof replacement) | LF | 2400 |
| 0001DH | Burdened hourly labor rate FFP Burdened labor rate for the purpose of, but not limited to, snow removal and inclement weather tent condition/removal | Hours | 240 |
| 0001DI | Construction of inclement weather tent FFP Construction of inclement weather ten using reinforced poly | SF | 6120 |
| 0001DJ | Operation of inclement weather tent- FFP Operation of inclement weather tent to include heaters, fuesland all necessary materials to operate between the temperatures of -10 and 30 degrees Fahrenheit | Days | 12 |
| 0001DK | Install 1/2" dia X 12" lightning protection air terminals over 75' high | EA | 50 |
| 0001DL | Install lightning protection cable, 375 lb per thousand ft over 75' high | LF | 500 |
| 0001DM | Install 3/4" dia grounding rod 10' long and weld wire to rod | EA | 5 |
| 0001DN | Install #2 grounding stranded copper wire | LF | 100 |
| 0001DO | Install 15 # Roofing felt | SF | 1000 |
| 0001DP | Install 30# Roofing felt | SF | 2000 |
| 0001DQ | Install up to 4" piping for roof drain,including hangers and accessories | LF | 4 |