T-38 RFP Q A as of 10 Feb 2011.docx

DOCX document 31 KB Posted

Attached to
T-38 Companion Trainer Program (CTP)
Solicitation number
FA4890-10-R-0008A
Issued by

About this file

Updated Q A IRT Amendment 1.

View the file

Other files

File Type Posted
T-38 Award Synopsis -.doc DOC document
T-38 RFP Q A as of 3 Feb 2011.docx DOCX document
Langley MOU.pdf PDF
Tyndall AFB WD 2005-3008 rev 12.pdf PDF
T-38 CTP PWS 3 Feb 2011.docx DOCX document
CDRL A010 Safety and Health Plan.doc DOC document
T-38 CTP Projected Force Structure and Flying Hours.docx DOCX document
Add NDI to Mech.pdf PDF
T-38 CTP Optional Priced CLIN Workload Information.docx DOCX document
FA489010R0008_0001.pdf PDF
Langley AFB WD 2005-2544 rev 12.pdf PDF
PWS Addendum 1 Description of Services to Accept and Regenerate 15 T-38 Aircraft.docx DOCX document
Whiteman AFB WD 2005-2308 rev 12.pdf PDF
CDRL A010 Safety and Health Plan.doc DOC document
T-38 CTP Optional Priced CLIN Workload Information.docx DOCX document
T-38 CTP Projected Force Structure and Flying Hours.docx DOCX document
PWS Addendum 1 Description of Services to Accept and Regenerate 15 T-38 Aircraft.docx DOCX document
Section B CLIN Schedule for New T-38 CTP Contract 14 Jan 11.docx DOCX document
T-38 Final Preproposal Conf Attendees list.docx DOCX document
Combined Final T-38 PPC Brief.pptx PPTX presentation
AFOSHSTD91-110.pdf PDF
AFOSHSTD48-9.pdf PDF
T-38 RFP Q A as of 17 Jan 2011.docx DOCX document
T-38 RFP Q A as of 10 Jan 2011.docx DOCX document
T-38 RFP DD254.pdf PDF
Pre-Proposal_Conference_Letter_to_Industry.docx DOCX document
Offical Question--Pre Proposal Conference.docx DOCX document
T-38 CTP Award Fee Plan - 21 Dec 10.docx DOCX document
T-38 CTP Sections L and M 04 Jan 2011.docx DOCX document
Appendix M - Proposal Incorporations.docx DOCX document
WD 2005-2308 rev 10.pdf PDF
WDs CBAs CAM 2010.pdf PDF
WD 2005-2056 rev 12.pdf PDF
T-38 CTP RFP 04 Jan 2011.docx DOCX document
FA4890-10-R-0008A T-38 RFP PWS Appendices List 04 Jan 2011.docx DOCX document
T-38 CTP PWS 04 Jan 2011.docx DOCX document
T-38_CBA_Aug_2010.pdf PDF
WD 2005-2512 rev 12.pdf PDF
1T-38-847.PDF PDF
1T-38-845C.pdf PDF
1T-38-840.pdf PDF
1T-38-840C.pdf PDF
1T-38-850.pdf PDF
1T-38-842.pdf PDF
1T-38-848.pdf PDF
1T-38-849.pdf PDF
1T-38-845.pdf PDF
1T-38-843.pdf PDF
Langley_753_2.pdf PDF
HPIM0602.JPG JPG image
Show 40 more

Latest 50 of 189 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

T-38 RFP Q&A as of 10 Feb 2011

T-38 RFP Q&A:

1. Ques: Reference Appendix G (CDRLs): CDRL A002, Contingency Strike Plan, and CDRL A003, Labor Relations Plan, indicate they are to be submitted with the proposal. Section L provides no instructions for doing this. Should these deliverables/plans be submitted with the proposal? If so, are they included in page count and should we follow the CDRL format instructions and technical instructions for number of copies, etc?

Government answer:

The two deliverables (Strike Plan and Labor Relations Plan) should be submitted with the proposal as directed by CDRLs A002 and A003 following CDRL format instructions. Include these in the Mission Capability Volume as addendums. These addendum pages will NOT count against the page total for that volume (75). Number of copies should follow directions for Mission Capability Volume (Orig + 5).

The two deliverables will NOT be comparatively evaluated with other proposals. The only evaluation will be "submitted as required by CDRL - Yes/No".

2. Ques: Reference PWS Section D, 3.1, Performance of Service during Crisis Declared by the National Command Authority. We could not find a reference for this in Section H. Should this be Section I, 5352.223-9002, Requirements Affecting Contractor Personnel Performing Mission Essential Services?

Government answer:

Reference should be Section I not H.

3. Ques: Reference Attachment 3, Section L, Sample Past Performance Questionnaire Cover Letter. Para. 3 of the Sample Past Performance Questionnaire Cover Letter includes this statement addressed to the recipient of the questionnaire, "Request your written response no later than XX [15 calendar days after release of solicitation]." which would be 19 Jan 11. Should offerors include this date in the cover letter?

Government answer:

Date of 19 Jan 11 should be included in the cover letter.

4. Ques: Reference Schedule B Optional CLINs 1042, 2042, 3042, 4042 and 5042.

Is pricing expected on unnamed location in the CLINs named?

Government answer:

Yes pricing is expected. The Government feels that sufficent data has been provided for other locations that an offeror can make a realistic pricing bid for an additional location.

5. Ques:

CLIN 0100
The CLIN requires the contractor to price a transition period at Tyndall AFB starting 1 AUG 11. The current timeline for the arrival of the first T-38 is SEPT-OCT 11. If the contract start date and squadron stand up date at Tyndall remain the same, what will the transition period at Tyndall actually entail? Will the new contractor actually be putting the entire maintenance operation in place and not just performing transition duties?

Government answer:

The contractor will be responsible for normal transition activities like those outlined in the contract RFP Section L. The government is responsible to establish the Tyndall operating location.

6. Ques: Reference: Section B CLINs 0030, 1030, 2030, 3030, 4030, and 5030 (travel CLINs) reference Section A Paragraph 4.1.9 and JTR Comment: PWS Section A, Paragraph 4.1.9 46TG Publications has nothing to do with travel.

Question: What is the correct reference?

Government answer:

Reference: Section B CLINs 0030, 1030, 2030, 3030, 4030, and 5030 (travel CLINs) reference Section A Paragraph 4.1.10. and JTR. PWS Section A, Paragraph 4.1.10 46TG Deployments

7. Ques: Reference: Section B CLIN 0038 FY 12 (One-Time CLIN) Aircraft Regeneration Support at Holloman CRF Comment: PWS Section A, Paragraph 1.7.1 Aircraft Acceptance and Regeneration. For FY 12 the Government requires 7 T-38 aircraft removed from the Aerospace Maintenance and Regeneration Group (AMARG) be regenerated IAW PWS Addendum #1.

Question: Should PWS Section A, Paragraph 1.5 Projected CTP Program Force Structure for FY 12 number of aircraft be affected by these 7 aircraft?

Government answer:

The 7 aircraft identified for regeneration will be assigned to Tyndall AFB, FL within the 10 total aircraft identified in paragraph 1.5. The government has projected 3 aircraft assigned and on-station at Tyndall 1 Oct 2011. Seven remaining aircraft projected for Tyndall will require regeneration.

8. Ques: Reference: Section B CLIN 1039 FY 13 increase of 3 additional T-38 aircraft for Organizational Maintenance support at Tyndall AFB Question: Should PWS Section A Paragraph 1.5 Projected CTP Program Force Structure for FY 13 number of aircraft be affected by these 3 aircraft?

Government answer:

The Government has identified the approved force structure in PWS Section A paragraph 1.5. CLIN 1039 is identified as a Priced Optional CLIN. This force structure decision is probable, however it has not been made. Therefore, the effort is not included in paragraph 1.5. The government has requested this option be priced should it be exercised.

9. Ques: Reference: Section B CLIN 1040 FY 13 increase of 7 additional aircraft for Organizational Maintenance Support at Langley AFB Question: Should PWS Section A, Paragraph 1.5 Projected CTP Program Force Structure for FY 13 number of aircraft be affected by these 7 aircraft?

Government answer:

The Government has identified the approved force structure in PWS Section A paragraph 1.5. CLIN 1040 is identified as a Priced Optional CLIN. This force structure decision is probable, however it has not been made. Therefore, the effort is not included in paragraph 1.5. The government has requested this option be priced should it be exercised.

10. Ques: Reference: Section B CLIN 2042 Y 14 Organizational Maintenance for T-38 support for 7 T-38sw at a location TBD.

Question: Should PWS Section A, Paragraph 1.5 Projected CTP Program Force Structure for FY 14 Number of aircraft be affected by these 7 aircraft?

Government answer:

The Government has identified the approved force structure in PWS Section A paragraph 1.5. CLIN 2042 is identified as a Priced Optional CLIN. This force structure decision is probable, however it has not been made. Therefore, the effort is not included in paragraph 1.5. The government has requested this option be priced should it be exercised.

11. Ques: Reference: CLIN 5042 Six-month extension Optional CLIN Quantity 12 Question. Should the CLIN quantity be 6 vice 12?

Government answer:

Yes, the quantity is 6. the error was corrected Questions 12 thru 28:

No.
Document (RFP, PWS)
Page No.
Para No.
Question
Date/Answers
12
RFP
188
Clauses
What is the payment process? Did not find the Progress Payment Clause, or the Milestone Payment Clause, Performance Based Payment Clause, or even the Prompt Payment Clause. If we submit combo WAWF documents – what do we place on those documents?
The following clauses are in the RFP related to the payment process: Section I – 52.232-1, 52.232-8, 252.204-7006, & 252.232-7003.

Instructions for Invoicing under WAWF are located in Section G.

13
RFP
187
Clauses
Clause 52.204-10 is required in proposals > $500M per 4.1401(a). Should this clause be removed?
Clause 52.204-10 has been removed.
14
RFP
189
Clauses
Clause 252.243-7002 – REA’s. Can you provide history of REA’s on existing and previous contracts (e.g. # of REA’s and any challenges with payment of these requests from the contractor(s)? With a proposal that includes some gray areas over and above work often is required, and this may be one method for contractors to receive funding
REAs and the resultant Government decision are non-releasable information and will not be provided under this solicitation.
15
RFP
Clauses
What is proposed process for managing over and above work on FFP CLINS? Contract mod, or REA’s?
Contract modification unless otherwise directed by the Contracting Officer.
16
PWS
43
5.6
Vehicles – What vehicles will contractor need to provide and maintain on each of the bases included in this proposal?
All required general purpose vehicles including a suitable T-38 aircraft towing vehicle. The government will provide any other special vehicles.
17
PWS
Will contractor be required to remove propulsion engines from aircraft? If so, what equipment will be required and provided by host or contractor?
Yes, the contractor will be required to remove/replace engines. All required engine maintenance and support equipment is government provided.
18
RFP
187
Clauses
52.215-11 is listed with an effective date of Oct 1997. That clause and others have been updated. 52.215-11’s current effective date is Oct 2010. Will the government “scrub” each of the clauses in section I and elsewhere to ensure the most recent effective date is provided?

The clauses have been reviewed and updated with the most current versions within our contract writing system (PD2).

19
RFP
200 - 201
Section J
The CBA provided only covers Holloman, Beale, and Whiteman AFBs. For the purpose of pricing Langley and Tyndall, should the local SCA Wage Determinations be used, are there existing CBAs for Langley and Tyndall, or will the current CBA be expanded to cover the other locations?
Wage determinations for Langley and Tyndall have ben Posted to FBO to be used for those locations. WD 2005-2544 Rev 12, WD 2005-3008 Rev 12 respectively.
20
RFP
200 - 201
Section J
The CBA provided only covers Holloman, Beale, and Whiteman AFBs. For the purpose of pricing, what Wage Determination should be used for the TBD location?
Reference revised Appendix E document: Optional Priced CLINs Workload Informantion for details regarding the TBD location.

Summarization: For pricing aspects of the technical approach that are not specifically direct to utilize a specific location as a basis (e.g. use Holloman for CRF), then utilize the most expensive wage determination location provided by the Government for rates to utilize.

21
PWS
36
5.2.3.3
Do primary and alternate Information Security Managers need to be appointed at all locations?
Yes.
22
PWS
36
5.2.4
Does the Information Technology Hardware Asset Management Program need to be administered at each location – including the appointment of Equipment Custodians?
Yes.
23
PWS
38
5.3.9
Does a Site Security Manager need to be appointed for each location?
Yes.
24
PWS

CBA

27-29

3.3.13 – 3.3.13.5 3.3.13.7 Appendix A

Appendix A of the CBA indicates that A/C Painters are not used at Holloman. However, PWS paragraphs 3.3.13 – Corrosion Control, 3.3.13.1 – Corrosion Facility Limitations, 3.3.13.2 – Aircraft Paint Condition, 3.3.13.3 – Aircraft Top Coats, 3.3.13.4 – Full Corrosion Treatment, 3.3.13.5 – Paint Condition of Static Display Aircraft, , and 3.3.13.7 – Holloman AFB Heritage Park all contain work that is generally performed by Aircraft Painters. Please advise which CBA Labor Classification is currently used for performing painting tasks.
Aircraft painters were re-designated as aircraft mechanics through the CBA.
25
RFP
200
Att. 3
Neither Langley AFB nor Tyndall AFB are covered by a CBA so they should be priced using an SCA AWD for those areas. Please provide the appropriate SCA AWDs for Tyndall and Langley.
Wage determinations for Langley and Tyndall have ben Posted to FBO to be used for those locations. WD 2005-2544 Rev 12, WD 2005-3008 Rev 12 respectively.

WD 2005-2308

WD 2005-2308 Revision 10 dated 10/29/2009 is outdated. In many cases the wages are incorrect and it does not reflect the Health and Welfare increase to $3.50.

Recommendation: Use 2005-2307 Revision 11 dated 09/17/2010 WD 2005-2308 Revision 12, dated 17 Sep 2010 has been posted on FBO.

27
RFP updated Section B

CLIN Schedule for New T-38 CTP Contract 14 Jan 11

0038
Quantity and Unit blocks indicate this CLIN is for 6 months. Narrative states:

“FY 12 Aircraft acceptance and regeneration actions in accordance with PWS Section A, Paragraph 1.7.1. Period of performance is from 01 Oct 11 thru 30 Sep 12” - which is 12 months. Please clarify.

Schedule B now revised. Period of performance is 01 Oct 11 thru 31 Mar 12.

28
RFP, PWS

CBA, Appendix C

Upon a closer look at Appendix C to the CBA there are no costs included for employee contributions or company contributions for the Medical, Dental, Vision, Short Term Disability, Life Insurance and AD&D commencing 10/1/2011 (Base Yr) OP 1. Please provide this information for period beginning 10/1/2010?

IAW FAR 22.1008-2 -- Section 4(c) Successorship with Incumbent Contractor Collective Bargaining Agreement:

“Section 4(c) of the Act provides that a successor contractor must pay wages and fringe benefits (including accrued wages and benefits and prospective increases) to service employees at least equal to those agreed upon by a predecessor contractor under the following conditions: … (3) The incumbent prime contractor or subcontractor is furnishing such services through the use of service employees whose wages and fringe benefits are the subject of one or more collective bargaining agreements.”

A revised CBA has been uploaded with this RFP. There is no additional data available to provide other than what is already stated in the existing CBA.

29. Ques: Reference: Section B, 016-019 series CLINs, PWS 3.3.13.4 Question: Earlier versions of the PWS indicated a requirement to strip 20 aircraft over the period of the contract (PWS posted 1 Jun 10) and 4 per year (PWS 1 Sep 10). The final CLIN structure shows a quantity of 5 aircraft (2 ACC, 1 Beale, 1 Whiteman, 1 AFMC) stripped per year in the Base Year and in Option Years One and Two for a total of 15 aircraft. CLINs 016-019 for Option Years Three, Four and the Six-Month Extension show NTE values that infer aircraft will be stripped, but no quantity is indicated in those CLINs. Is there a requirement to strip aircraft in Option Years Three, Four and the Six-Month Extension? If so, should a quantity be inserted in each CLIN? If not, should an NTE value be provided for those CLINs?

Government Answer: The T-38 CTP Schedule B was adjusted to reflect a quantity of aircraft each CLIN, each year, including the potential 6-month extension. The T-38 CTP PWS is adjusted as follows in paragraph 3.3.13.4 (inserted) “Although the Schedule B CLINs will indicate up to 28 potential full strips the government projects only 20 full strips over the term of this contract. Inclusion of the additional CLINS will allow the government flexibility in allocating full strip aircraft across ACC, AFGSC and AFMC aircraft as aircraft paint condition dictates.”

30. Ques: Reference: Section B, CLIN 5010, PWS 1.5 Question: CLIN 5010 (Intermediate Maintenance provided by Holloman CRF) mentioned "T-38s assigned to Holloman, Langley and Tyndall AFBs" in the CLIN description. Should Holloman be deleted from the CLIN description since the 7 ACC T-38 aircraft will have been transferred from Holloman to Tyndall in the first Option Year (FY13)?

Government Answer: CLIN 5010 corrected to read "T-38s assigned to Langley and Tyndall AFBs"

31. Ques: Reference: PWS 3.3.8 NDI Question: Please clarify the statement “ Ensure Civil Service and contracted NDI technicians are certified IAW NAS 410.” What is the service provided expected to do in regards to Civil Service Technicians?

Government Answer: Removed reference to civil service within PWS paragraph 3.3.8 .

32. Ques: Reference: PWS 4.2.1 Question: Please clarify what is meant at the last sentence that states “PM Review of requirement. ) Government Answer: Removed erroneous statement “PM review of requirement.”

33. Ques: Reference: Instructions Section L-8.1 and Section M-3.3.1.2.

Question: Second sentence states: “ This volume of the proposal shall consist of two parts: technical and risk.” In addition, sentences 5 through 8 of the same paragraph addresses at length how the offerors should address risk in their proposal. However, there is no Subfactor in Section L showing to address risk as a proposal section nor in the pre-proposal conference slides, instructions for a Risk Proposal Section. Does the technical proposal consist of two parts as described in L-8.1 and is the risk section included in the page count?

Government Answer: Risk should be addressed at the Sub-factor level.

34. Ques: Reference: PWS Section B, Service Summary, paragraph 1.5 Services Summary Table, Performance Objective #2, Resource Management.

Question: Under the referenced performance objective titled “Resource Management” there are references to PWS Section A, Para 2.3, 2.12, 5.4.7, Section C, Para 1.2, 1.3 Appendix D. In addition, the corresponding Performance Standards listed for Resource Management state “Personnel: 200% task coverage at 100% availability, meaning two persons qualified for each task with one available at all times”. The PWS references do not seem to correspond to this Performance Standard.

Government Answer: Corrected PWS references for PWS Section B, Service Summary, paragraph 1.5 Services Summary Table, Performance Objective #2, Resource Management. Expanded language in PWS Section A paragraph 2.2.4.1 concerning “200% task coverage, 100% availability.”

35. Ques: Reference: PWS Section B, Service Summary, paragraph 1.5 Services Summary Table, Performance Objective #2, Resource Management.

Question: Request the Government clarify the intent of this Performance Standard relative to the PWS sections and paragraphs referenced in the Performance Objective column of the table or other PWS sections. The title of Section A, Para 2.3 is “Contract Administration”; the title of 2.12 is “Data Integrity”; the title of 5.4.7 is “Repair Cycle Assets”; Section C references address Government Furnished Property and Services; and Appendix D covers the Quality Management System Requirements. Is it possible that the applicable corresponding PWS references for the 200% task coverage at 100% availability performance standard include Section A, Para 3.2 “Organizational Maintenance”, and 3.3 “Centralized Repair Facility (Holloman) Intermediate Level Maintenance Support”? Please clarify.

Government Answer: References provided to indicate applicable passages within PWS to the specified area. Corrected PWS references for PWS Section B, Service Summary, paragraph 1.5 Services Summary Table, Performance Objective #2, Resource Management. Expanded language in PWS Section A paragraph 2.2.4.1 concerning “200% task coverage, 100% availability.”

PERFORMANCE OBJECTIVE
PERFORMANCE STANDARD
PERFORMANCE THRESHOLD
1.
Program Management:

Provide and maintain comprehensive, pro-active, integrated Program Management that focuses on meeting or exceeding PWS requirements and ensures compliance to all mandatory instructions, directives, statutory and regulatory requirements.

PWS Section A, Para 2.0, 2.3, 2.12

IAW PWS requirements.

-Meet or exceed PWS requirements 100% of the time.

--Perform Management Reviews --Take action as a result of those reviews --Analyze data to make fact-based decisions -- CDRLs and MIS 100% on time delivery and accuracy

No major non-conformances allowed.

2.

Resource Management:

Provide and maintain, comprehensive Resource Management that focuses on meeting or exceeding PWS requirements and ensures compliance to all mandatory instructions, directives, statutory and regulatory requirements.

Parts/Equipment: PWS Section A, Para 5.4.7

Inventory: PWS Section A, paragraph 5.4.9, 5.4.17.1 and Section C Para 1.4

Personnel: PWS Section A paragraph 2.2.4.1

Infrastructure: PWS Section C, paragraph 1.2, 1.3

Parts/Equipment:

Due In From Maintenance (DIFM) turn in times = 24 hours for 2-level components and six calendar days for all others.

Inventory Accuracy Rates:

(Equal to or above) Nonexpendable Equipment: 98% CA/CRL Equipment: 100% Repairable spares: 98% Consumable: 95%

Personnel:

200% task coverage at 100% availability, meaning two persons qualified for each task with one available at all times.

Infrastructure:

Maintain a clean and professional working environment.

No major non-conformances allowed.

36. Ques: Reference: CLINs X005, CLINs X008, CLINs 1039, 2039, 3039, 4039, 5039, CLINs 1040, 2040, 3040, 4040, 5040, where “X” represents the performance period option.

Discussion: The solicitation was issued with Department of Labor Area Wage Determinations for the areas covering Holloman, Whiteman and Beale AFBs, along with the corresponding Collective Bargaining Agreements. However, there were no local AWDs posted for the areas covering Langley and Tyndall AFBs, although the CBA states that it will be applicable if new sites are added.

Question: Does the Government plan to issue applicable AWDs for these sites?

Government Answer: The following wage determinations have been posted on FBO for use for the following sites:

Langley AFB – WD 2005-2544, Rev 12, dated 15 Jun 2010 Tyndall AFB – WD 2005-3008, Rev 12, dated 15 Jun 2010

37. Ques: Per the revised RFP in Amendment 11 (A001), we noticed that a number of CLINs were deleted. Please verify that these CLINs were either deleted or pages in pdf are missing.

• The following CLINS were deleted in Amendment 11 (A0001):

• 2029 - 2040

• 3003 - 3012

• 3016 – 3027

• 3031 – 3042

• 4004 – 4012

• 4017 – 4027

• 4031 – 4042

• 5004 – 5014

• 5018 – 5028

• 5033 – 5042

Clarification requests

• CLIN 3002 – the pdf image didn’t capture the whole CLIN. We can assume there were no changes from the original RFP, but need confirmation.

• CLIN 4016 – “Amount” shows $15,000; “NTE” shows $34,000 for one unit. Please verify.

• CLIN 5032 - the pdf image didn’t capture the whole CLIN. We can assume there were no changes from the original RFP, but need confirmation.

Government Answer: Amendment 0001 had scanner errors in the pdf on Schedule B (the CLINs). No CLINs were deleted. Refer to original document for all CLINs with the exception of CLIN 5042. CLIN 5042 had a quantity change from 12 down to 6 units (to match the 6 month description field). No change to CLIN 3002. No change to CLIN 5032. CLIN 4016 remains $15,000. A split field (caused by the scanner error) shows the $34,000 of another CLIN.