FA4861-16-R-A300_-_Paving_IDIQ_RFIs_Answers.pdf

PDF 60 KB Posted

Attached to
Paving IDIQ Federal contract opportunity
Solicitation number
FA4861-16-R-A300
Issued by
Department of the Air Force Air Combat Command

About this file

Paving IDIQ RFI Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Paving IDIQ, newest first.
File Type Posted
Atch_01_Paving_SOW_22Aug16.pdf PDF
Atch_56_AFI_31-501_Prsnl_Security_Pgm_Mgmt.pdf PDF
FA4861-16-R-A300_Amendment_03.pdf PDF
16RA300_Amendment_02.pdf PDF
16RA300_Amendment_01.pdf PDF
16RA300_Mtg_Minutes.pdf PDF
Atch_01_Paving_SOW_7Feb16.pdf PDF
Atch_05_Spec_Section_32_01_17_Crack_Sealing.doc DOC document
Atch_32_APPENDIX_11_Rpr_of_Concrete_Pavements.pdf PDF
Atch_46_APPENDIX_25_VEA_Connection_Charge_Agreement.docx DOCX document
Atch_23_APPENDIX_2_Mooring_Detail.pdf PDF
Atch_27_APPENDIX_6_Sidewalk_Detail.pdf PDF
Atch_40_APPENDIX_19_Schedule_of_Values_Template.pdf PDF
Atch_08_Spec_Section_32_11_16_Subbase.doc DOC document
Atch_21_Spec_Section_34_73_13_Mooring_and_Grounding.doc DOC document
Atch_18_Spec_Section_32_16_23_PCC_Sidewalks.doc DOC document
Atch_04_Spec_Section_32_01_16_Milling.doc DOC document
Atch_49_WD_NV160001_20160311.pdf PDF
Atch_55_Sample_Client_Authorization_Letter.pdf PDF
Atch_07_Spec_Section_32_01_29_Spall_Repair.doc DOC document
Atch_12_Spec_Section_32_12_15_HMA_Airfield.doc DOC document
Atch_31_APPENDIX_10_Full_Depth_Rpr_Details.pdf PDF
Atch_29_APPENDIX_8__Bollard_Detail.pdf PDF
Atch_35_APPENDIX_14_Compression_Seal_Detail.pdf PDF
Atch_54_Subcontractor_or_Teaming_Partner_Consent_Form.pdf PDF
Atch_36_APPENDIX_15_ADA_Warning_Panel_Detail.pdf PDF
Atch_25_APPENDIX_4_A_Curb_Detail.pdf PDF
Atch_28_APPENDIX_7_Valley_Gutter_Detail.pdf PDF
FA4861-16-R-A300_Solicitation.pdf PDF
Atch_30_APPENDIX_9_Partial_Depth_Rpr_Details.pdf PDF
Atch_24_APPENDIX_3_Wing_Wall_Inlet_Detail.pdf PDF
Atch_02_Spec_Section_02_41_13__Demolition.doc DOC document
Atch_42_APPENDIX_21_NAFB_Form_0-74 _Range_Pass.pdf PDF
Atch_26_APPENDIX_5_L_Curb_and_Gutter_Detail.pdf PDF
Atch_34_APPENDIX_13_Field_Molded_Joint_Seal_Detail.pdf PDF
Atch_17_Spec_Section_32_13_73_19_Compression_Seals.doc DOC document
Atch_11_Spec_Section_32_12_13_Tack_ _Prime_Coat.doc DOC document
Atch_50_WD_NV160034_20160108.pdf PDF
Atch_44_APPENDIX_23_Nat'l_Manual_on_Traffic_Control_Dev.pdf PDF
Atch_39_APPENDIX_18_AF_Form_103.pdf PDF
Atch_20_Spec_Section_32_17_26_Tactile_Warning_Panels.doc DOC document
Atch_22_APPENDIX_1_Duct_Details.pdf PDF
Atch_37_APX_16_Nellis-Creech_ID2_Handbook_2011.pdf PDF
Atch_45_APPENDIX_24_DOD_Supplement_to_MUTCD.pdf PDF
Atch_47_APPENDIX_26_VEA_Trenching_ _Backfill_Req.pdf PDF
Atch_43_APPENDIX_22_Env_Permit-ATP_Guidance.doc DOC document
Atch_03_Spec_Section_31_00_00_Earthwork.doc DOC document
Atch_13_Spec_Section_32_12_16_HMA_Roads.doc DOC document
Atch_53_Past_Performance_Questionnaire.pdf PDF
Atch_15_Spec_Section_32_13_11_PCC_Airfield.doc DOC document
Show all 50

Paving IDIQ has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: FA4861-16-R-A300

Request For Information

15AUG16

1. Line Items #1.3.10.1 through 1.3.10.4 is for Permanent Traffic Control Signs. Where can we cover the Temporary Traffic Control Signage as required for the various scopes of work?

Reference para 1.3.1. in Division 01 11 00: The Contractor shall provide and install all safety barricades, traffic control items and detour signs, and the cost of such shall be included in the bid prices for the line items.

2. Line Item #1.3.11.1 Demobilization & Remobilization is for Nellis AFB. There needs to be two (2) separate bid line items for Mobilization to Creech and NTTR? Each of these locations will have varying differing cost for mobilization which may not be able to be covered as a percentage over just a few line items of work. Please include these additional items.

The one line item as described will be sufficient. This item will only be used for a particular task order if a gap in available work periods will be expected to exceed 30 days.

3. Are we to submit a separate copy of the bid schedule for all line items of work for Creech & NTTR, due to the fact the deliveries of all materials will vary for each of the items. This will be difficult to create a percentage that works for all line items. Please provide some direction on how deal with this matter.

No, the percentage factor has been successfully used in past IDIQ contracts.

4. Removal of Concrete items do not address the excavation to subgrade, to make room for the Aggregate Base section. Will we use the Excavation line item to cover for this work?

Yes, the intent would be to use line item 1.3.5.20 to account for excavation requirements that would be required that are not already accounted for in the respective demolition & construction line items.

5. Is there to be a material escalator for items such as concrete, steel and asphalt? We can get price protect on materials for a year at a time. Will the owner be reviewing the cost changes of these materials annually for price adjustments?

No, adjustments to line items shall be captured in subsequent Option Year pricing.

6. Is Flaggers to be covered in the line items as well or will they be done on a Time & Material Basis?

Cost for flaggers shall be incorporated into the unit costs of the line items that might require them.

7. Are there any existing environmental conditions I need to be made aware of that will affect the progress of the work as described in any of the SOW’s for any of the locations included in this Paving IDIQ?

Environmental items are addressed in paragraph 1.22 in Division 01 11 00.

8. All projects in Clark County require a Dust Permit! Where is this cost to be covered?

Cost for this shall be incorporated into the unit costs of the line items for which it would be applicable.

9. All projects in the State of Nevada require a SWPPP Permit! Where is this cost to be covered?

Cost for this shall be incorporated into the unit costs of the line items for which it would be applicable.

10. Southern Ranges of the NTTR (Range 63 and Point Bravo): What are the gate access locations for this area? Where are the potential work areas? Please will you provide a plan for general access and locations?

Access to Range 63 will be through the access gate across US 95 from the highway 156 intersection. Access to Point Bravo will be through the access gate at Point Bravo which is approximately 6 miles southeast of Indian Springs off of US 95. All work that might be executed on the southern ranges accessed from these locations would be within 6 miles of the respective entrance locations.

11. All Locations: Are there any borrow areas for native fill materials, also disposal areas for clean earth, asphalt milling and chunks, demolished concrete?

No, not at the time of the award of this contract. Reference paragraph 1.22.9 in Division 01 11 00.

12. Item 1.3.4.5: Patch Hot Mix Asphalt Pavement – Scope calls for placement of AC in max lift of 3” but replacement is assumed at 4” of AC – is this correct?

Yes

13. Item 1.3.4.6: Overlay 2” Thick Hot Mix Asphalt Pavement – This item clearly states that millings need to be hauled off base – other items do not specify that hauled concrete needs to be removed off base. What is required for all removed asphalt disposal?

In accordance with paragraph 1.3.1 in Division 01 11 00: Note the term demolition or remove includes haul and disposal of material off base; and paragraph 1.3.5.20 states all excavated material shall be hauled off base.

14. Item 1.3.4.13: Install Fill Material – Is the fill material available on site?

No

15. Item 1.3.4.14: Install Subbase Course – Is subbase materials available on site?

No

16. Item 1.3.6.1: Construct Drop Inlet – What is the estimated depth of the drop inlets?

The depth of the drop inlets shall be a maximum of five feet. Paragraph 1.3.6.1 has been changed to reflect this clarification.

17. Item 1.3.6.2: Connect Drop Inlet – What is the average depth of the pipe installation?

The average depth shall be four feet to top of existing drainage pipe. Paragraph 1.3.6.2 has been changed to reflect this clarification.

18. Item 1.3.6.3: Install Concrete Pipe Culvert – What is the depth that the invert of the pipe will be installed below grade? Bid item says backfill to 6” of above pipe included in the bid item; under which item does the balance of the trench backfill get paid? What are the bedding requirements for the pipe (thickness and materials type)?

The top of the drainage pipe shall be 6” below the excavated depth of an asphalt pavement section; the pavement section includes the asphalt and base course thickness which will vary depending on the line item. Trench backfill included in this line item. The pipe bedding layer shall be a minimum of 6” of either Type II aggregate base course or sand. Paragraph 1.3.6.3 has been changed to reflect this clarification.

19. Item 1.3.6.5: Install CMP - What is the depth that the invert of the pipe will be installed below grade? Bid item says backfill to 6” of above pipe included in the bid item; under which item does the balance of the trench backfill get paid? What are the bedding requirements for the pipe (thickness and materials type)?

The top of the drainage pipe is assumed to be going 6” below the excavated depth of an asphalt pavement section; the pavement section includes the asphalt and base course thickness which will vary depending on the line item. Trench backfill included in this line item. The pipe bedding layer shall be a minimum of 6” of either Type II aggregate base course or sand. Paragraph

1.3.6.5 has been changed to reflect this clarification.

20. Item 1.3.10.5: Install Asphalt Speed Table – Please clarify what the width of the lane measurement is.

Lane widths will vary. This line item is to be priced on a linear foot basis.

21. Item 1.3.11.2: Controlled Area Escorts – Please will you clarify “appropriate” security clearance.

The escorts will be responsible for ensuring that non-restricted badged workers stay within the pre-defined controlled area. The Contractor and escorts shall comply with applicable excerpts AFI 31-501, Personnel Security Program Management. These additional requirements will be completed with assistance from the 99 CES Security Manager. Paragraph 1.3.11.2 has been changed to reflect this clarification.

22. Section 1.3.2.1: Min $40K is the guaranteed IDIQ Contract award – does this mean we get paid this?

As stated on page 1 and page 5 of the solicitation, the minimum award amount for this contract is $25,000. Paragraph 1.3.2.1 of the Statement of Work has been changed to reflect this (see the new attachment 01, Statement of Work, dated 22 Aug 16). This means the contract is guaranteed to award one task order valued at a minimum of $25K.