Attachment 12 - RFI Log - B1383 and B1384 ISP Replacement and B123 Fiber Optic - Gov Reponse.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
Buildings 1383 and 1384 Inside Plant (ISP) Replacement and Building 123 Fiber Optic Work
Solicitation number
FA488725R0008
Issued by

About this file

The file is a Request for Information (RFI) Log for a federal contract opportunity to replace Inside Plant (ISP) systems and perform fiber optic work at Luke Air Force Base. The solicitation (FA488725R0008) is a Women-Owned Small Business (WOSB) set-aside for Buildings 1383, 1384, and Building 123, with a project scope involving low voltage and telecommunications infrastructure upgrades. Key details include a 270-calendar day performance period, work involving cable tray installation, conduit replacement, network cabling upgrades (Cat-6 plenum-rated), and fiber optic cable installations between multiple buildings.

The RFI log contains 77 detailed questions and responses covering technical specifications, installation requirements, electrical considerations, ceiling access, demolition expectations, and project logistics. Critical requirements include using EMT conduits, following specific UFC and BICSI standards, performing work during standard duty hours (0730-1630 Monday-Friday), and completing as-built drawings. Submittal turnaround time is 14 calendar days, with proposals originally due 21 July 2025 but extended to 7 August 2025 through two amendments. The project's estimated construction magnitude is between $500,000 and $1,000,000, with funds currently available and all prospective contractors required to be SAM-registered and WOSB-certified.

View the file

Other files

File Type Posted
Solicitation Amendment FA488725R0008 0003 SF 30.pdf PDF
Attachment 24 - B123 Rack Elevations.pdf PDF
Attachment 1 - SOW Luke AFB B1383 ISP Upgrade - 25July2025.pdf PDF
Attachment 18 - B1384 Comm Cabinet Rack Elevation.pdf PDF
Attachment 17 - B1383 Comm Cabinet Rack Elevation.pdf PDF
Solicitation Amendment FA488725R0008 0002 SF 30.pdf PDF
Attachment 19 - Luke AFB BLDG 528 - As-Built.pdf PDF
Attachment 10 - WD AZ20250039 dated 25 July 2025.pdf PDF
Attachment 22 - 2015 MAG Detail Drawings.pdf PDF
Attachment 23 - 2025 MAG Specifications for Public Works Construction.pdf PDF
Attachment 20 - As-Built bldg 1383.pdf PDF
Attachment 16 - B123 Communications Facility Drawings AS-BUILD 9-29-2022.pdf PDF
Attachment 2 - SOW Luke AFB B1384 ISP Upgrade - 25July2025.pdf PDF
Attachment 21 - As-Built 1384.pdf PDF
Solicitation Amendment FA488725R0008 0001 SF 30.pdf PDF
Attachment 11 - Anti-Terrorism Pamphlet.pdf PDF
Attachment 5 - Asbestos Recert Ltr B1383 Wiring Upgrade.pdf PDF
Attachment 15 - Section M Evaluation Factors For Award.pdf PDF
Attachment 12 - RFI Log - B1383 and B1384 ISP Replacement and B123 Fiber Optic.xlsx XLSX spreadsheet
Attachment 4 - AETC First 400 Feet Standard Guidance with Luke Supplemental May 2015 v4.pdf PDF
Attachment 7 - Asbestos Certification B528.pdf PDF
Attachment 9 - LUKE MASTER SPECS.zip ZIP file
Attachment 2 - SOW Luke AFB B1384 ISP Upgrade - 8 Jan 2025.pdf PDF
Attachment 10 - WD AZ20250039 dated 30 May 2025.pdf PDF
Attachment 13 - Past Performance Questionnaire.docx DOCX document
Attachment 3 - SOW Luke AFB FOC B123 to B528 and B530 - 10 April 2025.pdf PDF
Attachment 14 - Section L Instructions Conditions and Notices to Offerors.pdf PDF
Attachment 6 - Asbestos Recert Ltr B1384 Wiring Upgrade.pdf PDF
Solicitation - FA488725R0008.pdf PDF
Attachment 1 - SOW Luke AFB B1383 ISP Upgrade - 8 Jan 2025.pdf PDF
Attachment 8 - Asbestos Certification B530.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

REQUEST FOR INFORMATION LOG
CONTRACT #:SOLICITATION #: FA488725R0008B1383 and B1384 ISP Replacement and B123 Fiber Optic Work
TBD
SUBMITTED BY CONTRACTORTO BE COMPLETED BY GOVERNMENT
RFI #DATEDOCUMENTSHEET / PAGE / PARADISCIPLINEQUESTION / ISSUERESPONSE DATERESPONSEPOCCHANGE TO SOLICITATION REQUIRED (YES OR NO)DOCUMENT REVISEDQUESTION SUBMITTED BY
OFFICE SYMNAME
0013-Jul-25Low VoltageWhat are the design requirements for this project?7/7/25Follow guidelines in SOW, to include all applicable UFCs, Luke Specifications, AETC First 400 Feet Guidance Luke Supplement, referenced TIA standards, BICSI standards, etc. in Appendix A.56 CSMichael CarmineNoNo
0023-Jul-25Low VoltageIf we have to submit design requirements, can an additional 90 calendar days be added to the schedule for creation, submission, and approval of the design?7/9/25As Built Drawing are required per SOW section 2.2.8 for Fiber Optic Cable. As built drawing are required per SOW section 4.22 Bldg 1383 amd Bldg 1384. No additional time will be given for the as builts.56 CSMichael CarmineNoNo
0033-Jul-25Low VoltageHow long are electrical shutdowns?7/9/25Outage requests are processed by the 56th Civil Engineering Squadron and the prime contractor would complete an Outage Request Form for the duration of the outage to be evaluated and approved by 56 CES.56 CS & 56 CONSMichael Carmine & Kelli McDonaldNoNo
0043-Jul-25Low VoltageWhere is the laydown yard?7/3/25A laydown yard on base will be approved once the contract is awarded.56CONSKelli McDonaldNoNo
0053-Jul-25Low VoltageCan we assume all excavation material is clean?7/7/25Please refer to the Asbestos Report (Attachment-6)56 CSMichael CarmineNoNo
0063-Jul-25Low VoltageIs there onsite disposal for excavation material?7/7/25As per SOW, removal and disposal is the responsibility of the Contractor and to be disposed off-base.56 CSMichael CarmineNoNo
0073-Jul-25Low VoltageAs all three scope of work packages have a different period of performance, is it to be assumed that the period of performance for the contract will be longest of the three at one-hundred eighty (180) calendar days after the date of award?7/3/25Per the solicitation box 11, the period of performance for the whole project is 270 calendar days after recieving Notice to Proceed.56CONSKelli McDonaldNoNo
0083-Jul-25Low VoltageAs Buildings 1383 and 1384 are occupied and the need to terminate at work area outlets and cutover to the new system, how is the contractor expected to perform during normal work hours? Should the contractor expect to be working outside of normal work hours?7/7/25The expectation is for performance to occur during normal work hours.56 CSMichael CarmineNoNo
0093-Jul-25Low VoltageIs there a brand preference for ISP materials or can the Luke AFB I3A manual be provided?7/7/25There is no brand preference. Please refer to solicitation attachments for salient characteristics.56 CSMichael CarmineNoNo
0103-Jul-25Scopes of Work, SpecsVariousCablingDuring the site visit, it was noted that all new cabling throughout this project are to be CAT6A rather than CAT6 cabling, and that CAT6A should be Leviton brand. Please confirm.7/7/25Per the SOW, All new ethernet cabling and corresponding materials are Cat-6.56 CSMichael CarmineNoNo
0113-Jul-25Solicitation - FA488725R00084 of 30GeneralOn sheet 4 of the Solicitation document, it appears bidders are to provide separate CLIN pricing for 1) Building 1383, 2) Building 1384, and 3) Fiber Optic work between Building 123 to Building 528 and 530. However, there was some discussion at the site visit that these CLIN's might be revised in some way. Please provide revised bid form if changes to this cost breakdown are required.7/3/25The current solicitation CLIN structure is correct.56CONSKelli McDonaldNoNo
0123-Jul-25Scopes of WorkVariousEquipmentIn the project Scopes of Work, it is unclear which pieces of equipment are government-furnished and contractor-installed vs. contractor-furnished and contractor-installed. Please provide a list of equipment and responsibility matrix for which entity will be required to furnish and install each piece of equipment.7/7/25There is no governement furnished property. Cisco network switches in B1383 and B1384 are existing (plug and play).56 CSMichael CarmineNoNo
0133-Jul-25Scopes of WorkVariousElectricalIn the scopes of work, AC power circuits will need to be added into the existing buildings to serve new cabinets. During the site visit, a few existing electrical panels were opened, and it appeared that there was not sufficient spare capacity to add circuits to existing panels. Please provide electrical panel layouts, locations within the building, and nearest spare circuit capacity for required added circuits. If existing panels are full, it is possible that a new sub-panel will be required. Please clarify.7/11/25In Bldg 1383 Panel C in corridor 105 has enough available power to supply two 208v ckts. Bldg 1384 panel in the northwest hallway Panel C has enough power to supply 208v.56 CESEarnest PerkinsNoNo
0143-Jul-25Scopes of WorkVariousCablingDuring the site visit, patch cord quantities and lengths were briefly discussed. Please provide the lengths and quantities of Cat-6a patch cords for cross-connections within the rack cabinets (from the Cat-6a patch panels to the network Ethernet switches for all drops). Also, please provide the lengths and quantities of patch cords to be provided from the faceplates to user network devices (e.g., laptop, desktop, printer).7/7/25Per the SOW, all patch cords are Cat-6. The quanitity of patch cables will be double the number of new jacks installed.56 CSMichael CarmineNoNo
0152-Jul-25INSIDE PLANT WIRING UPGRADE, BUILDING 1383 &1384 SpecificationLow VoltageIn Building 1383, 1384 Could you please clarify which locations currently have existing outlets and which outlets will be new installations requiring conduits and boxes? This information will help us ensure proper planning and compliance with project requirements.7/7/25Please refer to SOW and SOW Attachment A Drawings, which states the total and the breakdown of drop outlets.56 CSMichael CarmineNoNo
0162-Jul-25INSIDE PLANT WIRING UPGRADE, BUILDING 1383 &1384 SpecificationLow VoltageIn the “INSIDE PLANT WIRING UPGRADE, BUILDING 1383 &1384 Specification”, Figure ATT-3 diagram, there is a diagram showing an Eaton UPS and Eaton Bypass. Are both Eaton items part of the bid scope?7/7/25Please refer to SOW 4.5.2.56 CSMichael CarmineNoNo
0172-Jul-25INSIDE PLANT WIRING UPGRADE, BUILDING 1383 &1384 SpecificationLow VoltageIn the “INSIDE PLANT WIRING UPGRADE, BUILDING 1383 &1384 Specification”, Figure ATT-4 diagram, shows CISCO C9300-48P-A POE Switches. Are the Cisco Switches part of the bid scope?7/7/25Please refer to SOW 4.6, the network switches are existing equipment that will be relocated to the newly installed comm cabinets.56 CSMichael CarmineNoNo
0182-Jul-25FOC to ITB to EB 528 & 530Low VoltageUnder the "FOC to ITB to EB 528 & 530" section 2.2.1.4.4 Innerduct. Please confirm if the 3" 3 cell innerducts is required for every newly installed conduit or only the conduit that requires fiber.7/7/25Yes, only conduit that has fiber installed will also have the innerduct installed for utilization. This is any existing or newly installed conduit that is part of a FOC run. Attachment Table 1, in SOW lists approx distances. Any newly installed innerduct requires mule tape and tracer wire.56 CSMichael CarmineNoNo
0192-Jul-25INSIDE PLANT WIRING UPGRADE, BUILDING 1383 &1384 SpecificationLow VoltagePlease confirm Color of Cat-6 Cables to be used.7/7/25Per SOW 4.9.3, blue for NIPRNet.56 CSMichael CarmineNoNo
0202-Jul-25Site PlansLow VoltageDuring a site review, we noted that several hallway ceilings are constructed with hard lids, leaving insufficient space for cable tray installation above the ceiling. Please advise on the following:
1.1. Hard Lid Hallways:
•- Is it permissible to install cable tray on top of the hard lid ceiling, if adequately supported?
•- Alternatively, may we hook/conduit through these areas using accessible points, such as walls or adjacent soffits?
2.2. Occupied Rooms:
•- Is routing cable tray through offices or classrooms acceptable if above-ceiling space is available?
•- Are there access or visibility restrictions we need to observe when routing through these occupied spaces? lids, leaving insufficient space for cable tray installation above the ceiling. Please advise on the following: Hard Lid Hallways:Is it permissible to install cable tray on top of the hard lid ceiling, if adequately supported?7/7/25Per SOW 4.7 and Attachment A. Drawings, Cable trays are needed on the main cable pathway annotated in the SOW in each drawing (Attachment A). These are proposed pathways and can be adjusted as needed due to space limitations or other issues that could be discovered during execution.

Cable ladders are needed in the comm rooms, if not already exisitng or if existing isn't sufficient enough for new cabling.

J-hooks are used to extend cabling from main pathway to drop outlets. If space is an issue above the ceiling in locations, J-hooks can be used in lieu of cable tray. However, the cable tray shall be used to the maximum extent possible.56 CSMichael CarmineNoNo
0212-Jul-25ElectricalDuring our site walkthrough of Buildings 1383 and 1384, we observed that the electrical panels currently installed appear to be at full capacity. We were unable to identify an available source for the cabinet circuits that are shown on the plans. Please clarify:

1.1. What is the designated source of power for the electrical circuits feeding the cabinets in Buildings 1383 and 1384?

2.2. If the existing panels are not intended to be used due to capacity limitations, will new panels or subpanels be provided?

3.3. Is there an alternate power source identified elsewhere in the design documents, or should provisions be made for panel upgrades or additions?7/11/251.1 Bldg 1383 desired panel for cabinets would be panel C in corridor 105. Bldg 1384 desired panel would also be panel C in the northwest corridor. 2.2 There is no government furnished property for this requirement. 3.3 Please reference As builts in attachments.56 CESEarnest PerkinsNoNo
0222-Jul-25ElectricalPer the contract drawings, cable tray is required to be installed in various interior areas where ceiling tiles and grid systems are present. In order to access these locations for installation, removal of ceiling tiles and potentially ceiling grid components may be necessary. Please confirm:
1.1. Is the electrical contractor responsible for the removal and reinstallation of ceiling tiles and/or ceiling grid to facilitate cable tray installation?
2.2. If so, will this work need to be coordinated with a specific trade (e.g., ceiling contractor), or will electrical be expected to perform all associated ceiling work?
3.3. Will repair or replacement of any ceiling components damaged during tray installation also fall under the electrical scope?7/7/25Yes, any removal and re-installation of ceiling tiles is in the scope of this project. Ceiling tiles can be removed and replaced unless the tile is damaged and then a new one will need to be contractor-provided and installed.56 CSMichael CarmineNoNo
0233-Jul-25GeneralPlease provide site visit sign in7/3/25Site visit sign-in sheet will not be provided.56CONSKelli McDonaldNoNo
0243-Jul-25GeneralPlease provide As-built for the work areas7/7/25Please see attachments.56 CSMichael CarmineNoNo
0253-Jul-25GeneralAre there project specific plans and specifications available7/7/25Follow guidelines in SOW and all associated UFCs, Luke Specifications, AETC First 400 Feet Guidance Luke Supplement, referenced TIA standards, BICSI standards, etc. in Appendix A. Please see As builts in Attachments56 CSMichael CarmineNoNo
0263-Jul-25GeneralIs the intent for this to be a Design / Build? If So7/7/25As Built Drawing are required per SOW section 2.2.8 for Fiber Optic Cable. As built drawing are required per SOW section 4.22 Bldg 1383 amd Bldg 1384.56 CSMichael CarmineNoNo
0273-Jul-25GeneralCan the Site Super wear 3 hats to include Superintendent, QCM and SSHO? Or, do these need to be separate people?7/7/25The Superintendent can perform safety responsibilities. Quality Assurance can not be performed by the Superintendent.56 CSMichael CarmineNoNo
0283-Jul-25GeneralIs the contractor responsible for third party testing?7/7/25Yes.56 CSMichael CarmineNoNo
0293-Jul-25Solicitation+-+FA488725R0008What type of Ceiling is in Building 1383, is it hardlid, dropped ceiling, open ceiling, combination of the three, etc.7/11/25Building 1383 has a drop ceiling.56 CESEarnest PerkinsNoNo
0303-Jul-25Solicitation+-+FA488725R0008Are you able to send photos of the ceiling structure in Building 1383?7/11/25Photos will be included as an attachment in the amendment.56 CSMichael CarmineNoNo
0313-Jul-25Solicitation+-+FA488725R0008What is the wall constructed of in Building 1383? Is it drywall or will we have to install conduit at each data location on a block wall?7/9/25Surface mount is allowed on non-drywall walls.56 CSMichael CarmineNoNo
0323-Jul-25Solicitation+-+FA488725R0008What type of Ceiling is in Building 1384, is it hardlid, dropped ceiling, open ceiling, combination of the three, etc.7/11/25Builing 1384 has a drop ceiling.56 CESEarnest PerkinsNoNo
0333-Jul-25Solicitation+-+FA488725R0008Are you able to send photos of the ceiling structure in Building 1384?7/11/25Photos will be included as an attachment in the amendment.56 CSMichael CarmineNoNo
0343-Jul-25Solicitation+-+FA488725R0008What is the wall constructed of in Building 1384? Is it drywall or will we have to install conduit at each data location on a block wall?7/11/25Surface mount is allowed on non-drywall walls.56 CSMichael CarmineNoNo
0353-Jul-25Solicitation+-+FA488725R0008Will there be another site walk so we can bring our excavating crew onsite?7/3/25No additional site walk is scheduled.56CONSKelli McDonaldNoNo
0363-Jul-25Solicitation+-+FA488725R0008Is there ceiling access in Building 1383?7/9/25Yes56 CSMichael CarmineNoNo
0373-Jul-25Solicitation+-+FA488725R0008Is there ceiling access in Building 1384?7/9/25Yes56 CSMichael CarmineNoNo
03830-Jun-25SOW 528 & 530, SOW 1383, SOW 1384What will the working hours for the project be?7/7/25As per SOW, standard duty hours are Mon-Fri, 0730 to 1630 local time.56 CSMichael CarmineNoNo
039SOW 528 & 530, SOW 1383, SOW 1384What would be the earliest start time?7/7/25As per SOW, standard duty hours are Mon-Fri, 0730 to 1630 local time.56 CSMichael CarmineNoNo
040SOW 528 & 530, SOW 1383, SOW 1384Will a location for material storage be provided?7/3/25A laydown yard on Luke AFB will be approved once the contract is awarded.56CONSKelli McDonaldNoNo
041SOW 528 & 530The asphalt in the parking lot is in poor condition. What is the expectation for asphalt restoration?7/11/25Please see attachments. Contractor is required to follow the MAG spec MAG. STD 212 for Potholing and MAG. 200-1 contractor can use option T-Top, Type A and B repair for trenches.56 CESEarnest PerkinsNoNo
042SOW 528 & 530Is there a requirement for a specific backfill material around vaults?7/9/25As per UFC 3-580-01 3-6.9.6 Backfilling, all excavated areas around new OSP supporting structures, conduits, and/or cables must be backfilled in accordance with the latest issuance of UFC 3-220-04FA.56 CSMichael CarmineNoNo
043SOW 528 & 530Paragraph 2.2.1.7.1.4 of the SOW states The Contractor shall use the method of horizontal directional drilling (HDD) on all paved surfaces but paragraph 2.2.1.7.1.5 states that the contractor shall install the appropriate physical protection required (concrete encasement, steel tube (casing) for buried PVC conduits or HDPE roll pipe. Please confirm if conduit is installed with the boring method that encasement of conduit is not required?7/7/25If boring, HDPE roll pipe must be Schedule 80 and follow applicable standards for minimum depth. As per UFC 3-580-01, Section 3-6.6.6 Restrictions, the HDD trenchless utility installation method may be used only in locations approved by the site owner. Conduits installed under roads by means of HDD must be of sufficient depth to clear existing utilities and meet the H-20 load ratings. The conduits placed by HDD must not directly enter an MH, but must be attached to conduit stub-outs that extend a minimum of 10 feet (3 meters) from the MH. The maximum radius curvature of a bore is limited to the maximum conduit diameter multiplied by 100 feet per inch (30.5 meters per 25 millimeters).56 CSMichael CarmineNoNo
044SOW 528 & 530What size and type of vaults are required for the OSP system?7/7/25As per AETC First 400 Feet Guidance, handholes, when specified, will be minimally 4’x4’x4’ inside dimensions and be provided with a grounding rod, cable rack supports, sump drain and pulling irons. Handhole covers will have a locking bar or other locking device to allow use of a padlock or other restriction to unauthorized entry. Covers shall be round and cast with “COMMUNICATIONS” exposed to the surface for easy identification.56 CSMichael CarmineNoNo
045SOW 528 & 530Is the underground 4” conduit schedule 80?7/7/25Yes, per SOW Section 2.2.1.7.1.1., Sch 80 is required.56 CSMichael CarmineNoNo
04630-Jun-25SOW 1383 & 1384Will the end user be responsible for taking down all photos on walls and moving furniture as required?7/7/25Yes56 CSMichael CarmineNoNo
047SOW 1383 & 1384The new cable trays shown on the drawings are in the main hallways/corridors of buildings 1383 and 1384 but during the site visit it was found that the majority of the corridors were fire rated (less the 12” from drop ceiling to hard fire rated lid) or have large ductwork running down the middle of them.
Would it be allowed to install the new cable tray above the fire rated corridor ceilings or above the ceilings inside the offices?7/7/25Cable trays are required on the main cable pathway annotated in the SOW section 4.7 and in each drawing (Attachment A).

Per SOW section 4.7, cable ladders are required in the comm rooms.

J-hooks are used to extend cabling from main pathway to drop outlets. If space is an issue above the ceiling in locations, J-hooks can be used in lieu of cable tray. However, the cable tray shall be used to the maximum extent possible.56 CSMichael CarmineNoNo
048SOW 1383 & 1384Paragraph 4.9.9 of the SOW states “If surface-mounted raceway is installed on wall surfaces, the surface-mounted raceway shall be secured with appropriate anchor and screw hardware and be “off white” in color unless otherwise noted. The surface-mounted raceway installed with adhesive tape is not authorized.”
During the site visit, it was mentioned wire molding in not preferable. The other option is to cut walls, install new conduits and boxes, then patch and paint wall. There is a huge cost difference in implementing each method. Please clarify this requiment and indicate if wire molding or inside-wall conduits is required.7/7/25As per SOW section 4.9.10, "The existing cable routes within the walls shall be reused where possible, provided they are within the general location of user drops." Reuse existing as much as possible.56 CSMichael CarmineNoNo
049SOW 1383 & 1384Is flexable conduit allowed to be used inside wall instead of EMT to run comm cables?7/8/25No. As per UFC 3-580-01, design conduit systems in accordance with TIA-569. Install EMT conduit from the cable backbone distribution system, whether cable tray or enclosed duct, to each outlet. For standard outlets, use a minimum 1-inch (27-millimeter) EMT conduit.56 CSMichael CarmineNoNo
050SOW 1384B1384 SOW specified (60) days period of performance. Can you extend to accommodate Luke access approvals, submittals and approval, and construction?7/3/25Per the solicitation box 11, the POP for the whole project is 270 calendar days after recieving Notice to Proceed.56CONSKelli McDonaldNoNo
051SOW 1383B1383 SOW specified (45) days period of performance. Can you extend to accommodate Luke access approvals, submittals and approval, and construction?7/3/25Per the solicitation box 11, the POP for the whole project is 270 calendar days after recieving Notice to Proceed.56CONSKelli McDonaldNoNo
052SOW 1384The Large conference room in 1384 has wall paper and may be impossible to match if we cut and patch the walls in this room. Is it acceptable to install surface mounted wire molding for all new drops?7/7/25Surface mount is allowed on non-drywall walls.56 CSMichael CarmineNoNo
053SOW 1383 & 1384Is the standard for ISP cabling Cat 6A plenum?7/7/25Per SOW, Standard is Category-6 Plenum-rated.56 CSMichael CarmineNoNo
054SOW 1383 & 1384Is there a required fill ratio for the J-hooks from the cable to drop location?7/7/25Yes, as per UFC 3-580-01, Section 2-3.5.3.1 Existing Facilities, maximum fill ration shall not exceed 50%56 CSMichael CarmineNoNo
055SOW 1383 & 1384Is a service loop required for the ISP cabling? If so which end?7/7/25Yes. As per AETC First 400 Feet Guidance, maintenance loops will be installed at both ends to accommodate future cabling system changes. Minimum length requirements are 10 feet at the Comm Room and 1 foot at the user outlet.56 CSMichael CarmineNoNo
056SOW 1383 & 1384Will there be a shutdown period to cut-over to the new ISP system?7/7/25Yes. Coordination will be done with CO/CS.56 CSMichael CarmineNoNo
057SOW 1383 & 1384What is the extent of the old comm system demolition? Is it required to demo the old cable trays, raceways, boxes, etc?7/8/25If there is existing infrastructure that is supporting inside cable plant and that same inside cable plant is removed (old wiring) the associated infrastructure should be removed as part of the demo, so long as those items are not being reused to support the new cable infrastructure (i.e. boxes, non-reutilized cable supports, etc…).56 CSMichael CarmineNoNo
058SOW 528 & 530, SOW 1383, SOW 1384Please confirm the contractor is not required to upgrade the existing dorm rooms used as Telecom room to the First 400 Feet requirements.7/7/25No. No room modifications/upgrades of the dorm rooms are part of this project scope.56 CSMichael CarmineNoNo
059SOW 1383 & 1384Is innerduct isntalled in the existing underground conduits and MM/HH?7/8/25Per our records, there is available innerduct cells in existing conduits except for between MH-68 and HH-2C-1; there will need to be a new 3-cell innerduct installed in this existing pathway56 CSMichael CarmineNoNo
060SOW 528 & 530, SOW 1383, SOW 1384What is the Submittal turnaround time?7/3/2514 calendar days from date the government recieves submittal.56CONSKelli McDonaldNoNo
0613-Jun-25Electrical low volatageWill entering the communication vaults take confined safety?7/7/25Yes, per SOW 2.1.1.2 .Fiber Optic Cable SOW56 CSMichael CarmineNoNo
0623-Jun-25Electrical low volatagedoes the inspector or the airforce base require MOP Method of procedure for the confined spaces?7/7/25No. The contractor would have to provide their written confined space program to the Luke AFB Safety Office as well as complete a Luke AFB confined space permit and follow all regulations in SOW section 2.1.1.2.56 CSMichael CarmineNoNo
0633-Jun-25Electrical low volatageWho would we submit safety paper work too?7/3/25The Luke AFB Safety office has a package that will be provided to conctractor and at the pre-construction meeting after contract award. Any safety paperwork would be a submittal to the government after contract award.56CONSKelli McDonaldNoNo
0643-Jun-25Electrical low volatageFor any sheet rock repair or cuts does the process need to be done dutijg off hours? Building 1383 and 13847/7/25As per SOW, standard duty hours are Mon-Fri, 0730 to 1630 local time.56 CSMichael CarmineNoNo
65+A71:K713-Jun-25Electrical low volatageWhat methods of dust containment need to be used?7/22/25A 56 Civil Engineering Squadron block dust permit will need to be completed. Following dust control requirements with Maricopa County which state "Any project disturbing 0.10 acre or more including trenching, staging or access roads would require a Dust Control Permit from the Maricopa County Air Quality Department."56 CESJosefa SilvaNoNo
0663-Jun-25Electrical low volatageFor piping or performing demo or new installation in building 123, 1383 and 1384, can this be done during normal business hours?7/7/25As per SOW, standard duty hours are Mon-Fri, 0730 to 1630 local time.56 CSMichael CarmineNoNo
0673-Jun-25Electrical low volatageWhen do they want to start the project?7/3/25Per the solicitation box 11, contract performance will start 10 calendar days after Notice to Proceed.56CONSKelli McDonaldNoNo
0683-Jun-25Electrical low volatageWhat are project time frames for each scope?7/3/25Per the solicitation box 11, the POP for the whole project is 270 calendar days after recieving Notice to Proceed.56CONSKelli McDonaldNoNo
0693-Jun-25Electrical low volatageCan potholes in the exisitng parking lot or bad asphat, can we patch back with Cold Patch or black concrete?Please see attachments. Contractor is required to follow the MAG spec MAG. STD 212 for Potholing and MAG. 200-1.56 CESEarnest PerkinsNoNo
0703-Jun-25Electrical low volatageIn buildings 1383 and 1384, what are the exterior wall construction details?7/11/25The exterior walls are stucco and concrete.56 CESEarnest PerkinsNoNo
0713-Jun-25Electrical low volatageIn buildings 1383 and 1384 How many exisiting locations for cat5 and cat3 are being reused?7/7/25Please refer to SOW and SOW Attachment A Drawings, which states the total and the breakdown. Whether replacing exisitng or a brand new location, the quanitity and approx locations are annotated. Any of the ceiling-mount outlets, hexa-drop outlets, and the single-drop outlets (AMRS) are new locations.56 CSMichael CarmineNoNo
0723-Jun-25Electrical low volatageWhat type of conduit can be used to protect the cat 6 going down the wall for new llocations in buildings 1383 and 1384?7/8/25As per UFC 3-580-01, design conduit systems in accordance with TIA-569. Install EMT conduit from the cable backbone distribution system, whether cable tray or enclosed duct, to each outlet... For standard outlets, use a minimum 1-inch (27-millimeter) EMT conduit. Surface mount is allowed on non-drywall walls.56 CSMichael CarmineNoNo
0733-Jun-25Electrical low volatageCan open backed remodel boxes be used for new cat6 locations in buildings 1383 and 1384?7/9/25As per UFC 3-580-01, 2-3.4.1.1 Wall-mounted Workstation Outlet Boxes, use double gang electrical boxes, minimum standard size 4-11/16 inches (120 millimeters) square and 2-1/8 inches (54 millimeters) deep with plaster ring for connection of single gang faceplate. Design outlet boxes for recessed mounting with the faceplate flush with the wall surface, at the same height as the electrical outlets.

Section 2-3.4.2.1 Outlet Faceplate states use a single gang, four-position, modular faceplate for each work area outlet.

Please see SOW and Attachment A Drawings that designating four-position and six-position faceplates.56 CSMichael CarmineNoNo
0743-Jun-25Boring And civilWho does traffic control for boring rig and shutdowns?7/7/25The contractor performs traffic control. 56 Civil Engineering Squadron handles dig permits and outage requests, with coordination of the project PM.56 CSMichael CarmineNoNo
075What if a work classification is not on the wage determination.7/17/25Please review the Wage Determination (4 July 2025) for this project. The work classifications in this wage determination is required to be followed for all employees working on this project.56CONSKelli McDonaldNoNo
076Attachment 3 SOW sect 1.0 says 12 strands of single mode FOC. Attachment 3 SOW figure 2 calls for 12 or 24 st SM FOC. Attachment 4 says something different. Please clarify Fiber Optic Cable requirement and is Corning Freedom LST loose tude, gel-free, interlocking, armored cable, riser 24 F, single mode (OS2) meet base requirement.7/22/25Single mode and multi mode FOC is used in different applications of the project. Attachment 4 specifies the standards for each type of fiber optic cable. Corning or equivalent would meet base requirement.56 CSMichael CarmineNoNo
077Does an AF 3064 Schedule need to be submitted with my proposal.7/24/25No. Please see updates to the SOW.56CONSKelli McDonaldNoYes