TO_000U_(Sigonella)_Unique_Requirements.pdf
PDF 24 KB Posted
- Solicitation number
- FA4890-16-R-0032
About this file
14 Mar 17 update to RFP Atch 08, Document TO 000U, NAS Sigonella, Italy (RQ-4) Unique Requirements, renumbered to match Atch 03 tabs and incorporated with Amendment 0001.
View the file
Other files
Show 40 more
Latest 50 of 182 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation: FA4890-16-R-0032 / Task Order 000U 14 Mar 17
ATTACHMENT 1
TECHNICAL TASK ORDER REQUIREMENTS
1.0 INTRODUCTION/BACKGROUND: ACC AMIC requires RPA organizational-level (O-level) support at the OCONUS location as identified below.
2.0 TASK ORDER OBJECTIVE: Provide O-level maintenance to OCONUS military units tasked for local and OCONUS missions.
3.0 REFERENCE: RPA Performance Work Statement (PWS) and Appendix N (Operational Requirements).
4.0 UNIQUE TASK ORDER REQUIREMENTS.
Task Order
Adjustments to Appendix N (Operational Requirements)
000U
NAS Sigonella
- 24/7 operations.
- 3 Block 30 Aircraft, flying 30 average sorties per month, 24 hours average duration, for 725 average flying hours per month.
- 0-3 Block 40 Aircraft, flying 18 average sorties per month, 24 hours average sortie duration for 450 average flying hours per month.
- Any sortie deemed non-effective due to an abort may require the contractor to launch a spare aircraft.
- Contractor provides all tool room support at the site.
- Contractor provides Transient Alert support at the site.
- This effort is a joint military/contractor effort with all backshop functions supported by military personnel.
- Contractor will be responsible to maintain one LRE, Common Data Link (CDL) and UHF Line of Sight Antennas.