T-38 RFP Q A as of 17 Jan 2011.docx

DOCX document 18 KB Posted

Attached to
T-38 Companion Trainer Program (CTP)
Solicitation number
FA4890-10-R-0008A
Issued by

About this file

Updated Questions and Answers as of 17 Jan 2011.

View the file

Other files

File Type Posted
T-38 Award Synopsis -.doc DOC document
T-38 RFP Q A as of 10 Feb 2011.docx DOCX document
T-38 RFP Q A as of 3 Feb 2011.docx DOCX document
Langley MOU.pdf PDF
Tyndall AFB WD 2005-3008 rev 12.pdf PDF
T-38 CTP PWS 3 Feb 2011.docx DOCX document
CDRL A010 Safety and Health Plan.doc DOC document
T-38 CTP Projected Force Structure and Flying Hours.docx DOCX document
Add NDI to Mech.pdf PDF
T-38 CTP Optional Priced CLIN Workload Information.docx DOCX document
FA489010R0008_0001.pdf PDF
Langley AFB WD 2005-2544 rev 12.pdf PDF
PWS Addendum 1 Description of Services to Accept and Regenerate 15 T-38 Aircraft.docx DOCX document
Whiteman AFB WD 2005-2308 rev 12.pdf PDF
CDRL A010 Safety and Health Plan.doc DOC document
T-38 CTP Optional Priced CLIN Workload Information.docx DOCX document
T-38 CTP Projected Force Structure and Flying Hours.docx DOCX document
PWS Addendum 1 Description of Services to Accept and Regenerate 15 T-38 Aircraft.docx DOCX document
Section B CLIN Schedule for New T-38 CTP Contract 14 Jan 11.docx DOCX document
T-38 Final Preproposal Conf Attendees list.docx DOCX document
Combined Final T-38 PPC Brief.pptx PPTX presentation
AFOSHSTD91-110.pdf PDF
AFOSHSTD48-9.pdf PDF
T-38 RFP Q A as of 10 Jan 2011.docx DOCX document
T-38 RFP DD254.pdf PDF
Pre-Proposal_Conference_Letter_to_Industry.docx DOCX document
Offical Question--Pre Proposal Conference.docx DOCX document
T-38 CTP Award Fee Plan - 21 Dec 10.docx DOCX document
T-38 CTP Sections L and M 04 Jan 2011.docx DOCX document
Appendix M - Proposal Incorporations.docx DOCX document
WD 2005-2308 rev 10.pdf PDF
WDs CBAs CAM 2010.pdf PDF
WD 2005-2056 rev 12.pdf PDF
T-38 CTP RFP 04 Jan 2011.docx DOCX document
FA4890-10-R-0008A T-38 RFP PWS Appendices List 04 Jan 2011.docx DOCX document
T-38 CTP PWS 04 Jan 2011.docx DOCX document
T-38_CBA_Aug_2010.pdf PDF
WD 2005-2512 rev 12.pdf PDF
1T-38-847.PDF PDF
1T-38-845C.pdf PDF
1T-38-840.pdf PDF
1T-38-840C.pdf PDF
1T-38-850.pdf PDF
1T-38-842.pdf PDF
1T-38-848.pdf PDF
1T-38-849.pdf PDF
1T-38-845.pdf PDF
1T-38-843.pdf PDF
Langley_753_2.pdf PDF
HPIM0602.JPG JPG image
Show 40 more

Latest 50 of 189 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

T-38 RFP Q&A as of 17 Jan 2011

T-38 RFP Q&A:

1. Ques: Reference Appendix G (CDRLs): CDRL A002, Contingency Strike Plan, and CDRL A003, Labor Relations Plan, indicate they are to be submitted with the proposal. Section L provides no instructions for doing this. Should these deliverables/plans be submitted with the proposal? If so, are they included in page count and should we follow the CDRL format instructions and technical instructions for number of copies, etc?

Government answer:

The two deliverables (Strike Plan and Labor Relations Plan) should be submitted with the proposal as directed by CDRLs A002 and A003 following CDRL format instructions. Include these in the Mission Capability Volume as addendums. These addendum pages will NOT count against the page total for that volume (75). Number of copies should follow directions for Mission Capability Volume (Orig + 5).

The two deliverables will NOT be comparatively evaluated with other proposals. The only evaluation will be "submitted as required by CDRL - Yes/No".

2. Ques: Reference PWS Section D, 3.1, Performance of Service during Crisis Declared by the National Command Authority. We could not find a reference for this in Section H. Should this be Section I, 5352.223-9002, Requirements Affecting Contractor Personnel Performing Mission Essential Services?

Government answer:

Reference should be Section I not H.

3. Ques: Reference Attachment 3, Section L, Sample Past Performance Questionnaire Cover Letter. Para. 3 of the Sample Past Performance Questionnaire Cover Letter includes this statement addressed to the recipient of the questionnaire, "Request your written response no later than XX [15 calendar days after release of solicitation]." which would be 19 Jan 11. Should offerors include this date in the cover letter?

Government answer:

Date of 19 Jan 11 should be included in the cover letter.

4. Ques: Reference Schedule B Optional CLINs 1042, 2042, 3042, 4042 and 5042.

Is pricing expected on unnamed location in the CLINs named?

Government answer:

Yes pricing is expected. The Government feels that sufficent data has been provided for other locations that an offeror can make a realistic pricing bid for an additional location.

5. Ques:

CLIN 0100
The CLIN requires the contractor to price a transition period at Tyndall AFB starting 1 AUG 11. The current timeline for the arrival of the first T-38 is SEPT-OCT 11. If the contract start date and squadron stand up date at Tyndall remain the same, what will the transition period at Tyndall actually entail? Will the new contractor actually be putting the entire maintenance operation in place and not just performing transition duties?

Government answer:

The contractor will be responsible for normal transition activities like those outlined in the contract RFP Section L. The government is responsible to establish the Tyndall operating location.

6. Ques: Reference: Section B CLINs 0030, 1030, 2030, 3030, 4030, and 5030 (travel CLINs) reference Section A Paragraph 4.1.9 and JTR Comment: PWS Section A, Paragraph 4.1.9 46TG Publications has nothing to do with travel.

Question: What is the correct reference?

Reference: Section B CLINs 0030, 1030, 2030, 3030, 4030, and 5030 (travel CLINs) reference Section A Paragraph 4.1.10. and JTR. PWS Section A, Paragraph 4.1.10 46TG Deployments

7. Ques: Reference: Section B CLIN 0038 FY 12 (One-Time CLIN) Aircraft Regeneration Support at Holloman CRF Comment: PWS Section A, Paragraph 1.7.1 Aircraft Acceptance and Regeneration. For FY 12 the Government requires 7 T-38 aircraft removed from the Aerospace Maintenance and Regeneration Group (AMARG) be regenerated IAW PWS Addendum #1.

Question: Should PWS Section A, Paragraph 1.5 Projected CTP Program Force Structure for FY 12 number of aircraft be affected by these 7 aircraft?

Government answer:

The 7 aircraft identified for regeneration will be assigned to Tyndall AFB, FL within the 10 total aircraft identified in paragraph 1.5. The government has projected 3 aircraft assigned and on-station at Tyndall 1 Oct 2011. Seven remaining aircraft projected for Tyndall will require regeneration.

8. Ques: Reference: Section B CLIN 1039 FY 13 increase of 3 additional T-38 aircraft for Organizational Maintenance support at Tyndall AFB Question: Should PWS Section A Paragraph 1.5 Projected CTP Program Force Structure for FY 13 number of aircraft be affected by these 3 aircraft?

Government answer:

The Government has identified the approved force structure in PWS Section A paragraph 1.5. CLIN 1039 is identified as a Priced Optional CLIN. This force structure decision is probable, however it has not been made. Therefore, the effort is not included in paragraph 1.5. The government has requested this option be priced should it be exercised.

9. Ques: Reference: Section B CLIN 1040 FY 13 increase of 7 additional aircraft for Organizational Maintenance Support at Langley AFB Question: Should PWS Section A, Paragraph 1.5 Projected CTP Program Force Structure for FY 13 number of aircraft be affected by these 7 aircraft?

Government answer:

The Government has identified the approved force structure in PWS Section A paragraph 1.5. CLIN 1040 is identified as a Priced Optional CLIN. This force structure decision is probable, however it has not been made. Therefore, the effort is not included in paragraph 1.5. The government has requested this option be priced should it be exercised.

10. Ques: Reference: Section B CLIN 2042 Y 14 Organizational Maintenance for T-38 support for 7 T-38sw at a location TBD.

Question: Should PWS Section A, Paragraph 1.5 Projected CTP Program Force Structure for FY 14 Number of aircraft be affected by these 7 aircraft?

Government answer:

The Government has identified the approved force structure in PWS Section A paragraph 1.5. CLIN 2042 is identified as a Priced Optional CLIN. This force structure decision is probable, however it has not been made. Therefore, the effort is not included in paragraph 1.5. The government has requested this option be priced should it be exercised.

11. Ques: Reference: CLIN 5042 Six-month extension Optional CLIN Quantity 12 Question. Should the CLIN quantity be 6 vice 12?

Yes, the quantity is 6. the error was corrected