General Questions and Answers (Part 2)

View the file

Other files for this federal contract opportunity

Other files attached to Nellis AFB Multiple Award Construction Contract (MACC) Solicitation, newest first.
File Type Posted
Bldg16_CAD.zip ZIP file
AutoCADcombined.dwg DWG drawing
Atch_62__Nellis_Creech_AFB_Facility_Metering_Requirements.pdf PDF
Atch_60_ETL_07-04_AF_Carpet_Standard.pdf PDF
16RA100_Tech_QA_(Part_3).pdf PDF
Atch_61__AF_Facility_Metering_Policy.pdf PDF
Atch_56_Asbestos_ _LBP_Reports _RKMF_16-0062_Rpr_Courtroom _Bldg_16 _Mar_2016.pdf PDF
Atch_53_Statement_of_Work _RKMF_16-0062_Rpr_Courtroom _Bldg_16_Revision_2.pdf PDF
16RA100SignInRosters.pdf PDF
Atch_54_Demolition_Plan _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
FA4861-16-R-A100-0005_General_QnA.pdf PDF
Atch_48_Teaming_List.doc DOC document
FA4861-16-R-A100-0003_Amendment.pdf PDF
Atch_59_Concept_Floor_Plan _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
FA4861-16-R-A100-0002_Amendment.pdf PDF
Atch_25_3PH__CJE_CREECH_4in-Profile_A-size.pdf PDF
Atch_29_Trench_Sand.pdf PDF
Atch_46_WD_NV160022_201600603.pdf PDF
Atch_50_Subcontractor_Teaming_Partner_Consent_Form.doc DOC document
Atch_19_AFI_33-580_Spectrum_Management.pdf PDF
Atch_31_UM3-14-Profile_A-size.pdf PDF
Atch_45_WD_NV160004_20160603.pdf PDF
Atch_06_Engineering_Technical_Letter_20020627.pdf PDF
Atch_52_Past_Performance_Questionnaire.doc DOC document
Atch_41_AF_3064_Progress_Schedule.xfdl XFDL file
Atch_11_AFI_23-204_Material_Management.pdf PDF
Atch_56_Asbestos_ _LBP_Reports _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_48_Teaming_List.doc DOC document
Atch_58_Bid_Schedule _RKMF_16-0062_Rpr_Courtroom _Bldg_16.doc DOC document
Atch_13_AFI_32-1024_Standard_Facility_Requirements.pdf PDF
Atch_23_(CREECH)_UR2_(S).pdf PDF
Atch_21_AFMAN_32-1084_Facility_Requirements.pdf PDF
Atch_33_UM33-Profile_A-size.pdf PDF
Atch_05_Environmental_Permit_ATP_Guidance.pdf PDF
Atch_36_NAFB_0-74_Range_Pass.pdf PDF
Atch_34_UM48-2_Multi-ground_rod-Profile_A-size.pdf PDF
Atch_30_Ug_17-2_Delta-Wye.pdf PDF
Atch_38_Nuclear_Gauge_Form_2.dotx DOTX file
Atch_57_As-Built_Drawings _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_44_WD_NV160001_20160311.pdf PDF
Atch_22_(CREECH)_UM1-6C.PDF PDF
Atch_28_Cooper_Transformers_Three_Phase_List.pdf PDF
Atch_39_AF_103_Base_Civil_Engineering_Work_Order_Request.xfdl XFDL file
Atch_40_AF_3052_Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
Atch_42_Contract_Progress_Report_Template.xfdl XFDL file
Atch_24_1PH_CJE-Profile_A-size.pdf PDF
Atch_55_Facility_Photos _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_16_AFI_32-7042_Waste_Management.pdf PDF
Atch_10_ACCMAN32-7051_hollomanafbsup_1.pdf PDF
Atch_02_Nellis_Creech_ID2_Handbook_201108.pdf PDF
Show all 50

Nellis AFB Multiple Award Construction Contract (MACC) Solicitation has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4861-16-R-A100

MACC General Questions and Answers (Part 2)

Q.

Section L, para C.10: Please clarify what single-spaced with 1.5 line spacing means – generally text is either single spaced OR has 1.5 line spacing. With very limited page count for the technical volume and a 12 point font we respectfully request that single line spacing be required.

A. See Ammendement 5 to Section L Instructions to Offerors paragraph C 10.

Q.

Can electronic copies of the proposal be submitted in PDF format since there are wet signatures to be included in the proposal?

A. See Ammendement 5 to Section L Instructions to Offerors paragraph C 16.

Q.

What is the maximum value of projects that will be evaluated as relevant in Volume 2-Past

Performance?

A.

Past performance shall meet the criteria outlined in Section L Instructions to offerors, paragraph F 4.

Q.

Are copies of the completed CPARS to be submitted behind Attachment 49 for projects that are to be submitted for recent and relevant contracts?

A.

CPARS shall be submitted within Vol 2 in accordance with Section L Instructions to

Offerors paragraph C 13.

Q. Is Attachment 48-Teaming List, to be included in the front of Volume 2?

A. See Ammendement 5 to Section L Instructions to Offerors paragraph F 2.

Q.

What is the minimum/maximum project value criteria for teaming partners/subcontractors who are also submitting up to three (3) relevant projects in Volume 2?

A. See answer to question 3

Q.

What format are the electronic copies to be in? For example are Attachments 40 and 43 are

Excel workbooks – are they to be submitted as Excel workbooks?

A. See answer to question 2

Q.

Section L, para G.2 and H.5: Are the financial capability letter and the financial responsibility letter one in the same? If not, please provide further instruction for what should be provided in the financial capability letter (para G.2).

A. See Ammendement 5 to Section L Instructions to Offerors paragraph G 2.

Q.

Are we to provide a copy of our annual SAM representations with our Volume 4 –

Administrative proposal?

A. See Ammendement 5 to Section L Instructions to Offerors paragraph H 4.

Q.

We are to provide PPISs (Attachment 49) for all “teaming partners.” Are subcontractors performing major scopes of work considered to be teaming partners?

a. If so, what does the government consider to be ‘major scopes of work’?

A. No.

11 Q.

Section L, para E and Q&A (Part 1): Please consider amending the page limitation for the technical volume.

A. See Ammendement 5 to Section L Instructions to Offerors paragraph E.

Q.

Request that para E.2(c) and Subfactor 3 be exempted from the page limitation, which would give offeror’s 20 pages for the construction narrative and Program Management

Plan.

A. See answer to question 11.

Q. Can we use the same letter for Volume 3 & 4 requirements?

A. See answer to question 8.

Q.

Requesting clarification on the number of volumes in Section L C.2. It states that the proposal shall consist of three (3) separate volumes, Volume 1 - Technical Proposal, Volume 2 - Past Performance Information, and Volume 3 - Cost/Price Proposal, and

Volume 4 - Administrative. Will there be a total of 3 binders for the 4 volumes consisting of volume 1, volumes 2 and 3, and volume 4. Or 4 separate binders for each volume?

A. See Ammendement 5 to Section L Instructions to Offerors paragraph C 2

Q.

Paragraph 10, page 58 of 70 states, "Pages shall be single-spaced with 1.5 line spacing."

Not sure if it is single spaced between lines or 1.5 spaced between lines. Please clarify.

A. See answer to question 1.

Q.

Schedule of Values should include percentages only and no cost/price information. Can you please clarify? Do we need to include Value?

A.

The value in the “Schedule of Values” is to ensure the total percentage of work is equal to the total proposed dollar value.

Q.

Are we to turn in (attachment 40) Construction Cost Estimate Breakdown as part of Bid

Proposal?

A. See Section L Instructions to Offerors paragraph G 1.

Q.

Some documents (SF 1442 for example) will need to be scanned in as a pdf and therefore will not be in the format(s) noted above. Please advise of the correct path forward.

A. See answer to question 2

Q.

Will you be posting the contractor sign in sheet from the RKMF 16-0062 Repair

Courtroom, Building 16 job walk held this past Thursday, July 7th at 8:30am?

A. Yes. See attachments to Ammendment 5.

Q.

Per Amendment 0004, Page 3, Section C.2 – It states the proposal shall consist of three (3) separate volumes – but then lists four volumes. Are any of the four volumes combined or should it have read that the proposal shall consist of four (4) separate volumes?

A. See answer to question 14.

Q.

Per Amendment 0004, Page 5, Section C.16 – It states that separate CDs are not required for each volume. Although not required, would it be acceptable if we did submit each volume on a separate CD?

A. Yes.

22 Q.

Per Amendment 0004, Page 5, Section C.16 – Lists that CDs are to be submitted in certain formats. With all the attachments and documents that will be scanned for signature, would it be acceptable to create the CD in a .pdf format?

A. See answer to question 2

Q.

Vol I Subfactor 3 requires to demonstrate bond capacity. Please confirm if bid bond for seed project is required for proposal package.

A.

A bid bond for seed project IS NOT required Volume 1 Subfactor 3 outlines bonding requirements for the MACC.

Q.

Page limit for Vol I is unlimited for 35% design. Is this unlimited for design drawings only or all items in subfactor 1? Please clarify the page limit for Vol 1 (It says 20 pages for all else. What includes “all else”?

A.

Unlimited pages applies only to the 35% Design. Additionally, see answer to question 11.

“All else” refers to any additional documentation required for the volume.

Q.

Vol I Subfactor 3 will be excluded from page limit count? 8(a) status and bonding letter will be easily upto 5-6 pages. Please advise

A. See answer to question 11

Q.

Will offeror collect PPQs from previous clients and include in Vol 2 package? or have them directly to send Nellis AFB POC?

A. See Section L Instructions to Offerors paragraph F 3.

Q.

On Vol 3, please clarify what financial capability letter refers to. Can offeror submit current line of credit to satisfy this requirement?

A. See answer to question 8.

Q.

On Vol 4 under Financial Responsibility Letter, Financial Institution does not have standing or rating for their customers. Please advise if this requirement can be omitted if not available.

A. See Ammendement 5 Instructions to Offerors paagraph H 5.

Q.

Current due date is Monday, July 25. Will the Government consider extending by one (1) day to Tuesday 26 July so that offerors may overnight their proposal packages on Monday rather than Friday or Saturday?

A. See Ammendement 5

Q.

We are unable to open the attached .XFDL file in the solicitation package, however in our experience these elements cannot be shown on the standard AF Form 3064. Will the

Government please provide an alternate format or instructions to open the file as well as clarification on the requirements for the AF3064 submittal as part of the proposal?

A.

XFDL viewer can be downloaded from http://www.e-publishing.af.mil/viewerdownload.asp http://www.e-publishing.af.mil/viewerdownload.asp http://www.e-publishing.af.mil/viewerdownload.asp