Solicitation Amendment 001-FA480326B00100001 SF 30.pdf
PDF 419 KB Posted
- Attached to
- Well 4 PFAS/PFOA Upgrade
- Solicitation number
- FA480326B0010
About this file
This is Amendment 0001 to Solicitation FA480326B0010, issued by the Air Force (FA4803 at Shaw AFB, South Carolina) on August 17, 2026. The amendment modifies a small business set-aside requirement valued between $5,000,000 and $10,000,000 for NAICS code 237110 (foundation, structure, and building exterior contractors).
The solicitation requires design and construction services to install an Ion Exchange (IX) Resin System and upgrades to Base Well 4 System. Key changes in this amendment include: (1) changing CLIN 001 unit of measurement from "Lot" to "Job"; (2) replacing the Statement of Work dated July 10, 2026 with a revised version dated August 12, 2026; (3) replacing the pricing sheet dated February 20, 2026 with a revised blank pricing sheet dated August 12, 2026; and (4) adding four new attachments containing a Wells 3 Final Report, Limited Asbestos Survey Report, Soil Sample Base Water Tower Report, and Wells 4 PFAS/PFOA Site Visit Questions and Answers. The period of performance was extended from 360 calendar days to 508 calendar days total, with the Design Phase increased from 120 to 160 days, Construction Phase from 210 to 288 days, and Contract Closeout from 30 to 60 days. Offerors must acknowledge receipt of this amendment in SF 1442 Block 19 with their bid submission. Funds are not presently available; no award will be made until appropriated funds are available to the Contracting Officer.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
J
2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
17 Aug 2026
4. REQUISITION/PURCHASE
REQUISITION NUMBER
5. PROJECT NUMBER (if applicable)
VLSB 24-0058
6. ISSUED BY CODE FA4803
FA4803 20 CONS LGCA
321 CULLEN ST BLDG 216, CP 803 895 5403
SHAW AFB, SC 29152-5125
UNITED STATES
CARLOS GRIGGS, Email: darrel.ford.3@us.af.mil Telephone: 803-895-5381 Darrel J. Ford, Email: darrel.ford.3@us.af.mil Telephone: 803-895-5381
7. ADMINISTERED BY (if other than Item 6)
CODE
SCD: PAS:
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)
CODE: FACILITY CODE:
9A. AMENDMENT OF SOLICITATION NUMBER
FA480326B0010
9B. DATED (SEE ITEM 11)
14 Aug 2026
10A. MODIFICATION OF CONTRACT/ORDER
NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; 1 or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required) See Section G - Contract Administration Data
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK
ONE
A.THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.)
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Schedule
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Darrel J. Ford, CO
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
17 Aug 2026
Computer generated. Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA-FAR (48 CFR) 53.243
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of this amendment is to: Block 14 (Description of Amendment/Modification):
1. Change CLIN 001 Unit of Measurement from "Lot" to "Job".
2. Remove Statement of Work, Attachment 01-SOW-VLSB 24-0058, dated 10 July 2026 and replace with revised Statement of Work, Attachment 01-SOW-VLSB 24-0058, dated 12 August 2026.
3. Removed blank pricing sheet Attachment 02-Pricing Sheet-Well 4 VLSB 24-0058, dated 20 February 2026 and replace with revised blank pricing sheet Attachment 02- Blank Pricing Sheet VLSB 24-0058 Well 4-dated 12 August 2026
4. Add Attachment 24-Wells 3 Final Report, dated July 2025.
5. Add Attachment 25-Limited Asbestos Survey Report, dated 7 May 2025.
6. Add Attachment 26-Soil Sample Base Water Tower Report, dated 26 June 2026.
7. Add Attachment 27, Wells 4 PFAS/PFOA Site Visit Questions and Answers, dated 17 August 2026.
8. Change total number of days for Design Phase from 120 Calendar Days to 160 Calendar Days.
9. Change total number of days for Construction Phase from 210 Calendar Days to 288 Calendar Days.
10. Change total number of days for Contract Close Out from 30 Calendar Days to 60 Calendar Days.
11. Change total number of Period of Performance Days from 360 Calendar Days to 508 Calendar Days.
***All other terms and conditions remain unchanged. Ensure to acknowledge this amendment in SF 1442 Block 19, Acknowledgement of Amendments with your Bid submission.***
Section A - Solicitation/Contract Form
The following modifications were made:
Information From To
Contract Description
Notice to Offerors and Suppliers: Funds are not presently available for this contract. No award will be made under this solicitation until funds are available. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.
This requirement is for the design and construction to install a Ion Exchange (IX) Resin System and upgrades to the Base Well 4 System in accordance with Statement of Work, dated 10 July 2026.
Period of Performance: 360 Calendar Days Total.
120 Calendar Days after Notice to Proceed issuance for Design Phase.
210 Calendar Days after Notice to Procced issuance for Construction Phase.
30 Calendar Days for Contract Closeout procedures.
Competition: This requirement is a 100% Small Business Concern Set Aside for North American Industry Classification System (NAICS) code 237110. The Magnitude of this requirement is valued between $5,000,000.00 and $10,000,000.00.
Notice to Offerors and Suppliers: Funds are not presently available for this contract. No award will be made under this solicitation until funds are available. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.
This requirement is for the design and construction to install a Ion Exchange (IX) Resin System and upgrades to the Base Well 4 System in accordance with Statement of Work, dated 12 August 2026.
Period of Performance: 508 Calendar Days Total.
160 Calendar Days after Notice to Proceed issuance for Design Phase.
288 Calendar Days after Notice to Procced issuance for Construction Phase.
60 Calendar Days for Contract Closeout procedures.
Competition: This requirement is a 100% Small Business Concern Set Aside for North American Industry Classification System (NAICS) code 237110. The Magnitude of this requirement is valued between $5,000,000.00 and $10,000,000.00.
Solicitation Number FA480326B0010 FA480326B00100001
Section B - Supplies or Services & Prices or Costs
Line Item 0001
The following Line Item modifications were made:
Information From To
FA480326B00100001
Unit of Measure Lot Job
Section J - List of Attachments
The following Header Attachment(s) were added:
Information Value Other Attachment Well 3 Final Report Attachment Name Attachment 24-Wells 3 Final Report-Jul 2025 - Copy 1 Date 01 Jul 2025 Number 24 Reference Identifier 24
Information Value Other Attachment Limited Asbestos Survey Attachment Name Attachment 25-Ltd. Asb. Survey Report 5-07-2026 Date 07 May 2026 Number 25 Reference Identifier 25
Information Value Other Attachment Soil Sample Report Attachment Name Attachment 26-Soil Sample Base Water Tower 4 6-25-26 Date 25 Jun 2026 Number 26 Reference Identifier 26
Information Value Other Attachment Site Visit Questions & Answers Attachment Name Attachment 27-Wells 4 PFAS PFOA - Site Visit Questions-17 Aug 26 Date 17 Aug 2026 Number 27 Reference Identifier 27
The following Header Attachment modifications were made:
Attachment 01- SOW-VLSB 24-0058-10 Jul 26
Information From To Attachment Name Attachment 01- SOW-VLSB 24-0058-10 Jul 26 Attachment 01-SOW-VLSB 24-0058 DATE 08-12-2026 Date 10 Jul 2026 12 Aug 2026
Attachment 02-Pricing Sheet-Well 4 VLSB 24-0058 Date 02-20-2026 Information From To
Attachment Name Attachment 02-Pricing Sheet-Well 4 VLSB 24-0058 Date 02-20-2026
Attachment 02-Blank Pricing Sheet-VLSB 24-0058 Well 4-12 Aug 26
Date 20 Feb 2026 12 Aug 2026
Attachment 15-WD-SC2026-0030 Mod 1-18 May 26 Information From To Reference Identifier 15
FA480326B00100001
| SUMMARY OF CHANGES |
| Solicitation/Contract Form |
| Supplies or Services & Prices or Costs |
| List of Attachments |
File details come from the government source that posted it. Updated .