Atch_21_Spec_Section_34_73_13_Mooring_and_Grounding.doc

DOC document 38 KB Posted

Attached to
Paving IDIQ Federal contract opportunity
Solicitation number
FA4861-16-R-A300
Issued by
Department of the Air Force Air Combat Command

About this file

Atch 21 Spec Section 34 73 13 Mooring and Grounding

View the file

Other files for this federal contract opportunity

Other files attached to Paving IDIQ, newest first.
File Type Posted
Atch_01_Paving_SOW_22Aug16.pdf PDF
FA4861-16-R-A300_Amendment_03.pdf PDF
FA4861-16-R-A300_-_Paving_IDIQ_RFIs_Answers.pdf PDF
Atch_56_AFI_31-501_Prsnl_Security_Pgm_Mgmt.pdf PDF
16RA300_Amendment_02.pdf PDF
16RA300_Amendment_01.pdf PDF
16RA300_Mtg_Minutes.pdf PDF
Atch_01_Paving_SOW_7Feb16.pdf PDF
Atch_05_Spec_Section_32_01_17_Crack_Sealing.doc DOC document
Atch_32_APPENDIX_11_Rpr_of_Concrete_Pavements.pdf PDF
Atch_46_APPENDIX_25_VEA_Connection_Charge_Agreement.docx DOCX document
Atch_23_APPENDIX_2_Mooring_Detail.pdf PDF
Atch_27_APPENDIX_6_Sidewalk_Detail.pdf PDF
Atch_40_APPENDIX_19_Schedule_of_Values_Template.pdf PDF
Atch_08_Spec_Section_32_11_16_Subbase.doc DOC document
Atch_18_Spec_Section_32_16_23_PCC_Sidewalks.doc DOC document
Atch_04_Spec_Section_32_01_16_Milling.doc DOC document
Atch_49_WD_NV160001_20160311.pdf PDF
Atch_55_Sample_Client_Authorization_Letter.pdf PDF
Atch_34_APPENDIX_13_Field_Molded_Joint_Seal_Detail.pdf PDF
Atch_17_Spec_Section_32_13_73_19_Compression_Seals.doc DOC document
Atch_11_Spec_Section_32_12_13_Tack_ _Prime_Coat.doc DOC document
Atch_50_WD_NV160034_20160108.pdf PDF
Atch_44_APPENDIX_23_Nat'l_Manual_on_Traffic_Control_Dev.pdf PDF
Atch_39_APPENDIX_18_AF_Form_103.pdf PDF
Atch_20_Spec_Section_32_17_26_Tactile_Warning_Panels.doc DOC document
Atch_22_APPENDIX_1_Duct_Details.pdf PDF
Atch_37_APX_16_Nellis-Creech_ID2_Handbook_2011.pdf PDF
Atch_45_APPENDIX_24_DOD_Supplement_to_MUTCD.pdf PDF
Atch_47_APPENDIX_26_VEA_Trenching_ _Backfill_Req.pdf PDF
Atch_43_APPENDIX_22_Env_Permit-ATP_Guidance.doc DOC document
Atch_03_Spec_Section_31_00_00_Earthwork.doc DOC document
Atch_07_Spec_Section_32_01_29_Spall_Repair.doc DOC document
Atch_12_Spec_Section_32_12_15_HMA_Airfield.doc DOC document
Atch_31_APPENDIX_10_Full_Depth_Rpr_Details.pdf PDF
Atch_29_APPENDIX_8__Bollard_Detail.pdf PDF
Atch_35_APPENDIX_14_Compression_Seal_Detail.pdf PDF
Atch_54_Subcontractor_or_Teaming_Partner_Consent_Form.pdf PDF
Atch_36_APPENDIX_15_ADA_Warning_Panel_Detail.pdf PDF
Atch_25_APPENDIX_4_A_Curb_Detail.pdf PDF
Atch_28_APPENDIX_7_Valley_Gutter_Detail.pdf PDF
FA4861-16-R-A300_Solicitation.pdf PDF
Atch_30_APPENDIX_9_Partial_Depth_Rpr_Details.pdf PDF
Atch_24_APPENDIX_3_Wing_Wall_Inlet_Detail.pdf PDF
Atch_02_Spec_Section_02_41_13__Demolition.doc DOC document
Atch_42_APPENDIX_21_NAFB_Form_0-74 _Range_Pass.pdf PDF
Atch_26_APPENDIX_5_L_Curb_and_Gutter_Detail.pdf PDF
Atch_13_Spec_Section_32_12_16_HMA_Roads.doc DOC document
Atch_53_Past_Performance_Questionnaire.pdf PDF
Atch_15_Spec_Section_32_13_11_PCC_Airfield.doc DOC document
Show all 50

Paving IDIQ has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAVING IDIQ

Solicitation: FA4861-16-R-A300

SECTION 34 73 13

MOORING AND GROUNDING POINTS FOR AIRCRAFT

1. PART 1 - GENERAL

1.1. REFERENCES

AMERICAN WELDING SOCIETY (AWS)

AWS D1.4/D1.4M (2005; E 2005) Structural Welding Code -

Reinforcing Steel

ASTM INTERNATIONAL (ASTM)

ASTM A 436 (1984; R 2006) Austenitic Gray Iron

Castings

ASTM A 615/A 615M (2006a) Standard Specification for

Deformed and Plain Carbon Steel Bars for

Concrete Reinforcement

ASTM B 371/B 371M (2006) Copper-Zinc-Silicon Alloy Rod

ASTM B 8 (2004) Concentric-Lay-Stranded Copper

Conductors, Hard, Medium-Hard, or Soft

ASTM C 94/C 94M (2006) Ready-Mixed Concrete

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 407 (2006) Standard for Aircraft Fuel Servicing

U.S. ARMY CORPS OF ENGINEERS (USACE)

COE CRD-C 300 (1990) Specifications for Membrane-Forming

UNDERWRITERS LABORATORIES (UL)

UL 467 (2004) Grounding and Bonding Equipment

1.2. SUBMITTALS

1.2.1. SD-02 Shop Drawings

1.2.2. SD-06 Test Reports

1.2.3. SD-07 Certificates

1.2.4. Mooring Devices: Certificate of compliance stating that the mooring devices meet the specified requirements.

1.2.5. Grounding Rods: Certificates of compliance stating that the grounding rods meet the specified requirements.

1.2.6. As-Built Drawings:

The Contractor shall submit AS-Built Drawings that provide current factual information, including deviations from and amendments to the drawings and changes in the work, concealed and visible.

2. PART 2 - PRODUCTS

2.1. METALS

2.2. MOORING DEVICES

Mooring devices shall be cast in ductile iron 80-55-06 conforming to ASTM A 436. The device shall be as shown in the contract drawings. The Contractor shall submit certificates of compliance on the devices.

2.3. CORING REQUIREMENTS

The holes shall be cored using rotary, non-percussion drilling techniques. The sides of the core hole shall be perpendicular to the pavement surface. Once the pavement is cored the base course shall be excavated as shown in the drawings. The sides of the core hole shall be cleaned of laitence and roughened by sand blasting. The Contractor shall place the concrete around the mooring device in two or more lifts. The first lift shall be placed to within 5 inches of the pavement surface and thoroughly consolidated by spud vibrators. The second lift shall be placed and also consolidated by internal vibration. The surface of the concrete shall be finished and textured to match the adjacent pavement surface and elevation. White pigmented curing compound meeting the requirements of COE CRD-C 300 shall be uniformly applied at coverage of not more than 4.5 square m/L (200 square feet per gallon).

2.4. GROUNDING RODS

Grounding rods shall conform to UL 467 and shall be made of copper-clad steel. The rods shall be not less than 3/4 inch in diameter and not less than 10 feet long. The copper cladding shall conform to the applicable requirements of ASTM B 371/B 371M, Copper Alloy UNS No's. c 69400, c 69430, c 69440 or c 69450. The copper cladding shall be not less than 0.010 inches thick at any point and shall comply with adherence requirements and the banding requirements of UL 467. The Contractor shall submit certificates of compliance on the grounding rods. Rods shall be provided with a closed eye having an inside diameter of not less than 1-1/4 inches. The rods shall be pointed unless used for flexible pavement. For flexible pavement, the rods shall have 3/4 inch American standard rolled threads for attachment of a bottom anchor and shall be equipped with a screw-type bottom having a wing diameter of not less than 152 mm (6 inches).

3. PART 3 - EXECUTION

3.1. MOORING POINTS IN EXISTING RIGID PAVEMENTS

The mooring points shall be installed in 12 plus or minus 1/2 inch diameter holes cored through the pavement. The core holes shall be drilled within plus or minus 1-1/2 inches of the location shown in the contract drawings. The mooring device and attached grounding rod shall be installed within plus or minus 1/2 inch of the center of the core hole. The top of the mooring device shall be installed within 1/4 inch of the surrounding pavement surfaces, but not higher.

3.2. GROUNDING POINTS

The grounding points shall be located as shown on the task order drawings to within plus or minus 2 inches.

3.3. EXISTING RIGID PAVEMENT

Grounding rods shall be installed in holes cored through the rigid pavement using rotary, non-percussion drilling techniques. The core holes shall have a minimum diameter of 6 inches. The grounding rod shall be installed by pushing or driving the rod through the pavement base courses and subgrade. The installation technique chosen by the Contractor shall not damage the grounding rod or the pavement. Installation shall be completed by placing concrete around the grounding rod in two lifts with each lift consolidated with spud vibrators.

3.4. CLEAN-UP

The Contractor shall control all operations to minimize the amount of dust, dirt, debris and laitance in the work area. The Contractor shall clean all dirt, dust, debris, or laitance from coring or concreting operations, from the pavement surfaces prior to final acceptance.

4. PART 4 - TESTS

Resistance to ground tests shall be measured as specified in NFPA 407. Test results shall be submitted to the Contracting Officer. Any ground rods that have more than 10,000 ohms of resistance shall be reported to the Contracting Officer immediately.

-- End of Section --