Attached are the Answers to Round 2 Questions.

View the file

Other files for this federal contract opportunity

Other files attached to Holloman AFB MACC, newest first.
File Type Posted
AF66.xlsx XLSX spreadsheet
AF_From_3064_Progress_Schedule_excel_template_26_Oct_2011.xls XLS spreadsheet
Geotech_Study_-_Fire_Stations.pdf PDF
01_Cover_Sheet.dwg DWG drawing
Summary_of_Amendments_to_MACC.xlsx XLSX spreadsheet
Consent_Letter_Past_Performance_29_Oct_13.pdf PDF
Atch_2_MACC_Statement_of_Work_17_Oct_2013.docx DOCX document
Atch_2_MACC_Statement_of_Work_10_Oct_2013.pdf PDF
MACC_solicitation_amendment_6_dated_10_Oct_2013.pdf PDF
Attach_2_MACC_Statement_of_Work_(SOW).pdf PDF
Historical_workload.pptx PPTX presentation
MACC_QA_Round_1_FINAL.xlsx XLSX spreadsheet
Atch_25_MACC_SITE_MAP.jpg JPG image
Atch_24__AF_3052.xlsx XLSX spreadsheet
Atch_8-1_Consent_Form.pdf PDF
Attachment_23_Financial_Information_Request.pdf PDF
MACC_Amend_1.pdf PDF
MACC_SITE_VISIT_List_of_Attendees_5_Sept_2013.docx DOCX document
A_MACC_Solicitation_19_Aug_2013.pdf PDF
Atch_16_DD_1354_Quick_Notes.pdf PDF
Atch_15_Form_1354.pdf PDF
Atch_10_2012_Holloman_AFB_Design_Compatibility_Standards.pdf PDF
Atch_19_HAFB_Municipal_Solid_Waste_Mgmt_Plan.pdf PDF
Atch_21_HAFB_Integrated_Natural_Resource_Mgmt_Plan.pdf PDF
Atch_11_MACC_Demonstration_Project_SOW_KWRD090122A.pdf PDF
Atch_12_AF_3064_--_Construction_Progress_Schedule.pdf PDF
Atch_8-2_Past_Performance_Info_Sheet.pdf PDF
Atch_8-4_Sample_Past_Experience_List.pdf PDF
Atch_14_HAFB_Standard_Design.pdf PDF
Atch_18_HAFB_Lead_Based_Paint_Mgmt_Plan.pdf PDF
Atch_2_MACC_Statement_of_Work_19_Aug_2013.pdf PDF
A_MACC_Solicitation_19_Aug_2013.pdf PDF
Atch_17_HAFB_Recycling_Guide.pdf PDF
Atch_6_Wage_Determination_NM130005_01-04-2013_Residential.pdf PDF
Atch_4_Wage_Determination_NM30008_01-04-2013_Heavy.pdf PDF
Atch_5_Wage_Determination_NM130050_01-04-2013_Highway.pdf PDF
Atch_8-3_Client_Authorization_Letter.pdf PDF
Atch_20_HAFB_Storm_Water_Pollution_Prevention_Plan.pdf PDF
Atch_7_AF_From_66_Sample.pdf PDF
Atch_3_Wage_Determination_NM130032_01-04-2013_Building.pdf PDF
Atch_13_Base_Access.pdf PDF
Atch_22_HAFB_Chemical_Reuse_Program.pdf PDF
Atch_9_Visitor_Access_Request_Form_and_Consent_Form.doc DOC document
Atch_1_Holloman_AFB_Local_Procedures_19_Aug_2013.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question&Answer2

ContractorCategoryQuestionAnswer
HUITT-ZOLLARS, INCAntiterrorism StandardsWhat level of protection is required to comply with the UFC-4-010-1Very Low Level of Protection as per Table 2-1, UFC 4-010-01.
HUITT-ZOLLARS, INCCAD FormatWill the HAFB Cover Sheet and Title block be made available to us in a CAD Format.See attached dwg files.
SBBIAZCertificationAre there ATFP requirements for the Training Classroom?Yes, refer to UFC 4-010-01 for specific requirements for windows, doors, and other requirements.
SBBIAZCertificationAre there LEED requirements for the classroom building?No, this demo project is exempt.
SBBIAZCertificationIs BIM required for the classroom Task Order and for the contract in general?No.
E-Corp4uCertificationIs LEED silver their expectation on the demonstration project? The MACC calls for self-certifyingNot required for the demonstration project.
SEI Group, Inc.Demonstration ProjectIs it the government’s intent for the 65% construction design plans to include (a) through (p) on page 6 of 8 from demonstration project statement of work?The contractor should complete the drawings for 65% to include as much information as possible covering the items a) through p).
SEI Group, Inc.Demonstration ProjectFor purposes of the “Demonstration” Project, if the 65% is evaluated as technically acceptable, can it be assumed that the next design deliverable would be the 95% design or will there be a 65% design review meeting.For this Demonstration Project, the 65% design, as included in the Contractor's proposal, will be evaluated per the criteria in Section M of the Solicitation for Sub-Factor 2 - Demonsration Project Proposal. There is NO 95% design for the Demonstation Project.
SEI Group, Inc.Demonstration ProjectWill the DDC controls required by the HVAC system, communication with the base energy management system or facilities management system?The new HVAC system controls should meet the base standard for EMCS - it should communicate with the base EMCS in Bldg 54 via the Base LAN.
SEI Group, Inc.Demonstration ProjectConfirm that this project does not require to be formally LEED certifiedThe Demonstration Project DOES NOT need to be LEED certified.
SEI Group, Inc.Demonstration ProjectIs there natural gas on site, or will all units for the HVAC system be electrical?There is no natural gas at the site (that is why there is a large propane tank for the fire fighter trainer). All HVAC for the Demonstration project is electric (i.e., heat pumps).
SEI Group, Inc.Demonstration ProjectWhat is the building orientation (north, south, east, west walls)?See attached site map indicating the approximate orientation of the facility.
SEI Group, Inc.Demonstration ProjectDoes the Government have a preference regarding pitch of PEMB roof?Per the Holloman AFB Design Compatibility Standards, the roof should be standing seam metal, sloped a minimum of 3:12.
SEI Group, Inc.Demonstration ProjectWith facility located remotely on the base, confirm that explosion resistant windows per ATFP are required.Windows and doors must be designed for the applicable standoff distances contained in UFC 4-010-01 except where otherwise established in those standards. See B-3.1 of UFC 4-010-01 for window design requirements.
SEI Group, Inc.Demonstration ProjectConfirm that the section on floor tile should read that all areas except the mech room and bathrooms to be VCT.That is correct.
SEI Group, Inc.Demonstration ProjectDoes the Government request/require an overhang porch at the designated main entrance?Provide a canopy or overhang at the entrance. Per the Holloman AFB Design Compatibility Standards, "Designers are encouraged to use strategically placed sloped roof elements to punctuate key building points (entrances for example)."
SEI Group, Inc.Demonstration ProjectWill a concrete apron be required around building? If so, what is to be the width of apron (5’)?Per the Holloman AFB Design Compatibility Standards, "All units shall have a 3 foot wide and 4 inch thick concrete apron around the entire perimeter."
SEI Group, Inc.Demonstration ProjectConfirm that the restroom ceilings are to be suspended tiles vs. hard gypsum board ceiling.Per the Demonstration Project Task Order
SEI Group, Inc.Demonstration ProjectIs break area countertop to be solid surface material or post-formed laminate plasticUse solid polymer (solid surfacing) fabrications for countertops and backsplashes.
SEI Group, Inc.Demonstration ProjectSince there are no administrative rooms identified as required on the floor plan, request clarification regarding quantity/locations of computer/comm outlets.See Engineering Technical Letter (ETL) 02-12: Communications and Information System Criteria for Air Force Facilities. I suggest one standard telecommunications outlet for each 4.5 square meters (48 square feet) of net office space.
SEI Group, Inc.Demonstration ProjectAny requirement for contractor to install a projection screen?No.
SEI Group, Inc.Demonstration ProjectDuring site walk it was mentioned that no parking lot was to be provided – please confirm that a paved/asphalt parking area with ADA compliant spaces as necessary is not part of this project. If parking lot is to be provided, request number of spaces to be provided.No parking lot is required as part of this project.
SEI Group, Inc.Demonstration ProjectDo we assume a distance for the sidewalk from the parking area to the new building?Use 17.5 feet from south parking area to main entrance.
SEI Group, Inc.Demonstration ProjectRequest clarification regarding required Period of Performance (PoP) for demonstration project. The solicitation states that PoP will be per task order. The demonstration project SOW (Attch 10) does not specify a PoP.Assume Period of Performance for this Design-Build Project is 365 days with 120 days allotted for design.
Barlovento LLCDemonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; states to assume the sanitary sewer system line 50 feet from the building. At the point of tie-in a) what is the sewer line invert relative to the finished floor of the new building, b) what is the sewer line material, c) is the trench only through native material, or is it through other manmade materials, d) what is the material of the new sewer line to be?Assume for the Demonstration Project the invert elevation at 50 feet from the building is such that a 6" sewer line can be installed with a near constant 2% slope from building waste line to tie-in. The new sewer will be PVC as per the Holloman AFB Design Compatibility Standards. The trenching for the sewer line will be through the existing native soil and will require importation of bedding material suitable for the type of sewer installed.
Barlovento LLCDemonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; states to provide site lighting as required to achieve adequate illumination levels for activities during non-daylight hours. Please describe all activities that will occur on site during non-daylight hours.The SOW states, "Install area lighting as required to achieve adequate illumination levels for activities during non-daylight hours on sidewalk(s)." No other area lighting is needed as the fire fighting trainer areas already possess area lighting.
Barlovento LLCDemonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; provides no mention of a fire line or fire hydrants. Is fire sprinkler for the building and site fire hydrants to be excluded from the demonstration project? If no, provide location, size, pressure, flow, etc.UFC 3-600-01 requires a fire hydrant to be within 350 feet of all parts of the building exterior. Since the existing hydrants at the site do not meet these conditions, include at least one hydrant in the design.
Barlovento LLCDemonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; makes no mention of a natural gas line at the building site. Is there a natural gas line to connect to, or shall the building be all electric? If there is a natural gas line available how far from the building is and what is the pressure.There is no natural gas at the site (that is why there is a large propane tank for the fire fighter trainer). All HVAC for the Demonstration project is electric (i.e., heat pumps).
Barlovento LLCDemonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; the representative floor plan shows a ceiling projector, a) is the projector GFCI, GFGI or by the contractor, b) is there to be a projector screen, if so manual or electric and is it GFCI, GFGI or by the contractor, because of the projector are the windows to have blinds.Since no data is given on the projector, the projector is GFGI but the contractor shall provide a suitable power outlet in the ceiling as per the project floor plan. No projector screen is included in this project.
Barlovento LLCDemonstration ProjectAttachment 11 (Page 4, Interior Specialties), is the government intent to have base and wall cabinets around the entire room?No. Only provide base and wall cabinets in the Break Room.
Barlovento LLCDemonstration ProjectIs the contractor to provide the ceramic wall tile in the restrooms?Install 4"x4" ceramic tiles on all walls from floor to ceiling.
Barlovento LLCDemonstration ProjectAttachment 11 (Page 4, Interior Specialties), is the break room countertop plastic laminate or solid surface?Use solid polymer (solid surfacing) fabrications for countertops and backsplashes.
Barlovento LLCDemonstration ProjectIs the expectation for primes to bid the site work before geotechnical data is available in the hope that geotechnical data will align with proposed and quoted design?Assume geotechnical conditions on site are similar to other areas at Holloman AFB. No geotechnical survey exists and no new study is to be performed.
Barlovento LLCDemonstration ProjectHow will the contractor have between each design submittal and what is the government review period for each submittal?The design period and the dates for submission of each design submittal will be specified for each task order. For the Demonstration Project, this is not necessary as we are requesting only the 65% design package.
LEC-GroupDemonstration ProjectDepth of water table?For this area of Holloman AFB, assume the water table is at 10 feet below grade (typical).
LEC-GroupDemonstration ProjectIs there a geotechnical study for sites near the project?See attached geotech study for Fire Station 3
LEC-GroupDemonstration ProjectIf we use RS Means, do we to apply city costs indexNo
LEC-GroupDemonstration ProjectAre there any specific requirements for landscape?No irrigation. Use rock mulch for ground cover and xeroscape plants per Holloman AFB Design Compatibility Standards.
RORE, Inc.Demonstration ProjectPlease provide civil and topographic as-builts if available.No as-builts could be located.
RORE, Inc.Demonstration ProjectDoes the government expect the 65% design submittal for the demonstration project to include a complete set of specifications?No specifications requested for this demonstration project.
RORE, Inc.Demonstration ProjectWill there be a topographic map provided in order to complete the grading plan?Attached site map includes contour lines at each 2' change in elevation.
RORE, Inc.Demonstration ProjectPer Factor 2 – Technical Acceptability section: Will the New Mexico state registration for the civil engineer be required at the time of RFP submittal or will it be acceptable at time of award.It will be acceptable at time of award.
CMS Corp.Demonstration ProjectFor ATFP requirements, what is the distance of the nearest road to the planned building location?As shown on the site map, the road is approximately 110' from the nearest point of the building.
CMS Corp.Demonstration ProjectWhat is the length of cabinetry desired in the Break room?That is up to the designer based on the given floor plan indicating the break room is 12' x 14'.
CMS Corp.Demonstration ProjectIs a handicap hi/lo water fountain or a non-compliant single water fountain requested as part of this request for proposal?Per demonstation project scope, situate 1 each wall mounted electric water cooler in breakroom area. That cooler should meet ADA requirements.
CMS Corp.Demonstration ProjectThe SOW indicates a 4 foot sidewalk required from the parking area to the main entrance. Please indicate where the parking lot is located.The parking area is the existing pavement located around the aircraft mockup. See site map for suggested location of sidewalk.
CMS Corp.Demonstration ProjectPlease clarify the requirement for "auxiliary heat for low ambient conditions" at the heat pump? Is the intent of this statement to have the heat pump be designed with a low-ambient kit or to have the fan/coil unit be designed with an auxiliary strip heat?This is up to the designer. The low ambient condition will be per the weather data for Holloman AFB - i.e., design for a 99.0% occurrence - 23°F.
CMS Corp.Demonstration ProjectWhat value shall be considered for the water pressure at 50 feet from the building?Assume the water pressure in the main will be approximately 50 psig.
CMS Corp.Demonstration ProjectWhat is the period of performance (POP) for the Seed project Bldg 17905.Assume Period of Performance for this Design-Build Project is 365 days with 120 days allotted for design.
CMS Corp.Demonstration ProjectWhat is the location of the existing parking lot?The parking area is the existing pavement located around the aircraft mockup.
CMS Corp.Demonstration ProjectIf there is not a parking lot are we to construct one?No need to construct a separate parking lot. The existing pavement will be used for vehicle parking.
CMS Corp.Demonstration ProjectIf we are to build a parking lot, how many parking spaces are required?No marking for parking spaces required.
CMS Corp.Demonstration ProjectIf utilizing the existing areas for parking which area do we run the side walk toSee site map for suggested location of sidewalk.
CMS Corp.Demonstration ProjectWhich direction is the building to be orientated?The corners of the building were marked with stakes. See attached site map to show the proposed building orientation.
CMS Corp.Demonstration ProjectWhich door entrance does the Government consider the main entrance?Use the door nearest the parking area for the main entrance. See attached site map.
CMS Corp.Demonstration ProjectWhat elevation required for the top of building foundation? Is Xft above the road to the East or Xft above the training area to the West or Xft above existing grade?Per the Holloman AFB Design Compatibility Standards, build up the site 12” to 24” above surrounding grade (existing grade at approximately 4109 ft elevation) to promote positive drainage away from building foundation.
CMS Corp.Demonstration ProjectCan Government provide any existing civil drawing from when the training area was built?No as-builts could be located.
CMS Corp.Demonstration ProjectDoes Government want access to building from the main road or the training area?See site map for main entrance location, relative to the fire fighter trainer.
CMS Corp.Demonstration ProjectDoes Government require a containment fence around the Mechanical system located outside of the building?Not required.
CMS Corp.Demonstration ProjectDoes Government have map for locations of existing utilities for power, water, sewer and gas? The SOW states assume 50ft away from building but does not provide which direction.Maps are available but do not show what is to be the actual Point of Connection to water and sewer utilities (there is no natural gas lines in vicinity). See attached site map.
CMS Corp.Demonstration ProjectPlease advise if there is a need for a service sink.No. SOW for Demonstration Project (Attachment 11) lists all plumbing fixtures.
Meridian-WestDemonstration ProjectThe table on page 71 of 76 states that the Architect is required to be a PE. Typically, an Architect is not a PE, rather he/she would be a Licensed Architect. Would the government consider changing the Architect's qualifications to "Licensed Architect" or "Licensed Architect in the State of NM"?The architect should be registered as an architect in any jurisdiction certified by the National Council of Architectural Registration Boards (NCARB).
AZTEC Contractors Inc.Demonstration ProjectVolume 2, Technical: Subfactor 2 Demonstration Project; the “Estimating Capability” section asks for a completed AF 3052Correct. An AF Form 3052 was posted to FBO.gov after the round 1 questions. On this form, we expect to see a detailed cost breakout that is in consonance with the technical approach described elsewhere in the proposal.
AZTEC Contractors Inc.Demonstration ProjectVolume 2, Subfactor 2, Demonstration Project Proposal, requests a filled out AF Form 3052. However, the RFP did notFollow the requirements given in the Solicitation, including INSTRUCTIONS TO OFFERORS (Paragraph F) which states, "Include a completed AF Form 3052, Construction Cost Estimate Breakdown. Offers should be complete, accurate, and sufficiently detailed to demonstrate a clear understanding of the requirement."
AZTEC Contractors Inc.Demonstration ProjectAs stated in the MACC SOW, paragraph 5 Design Documents, sub-para (b), the drawings required the use of HAFB coverAn AutoCAD cover sheet for Holloman AFB is attached.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; states to run theThese are spelled out for this demo to provide exact details for estimating the site communications work required.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; if no ATFP is required forComply with UFC 4-010-01 as far as design requirements for an occupied building (not a primary gathering area) requiring the minimum level of protection - Very Low Level of Protection as per Table 2-1.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; because of theUnclear what is question.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; more than likely theUnclear what is question.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; is a water softener systemAssume you are asking for a requirement for a water softener. No softener or RO unit is part of this project.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; code does not require aUnclear what is question.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; telephone cabling is calledProvide only the interior conduit and boxes as required by ETL 02-12, "Communications and Information System Criteria for Air Force Facilities." In SRM & O&M projects, the installation of wiring is performed separately by the Communications Squadron.
AZTEC Contractors Inc.Demonstration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; are occupancy sensorsNO occupancy sensors required for this project.
AZTEC Contractors Inc.Demonstration ProjectWill the Government clarify “Wall mirrors” in restroom – are they over the vanity or full length on walls?Assume standard wall mirrors directly above each lavatory (one per restroom).
AZTEC Contractors Inc.Demonstration ProjectHandicap access to the building requires paved H.C. Parking space – is the parking area to be a paved lot?Use existing pavement surrounding the aircraft mockup as a parking area for the new building. No work required as part of this demonstration project to modify or enhance existing pavements for parking.
AZTEC Contractors Inc.Demonstration ProjectIs water pressure to sight sufficient for “Flush Valve” type toilets?Yes.
AZTEC Contractors Inc.Demonstration ProjectWill the Government provide us with the existing topographic survey data?See attached site map.
AZTEC Contractors Inc.Demonstration ProjectWill the Government provide us with the existing utilities/potential utility connection locations?See attached site map.
AZTEC Contractors Inc.Demonstration ProjectWill the Government provide us with the existing Geo-tech report?None can be located for this site. However, a geotechnical report is available for for Fire Station 3. Assume similar soil conditions.
AZTEC Contractors Inc.Demonstration ProjectBuilding will have only one air handler, is it still required to provide DDC controls for the single unit, tied to the base?Yes.
AZTEC Contractors Inc.Demonstration ProjectOr a R.O. system required for the lavatories, sinks and EWC?No R.O. system is to be included in the plumbing system design.
AZTEC Contractors Inc.Demonstration ProjectFire alarm system for the building, however the SOW calls for an addressable panel. Is the fire alarm system to be a manual?Fire alarm system shall be per Holloman AFB Design Compatibility Standards with addressable FACP and Monaco BTX radio transceiver. Include horn/strobes, manual pull stations as per NFPA 72.
E-Corp4uDemonstration ProjectThe RFP calls for R-11 walls. The code requires R-19. To be even close to LEED silver we will likely need 30 on the walls and 50 on the roof.. How do you want to address this?No LEED requirements on this demonstration project. Follow directions in the MACC Demonstation Project SOW regarding design for walls and roof.
E-Corp4uDemonstration ProjectChecking the frost depth there, it is Min. 12”. Should use 18” as the turn down. Are you going to get your metal building people to get us a 65% footing and foundation design?Per Holloman Design Criteria, the Frost Depth (50 year occurrence) is 4 inches. Steel building (PEB) footings and foundation designs do not need to be included in 65% submission (these are typically provided as shop drawings during the submittal phase).
E-Corp4uDemonstration ProjectAre the cover page, title blocks and CADD borders available for Holloman AFB?Yes, these drawings will be provided.
RORE, Inc.Demonstration ProjectUFC 4-010-01 defines the building as a Occupied Building which would require a mass notification system installed in accordance with UFC 4-021-01. Please ensure the building is not to be provided with a mass notification system.Paragraph B-4.6.1 of UFC 4-010-01 states "New buildings must have a capability to provide real-time information to building occupants or personnel in the immediate vicinity of the building during emergency situations." Provide a MNS with this project.
RORE, Inc.Demonstration ProjectThe RFP requires a fire alarm and detection system. Is this meant to mean that the entire building should be provided with smoke detection?No, design a fire alarm system per NFPA 72 for an occupied building NOT equipped with an automatic sprinkler system (per UFC 3-600-01, Para 4-2.2, an automatic sprinkler system is not needed). That usually requires protection of the fire alarm system by installation of automatic smoke detection at the location of the FACP.
SBBIAZDemostration ProjectIt appears that you are requiring a 60 % design on all Task Orders at the proposalAn Invitation for Bid (IFB) or Request for Proposal (RFP) issued under this contract will be issued to all the contractors and will include a Task Order (TO) defining the project requirements. The level of design for the proposal can vary and may be a 35% design, or if a 100% design is already available, the IFB will only require a bid or cost proposal.
HUITT-ZOLLARS, INCDemostration ProjectWill a CAD drawing of the site be made available?None can be located at this time.
HUITT-ZOLLARS, INCDemostration ProjectPage 4 of 8 – Interior Floor Finishes – What is the required finish in the restroomsCeramic tile floors, 4"x4" ceramic tiles on all walls from floor to ceiling, acoustic ceiling tiles.
SBBIAZDemostration ProjectWhat is the building occupancy, peak and average?Assume a peak of 70 students plus 1 instructor and an average occupancy of 25 students plus 1 instructor.
HUITT-ZOLLARS, INCDemostration ProjectHow many occupants are planned for this building?Assume a peak of 70 students plus 1 instructor and an average occupancy of 25 students plus 1 instructor.
SBBIAZDemostration ProjectDoes the requirement for a parking lot still remain?The vehicle parking for this facility will utilitize the existing pavements next to the proposed facility. No construction of parking areas is required under this demonstration project.
Mesa VerdeDemostration ProjectHow much area should be cleared on site (for example an area 80’ x 150’)?The is up to your designers. I suggest minimizing the amount of clearing and grubbing to reduce the amount of restoration required.
Mesa VerdeDemostration ProjectWill the existing elevations be supplied in order to complete a site grading plan?See attached site map for contours.
Mesa VerdeDemostration ProjectSince the plan is for one open room, how many telephone outlets are required?See Engineering Technical Letter (ETL) 02-12: Communications and Information System Criteria for Air Force Facilities. I suggest one standard telecommunications outlet for each 4.5 square meters (48 square feet) of net office space.
Mesa VerdeDemostration ProjectAre we to follow ATFP guidelines when constructing the building?Follow the requirements in UFC 4-010-01 for ATFP requirements. Provide Very Low Level of Protection as per Table 2-1.
Mesa VerdeDemostration ProjectWhat type of parking lot will be required with the building and will there be any handicapped spaces required?The vehicle parking for this facility will utilitize the existing pavements next to the proposed facility. No construction of parking areas is required under this demonstration project.
Mesa VerdeDemostration ProjectIn the aerial photo a barbed wire fence is shown, is supplying and installing the fence a requirement of this contract?No fence is included in this demonstation project.
Mesa VerdeDemostration ProjectWhich road will be utilized to access the building?No. Utilize existing pavement for parking and construct sidewalk (see site map) to obtain access.
FutureNet GroupDemostration ProjectIs a dumpster going to be required? If so, the IDG says to screen it with masonry walls. The SOW does not address the need for a dumpster.There is an existing dumpster already present on the north pavement. Do not provide a separate dumpster enclosure for this demonstration project.
FutureNet GroupDemostration ProjectThe IDG says to use a three foot wide concrete slab around the perimeter of the building. The SOW does not address this. Is this required?Per the Holloman AFB Design Compatibility Standards, "All units shall have a 3 foot wide and 4 inch thick concrete apron around the entire perimeter."
FutureNet GroupDemostration ProjectAre we allowed to include betterments in our proposal?Yes.
SEI Group, Inc.Demostration ProjectFor purposes of the “Demonstration” project, will a project schedule and AF Form 3064 depicting Project Kick-Off meeting and 35%/65% design events being complete acceptable?Yes.
SEI Group, Inc.Demostration ProjectDoes the main room need to be pre-wired for a projector or audio equipment?Provide a power outlet plus data drop in ceiling for GFGI projector. No audio equipment is required.
Barlovento LLCDemostration ProjectAttachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph ; states to assume the water line 50 feet from the building. At the point of tie-in a) what is the water line size, b) what is the water line material, c) what is the water pressure and flow, d) what is the depth of the water line, e) is the trench only through native material, or is it through other manmade materials, f) will a water meter be required, g) what is the material of the new water line to be?Assume for the Demonstration Project thepoint of connection is a 6" PVC water line buried approximately 4 feet below the surface. The line pressure is 50 psig and the measured flow rate (at the nearest fire hydrant) is 915 gpm @ 10 psi. The trenching for the water line will be through the existing native soil and will require importation of bedding material suitable for the type of sewer installed. Provide a water meter for the new facility. The new water line will be PVC (AWWA C900) pressure pipe as per the Holloman AFB Design Compatibility Standards.
Barlovento LLCDemostration Project4. Attachment 10, the Demonstration Project Task Order, Statement of Work (SOW) Paragraph 3; states to assume the primary electrical line 50 feet from the building. At the point of tie-in a) is the existing electrical primary overhead or underground, b) assuming underground, how is the new primary to be connected to the existing primary, c) is the existing primary single phase or three phase, d) is the new transformer to be single phase or three phase, e) is the transformer to be at the point of tie-in or at the building, f) is an electric meter required?Assume overhead primary electrical line 50 feet from building (deadend assembly at utility POC point on site plan). Primary is 13.2KV 3-phase 4-wire. Install conduit riser with fuse cutouts, surge arrestors, and mounting bracket on existing pole. Provide cable, conduit and concrete encased ductbank for primary feed to new pad-mounted 208Y/120 transformer. Transformer pad needs to be located near new building. Provide underground secondary electrical distribution per SOW to building main distribution panel. Provide electric meter at new transformer.
Barlovento LLCDemostration ProjectWill you please provide the desired Period of Performance for the demonstration project?Assume Period of Performance for this Design-Build Project is 365 days with 120 days allotted for design.
RORE, Inc.Demostration ProjectPlease ensure the building is not required to be provided with a sprinkler system.Building will NOT be provided with automatic sprinkler system as per UFC 3-600-01, paragraph 4-2.2.
HUITT-ZOLLARS, INCDesignWhat is the amount of parking spaces required for the Fire Training Classroom?Ample parking area already present on existing pavements. Do not include any pavement work or pavement striping as part this demonstration project.
Meridian-WestDesignIn volume 3 we are asked to provide information on at least three but no more than six recent contracts. Is the government looking for IDIQ-type contracts (similar to the MACC) or rather single projects/TOs in answer to this requirement?Either kind of experience that is recent and relevant can be used for Past Experience.
SBBIAZDesignWhere does the sidewalk lead to and where does it end?See Site Map. Should begin at the parking pavement and end at the main entrance to the new building.
KomadaDesignSF 1442, block 13A: The due date and time is listed on the SF 1442 as October 1st at 12:00 AM. To meet the current deadline and have the proposal delivered on Monday, 9/30 offerors will have to ship by Friday9/27 at the latest. Please consider extending the due date 1 day to allow offerors to ship overnight on Monday 9/30 for delivery by 11:59 PM on 10/1.
See Amendment No. 6 posted on FedBizOps 11 Oct 2013 for proposal due date.
Barlovento LLCDesign“The contractor shall provide a complete 65% construction design which ensures the successful completion of the Demonstration Project..”. We respectfully request that the 65% design is limited to a 35% submission. A 65% design submission for this size of demonstration project will typically cost the Small Business Construction Contractor approximately $10,000-$12,000 from the Architectural Engineer Firm. The majority of all A/E firms will not provide a 65% design for a proposal without the associated fee. This is an extreme cost burden on all Small Business’s providing proposals for this contract. We respectfully request that this requirement is changed.Provide a 65% design submittal as part of your proposal. This design submittal is for a demonstration project and DOES NOT represent the usual requirement.
Barlovento LLCDesignPage 66- a) Design: “The contractor shall provide a complete 65% construction design which ensures the successful completion of the Demonstration Project..”. We respectfully request that the 65% design is limited to a 35% submission. A 65% design submission for this size of demonstration project will typically cost the Small Business Construction Contractor approximately $10,000-$12,000 from the Architectural Engineer Firm. The majority of all A/E firms will not provide a 65% design for a proposal without the associated fee. This is an extreme cost burden on all Small Business’s providing proposals for this contract. We respectfully request that this requirement is changed.Provide a 65% design submittal as part of your proposal. This design submittal is for a demonstration project and DOES NOT represent the usual requirement.
Barlovento LLCDesignPage 66- Design- Is there a geotechnical report and a site survey report available for the demonstration project?No. See other reports for best available information.
Barlovento LLCDesignThe Statement of Work (SOW), Attachment 2 paragraph 5. g. Specifications states, “If required by the DO, provide ….” the specification by using the appropriate Unified Facilities Guide Specifications (UFGS). a) does the DO require specifications for the 65% design of the Demonstration Project Task Order? b) if yes, then may the offeror utilize standard commercial design specifications in lieu of the UFGS specifications for the Demonstration Project Task Order since the time period for 65% design is very short and it takes a lot of time and expense to edit the UFGS specifications?No specifications requested for this demonstration project.
SEI Group, Inc.Design CostRequest clarification as to how Design Costs for the “Demonstration” project are to be identified and presented. Even though proposal prep costs are not “reimbursable,” if this project is awarded, the DD Form 1354 will need to capture design, construction and SIOH costs. If the costs associated with preparing the 65% design submittal are not included with the cost proposal, how will Government determine total project cost?The 1354 is the Real Property Transfer Record that the contractor must file at the end of the project, if awarded. The cost of this design/build task order, if awarded, will be recorded in the 1354 as the total amount.
SEI Group, Inc.Design CostReference question 3 above, how will the Government evaluate cost proposals if some offerors include proposed design costs and other offerors only include design after the 65%.Refer to the Solicitation for preparation of the cost estimate, including the coefficient to include design costs.
SEI Group, Inc.Design CostEvaluation Factor 1 (page 70 of 76) states that the Bond and NM Gross Receipts Tax will not be included in the determination of the “Lowest Price” portion of the LPTA evaluation. The AF Form 3052 does not provide for NMGRT or bond costs. How does the Government prefer to have these costs provided/presented for the “Demonstration” project?The amounts for NMGRT and bond will be determined at the time of award of the demo task, if funded. There is no need to include these costs in this proposal.
KomadaDrawingsProposal Preparation Instructions, Page 63/76, item 9; The RFP requires 1.5 line spacing. Does that apply to the Attachment 8.2 – Past Performance Information Sheet? Attachment 8.4 – Sample Past Experience List- This attachment is included in the RFP documents but I cannot find a reference in the Proposal Preparation Instruction. Where should this form be included in the proposal and what information should it contain?
All pages in the proposal shall be single spaced with 1.5 line spacing. Follow exactly the instructions contained in the Solicitation for preparation of your proposal.
R-CONFloor FinishesSub Factor 1: Construction Management and capability: (Page limitation: 20 Pages).Yes.
R-CONFormsa) Bank Reference: In order to assist in determining the offerors' responsibility, offerors shall complete the Financial Information Request, provide it to their financial institution, an instruct them to complete and returned it o the Contracting Office not later than the required proposal submission date.Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013.
SEI Group, Inc.General QuestionCan the offeror modify or revise the AF Form 3052 to reflect Design, Bond, NMGRT?Design is part of the FEP rate, and the amounts for NMGRT and bond will be determined at the time of award of the demo task, if funded. There is no need to include these costs in this proposal.
R-CONOccupancyb) Bonding: In order to assist in determining the offeror responsibility, offerors shall complete the Bonding Information request provide it to their surety, and instruct to to complete and return it to the Contracting Office not later than the required proposal time.Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013 which provided bonding information.
RORE, Inc.OccupancyIn box 13 A of the SF1442 it states that proposals are due by 12:00AM 01 October 2013, Is the listed time correct?See Amendment No. 6 posted on FedBizOps 11 Oct 2013 for proposal due date.
HUITT-ZOLLARS, INCParkingIs there information on existing utilities of the site?Assume water, sewer and primary electrical are located 50 feet from building. Water system, sewer system and electrical system are described.
HUITT-ZOLLARS, INCParkingIn which HAFB zone is the site located?Zone 1.
SBBIAZPast Performancestage; this seems a bit advanced for a proposal. Is your intent to require 60% designs on all task order proposals?Follow direction contained in Solicitation for preparation of the Demonstration Project design. This is NOT typical for other projects.
Past PerformanceAntiterrorism Standards for buildings?Very Low Level of Protection as per Table 2-1, UFC 4-010-01.
Barlovento LLCPast PerformancePage 67, a) Past Performance Information Sheet (PPIS): “Offerors shall submit information on at least three (3) but no more than six (6) RECENT contracts considered most RELEVANT in demonstrating performance abilities on the proposed effort. Also, Offerors shall include information, if applicable, on up to three (3) recent contracts performed by each joint venture partner considered most relevant in demonstrating their ability to perform the proposed effort.” What is the maximum amount of projects that each Joint Venture partner is allowed and what is the minimum amount that each partner is allowed?Total shall be no more than 6 RECENT contracts for all members of a JV partnership. Follow exactly the direction contained in Solicitation for preparation of your proposal.
Barlovento LLCPast PerformanceAttachment 8-4 Past Experience List- A sample has been provided in the attachments (8-4), but we could find no reference to its requirement in Section L. Please clarify if this form was included within the attachments in error.Attachment 8-4 was included only to provide contractors with a sample or illustration for listing past experience. Contractors are NOT required to use this sample, thus it is not in Section L.
RFIand mechanical room? Bullet #1 states 12 x 12 VCT and Bullet #2 states 2x2 tile.Yes.
SidewalksNo question.
RORE, Inc.SolicitationAttachment 8-1 is missing. Are you planning on making attachment 8-1 available?Refer to 8-1 Revised Past Performance Consent Letter posted on FedBizOps 29 Oct 2013.
RORE, Inc.SolicitationIn Volume 2, sub factor 1: Are the signed team member letters part of the 20 page Limit?Letters will be treated as attachments to the proposal and do NOT count against the 20 page limit.
RORE, Inc.SolicitationOn page 66 (e) it states: “Provide a narrative description of your overall Quality Control approach to the basic IDIQ MACC and how it would mitigate risks such as possible Foreign Object Damage (FOD) for projects on or near the airfield and how it will be applied to individual projects awarded under this contract.” Is this a correct statement?Yes. This is based on historical project data at Holloman AFB.
RORE, Inc.SolicitationVolume 3 states that the past performance volume is due 14 calendar days prior to the solicitation closing date which would be September 17, 2013. Is this correct? If so, does that include the entire volume or only the past performance information sheets? Also, does the contractor have to submit 2 hard copies and one electronic copy of this volume?Refer to Amendment 6 posted on FedBizOps 11 Oct 2013 for revised closing date for proposals. Section L, subsection G, para. 2c) requests submission of the past performance volume at least fourteen (14) calendar days prior to the solicitation closing date; however, failure to submit proposal information early will not result in Offeror disqualification.
RORE, Inc.SolicitationIn the scope of work it is unclear how many parking spaces are needed. Can you please indicate the number of parking spaces needed on this project?Assuming you are referring to the Demonstration project, refer to the Statement of Work for this project.
RORE, Inc.SolicitationWill you provide the ‘Financial Information Request’ form and the ‘Bonding Information Request’ form as requested in Volume 2 under sub factor 1?Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013.
RORE, Inc.SolicitationDoes the government expect the 65% design submittal for the demonstration project to include a complete set of specifications?No specifications requested for this demonstration project.
RORE, Inc.SolicitationWould the government consider extending the RFI deadline to ensure a better comprehensive understanding of the scope.See Amendment No. 6 posted on FedBizOps 11 Oct 2013 for proposal due date.
RORE, Inc.SolicitationIn the RFP it is indicated that the specifications, standards, plans, drawings, data item descriptions, and other pertinent documents cited in this solicitation are not available for distribution but may be examined at the following location: 49 CONS/LGCB, 490 First Street, Suite 2160, Bldg 29, Holloman AFB, NM 88330-8225. Do any of these documents pertain to the demonstration project?All pertinent documents that are going to be provided for the demonstration project have been made available.
Mirador Enterprises, Inc.SolicitationWill the government be releasing " Financial Information Request and Bonding Information Request forms?Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013 which provided bonding information.
Mirador Enterprises, Inc.SolicitationIs this solicitation for a contract to be awarded with a cumulative $75,000,000.00 cap for all of the 3-5 awarded contractors or is it for a contract that has cap of $75,000,000.00 for each of the 3-5 awarded contractors?This contract will have a cumulative total ceiling of $75,000,000.00 for all task orders/delivery orders issued under the contract.
Mirador Enterprises, Inc.SolicitationShould the electronic copy have separate CD’s for each volume or all volumes on one CD?Separate CDs are not required for each volume. All three volumes may be included on one CD. Offerors shall submit the SF 1442 on paper with an original signature.
Mirador Enterprises, Inc.SolicitationDoes the guaranteed minimum award of $2,000.00 apply to each of the 3-5 awarded contractors?The guaranteed minimum applies to each Delivery/Task Order issued/awarded under the MACC.
Barlovento LLCSolicitationOur designers are working on the 65% design submittal for MACC demonstration project and want to confirm the building orientation in relation to the flagged corners at the site. I suggested the attached. Please concur and forward to other bidders if needed.Concur. Refer to site map posted as Amendment #5 on FedBizOps.
Dawn IncorporatedSolicitationCould the government please provide the referenced “Financial Information Request,” so we may send it to our financial institution?

Volume II Technical Proposal Sub Factor 1: Construction Management and Capability: (Page limitation: 20 pages).

a) Bank Reference: In order to assist in determining the offerors’ responsibility, offerors shall complete the Financial Information Request, provide it to their financial institution, and instruct them to complete and return it to the Contracting Office not later than the required proposal submission date.Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013.
Dawn IncorporatedSolicitationCould the government please provide the referenced, “Bonding Information Request,” so we may provide it to our surety company for completion and submission?Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013 which provided bonding information.
Dawn IncorporatedSolicitationb) Bonding: In order to assist in determining the offerors’ responsibility, offerors shall complete the Bonding Information Request, provide it to their surety, and instruct them to complete and return it to the Contracting Office not later than the required proposal submission date.Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013 which provided bonding information.
Dawn IncorporatedSolicitationQuestion: The proposed building is of A-3 occupancy (New Assembly), one story, 2,000 sq.ft., and of Type II-B construction. Per UFC 3-600-01, section 4-2.2, a fire sprinkler system is not required. Per NFPA 101 sections 12.3.5.1, 12.3.5.2, or 12.3.5.3, a fire sprinkler system is not required. Is a fire sprinkler system to be provided for this facility?NO automatic sprinkler system is required for this facility.
Dawn IncorporatedSolicitationThere is no indication if the fire alarm system can be combined with the mass notification system. The Holloman AFB Design Compatibility Standards section 18.A indicates for an individual building mass notification system with LOC, ACU, etc. Please confirm the intent is to provide a separate system for the mass notification that includes separate items such as speakers, strobes and control unit from the fire alarm system.Paragraph B-4.6.1 of UFC 4-010-01 states "New buildings must have a capability to provide real-time information to building occupants or personnel in the immediate vicinity of the building during emergency situations." Provide a MNS with this project with all the components necessary, including speakers, strobes and control panel.
Dawn IncorporatedSolicitationPlease confirm the Mass Notification System is to use Amber strobes per UFC 4-021-01, 4-3.4.2.2 for Air Force installationsYes.
Dawn IncorporatedSolicitationThe RFP and Holloman AFB Design Compatibility Standards do not mention the use of Text Signs for the mass notification system as identified in UFC 4-021-01 4-3.4.2.2. Please confirm Text Signs are not required.Use amber strobe per UFC but NO text signs.
Mesa VerdeSolicitationWhere do we get copies of the Financial Information Request and Bonding Information Request to use for the MACC proposal.These forms will be made available.
RORE, Inc.SolicitationExterior Windows: Are the windows tinted? Exterior Doors: Are the glass doors half glazed or full? Interior Partitions: The interior partitions are specified as 2x4 steel studs. 2x4 are usually specified when in wood framing. I assume the walls can be 3-5/8" x 25 guage metal studs. Interior specialties: What's the material for the toilet and urinal partitions. Partitions are not specified.See Holloman Design Compatibility Stds. Install bronze anodized aluminum frame double hung type windows (double glazed) with bronze tinted glazing as required by the building’s design and Force Protection standards. Install a 3’0” X 7’0” bronze anodized aluminum and tinted glass storefront door at the main entrance (size of glazing up to manufacturer). Install a 3’0” X 7’0” hollow metal door at the service entrance and at mechanical room. Use steel studs for interior wall partitions. For toilet partitions, use HDPE high density plastic polymer in high usage areas/public areas.
SolicitationPage 66, Sub Factor 1, Bank Reference- The Financial Information Request Form that is required to be filled out was not provided within the solicitation documents. Could you please provide the requested form.Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013 which provided bonding information.
Barlovento LLCSolicitationPage 67, b) Consent and Client Authorization Letter- The Consent Letter Form that is required to be filled out was not provided within the solicitation documents. Could you please provide the requested form.See Solicitation Attachment 8-3.
Barlovento LLCSolicitationPage 71- Sub-Factor 1- “Relationships may be demonstrated by a letter from each entity..” Where in the proposal submission should the letters of commitment be placed? Will these letters count against the page count requirements?Place letter attachments at the end of Volume 2 Sub factor 1. Letters do not count against the 20 page limit.
Barlovento LLCSolicitationPage 67- Estimating Capability- Can you please provide us AF Form 3052?Refer to Amendment No. 4 posted on FedBizOps 23 Sep 2013.
SBBIAZSolicitationWhere can we get a copy of the Financial Information Request?Refer to Amendment No. 2 posted on FedBizOps 23 Sep 2013.