19. RFI - Utility well no.1 and CVIA Ag well-BAEYL-304505.pdf

PDF 453 KB Posted

Attached to
Utility Water Well no. 1 and CVIA Agricultural Well BEALE AFB
Solicitation number
FA468622R0004
Issued by

About this file

This request for information and site visit questions and answers document provides details for a federal contract opportunity to install new water wells at Beale Air Force Base in California. The scope of work includes drilling a new utility water well to replace Well No. 1, decommissioning the existing well once replaced. A new agricultural well will also be installed near the Commercial Vehicle Inspection Area. There are optional line items to install electrical transformers and water tanks, and two additional agricultural wells in pastures H2 and B5, which would be solar powered. The contractor will be responsible for obtaining permits, drilling the wells, connecting them to existing infrastructure, and addressing environmental and disposal requirements. The document answers questions to clarify project details such as well locations and specifications, access, permits, design expectations, and responsibilities.

View the file

Other files

File Type Posted
18. ML 3 Draft Site Characterization Report for Dam_.pdf PDF
17. ML 1 Draft Geological and Geotechnical Investigation_.pdf PDF
0. Solicitation - FA468622R0004 - Amendment no.1.pdf PDF
11. AF813 - Environmental Analysis - Utility Well no.1.pdf PDF
15. BAFB Well Install MemoReport 2019-02-07 - Previous Agricultural Wells.pdf PDF
8. Pictures and Plan - Utility Well no.1.pptx PPTX presentation
4. Past Performance Questionnaire - AG WELLS CVIA H2 B5.pdf PDF
1. Statement of Work - Utility Well no.1 and CVIA Agricultural Well.pdf PDF
3. Past Performance Questionnaire - UTILITY WELL.pdf PDF
5. Bid Schedule - Utility Well no.1 and CVIA Well.docx DOCX document
13. Site Concept Drawings - CVIA H2 B5 Agricultural Wells.pdf PDF
6. Hold Harmless Agreement - Utility Well and CVIA Agricurltural wells.docx DOCX document
12. Well Location Overview Picture - Utility Well no.1.pdf PDF
7. Site Map - Utility Well no.1.pdf PDF
2. Wage Determination - CA20220007 - 22JUL2022.pdf PDF
16. EAL Template.xlsx XLSX spreadsheet
14. AF813 - Environmental Assessment - Agricultural Wells H2 and B5.pdf PDF
0. Solicitation - FA468622R0004.pdf PDF
10. Site Plan, Sections & Details - Utility Well no.1.pdf PDF
9. Electrical Details - Utility Well no.1.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Question Answer

When bidding this project we are assuming the working hours are between 7am and 4pm. Do you concur?

Yes. Standard hours apply.

Do all the wells require soil/water/drilling mud containment? Yes. Environmental direction to prevent soil runoff into wetlands and vernal pools.

Well material has a 8-10 week lead time. If the job is awarded material will need to be purchased and then the work for each well will start. Will the time frame be extended to accommodate the supply chain delays?

Please list your long lead items for materials in the exceptions section of the proposal.

Please provide ground water tables for each well? Well 1 - currently at 296 ft total depth H2 - new well, no comparison data B5 - new well, no comparison data CVIA well - estimated 100-200 ft

Please provide Geotechnical report? Two GeoTech Reports have been attached that pertain to Miller dam, close to agricultural well B5. Data is good for 60 feet, providing information on soil conditions. See "ML 1 Draft Geological and Geotechnical Investigation", and "ML 3 Draft Site Characterization Report for Dam".

Please provide the use of each well as we are required to report to the County. It appeared that at least one well that was classified as ag could be used a drinking water.

Well 1 - drinking well H2 - ag well for grazing livestock B5 - ag well for grazing livestock CVIA well - ag well for grazing livestock.

Solicitation & Amendment 01 documents are conflicting and do not include BOTH Wells #1 and #9. The original Solicitation and Attachment 5 Price Schedule list and itemize the work for Well #1.

There is no CLIN for #9, or indication of price breakdown for #9. Then Amendment 01 change includes Page 4, CLIN 0001 is now Well #9, but now there's no place to enter a price for Well #1. Please provide corrected Attachment 5 Price Schedule with both wells.

The solicitation CLIN will be corrected to reflect Well number 1. The bid schedule will remain the same as well.

There is no Scope of Work for Well #9. The site visit included well number 9 because it might have been another option for award. Currently, there are no environmental assessment nor approvals, so it will not be considered within this requirement.

Please confirm that the Range of Magnitude of $250,000 to $500,000 only applies to the Base Bid of Well #1 (or #9) and the CVIA Well.

The ROM is valued for the base (well no.1 & CVIA ag well) and all options included in the solicitation.

SOW states 18” top of casing for flood plan, site visit statement was 24”

SOW line item 1.1.7 & 1.1.8 states 24" above grade for well #1, which is correct.

Just got off the phone with Yuba County Environmental, was asked if Beale had gotten approval from the State to drill these wells?

Beale AFB is in process of completing notification/approval paperwork from the DWRCB-DDW and will forward once in hand.

Utility Well no.1 and CVIA Agricultural Well - FA468622R0004

My biggest concern is the lack of proper motor control present and not listed in requirements. To satisfy requirements for warranty proper motor controls need to be installed. It would be my recommendation to install a VFD.

Please include your recommended approach in your bid then. We rely on contractors with subject matter expertise to bid this contract.

Are you looking for an engineered design for the Well 1 replacement well by a hydrologist and geologist? Please clarify to what extent of the project design that the prime contractor is responsible for.

No, only need a basic drawing showing new well location and line diagram of pipe path to existing piping connection. This is only necessary so we have accurate line diagram of piping runs for planning purposes.

If the engineered design is required for Well 1, then the project schedule may need to be extended from 210 Calendar Days. What extensions can the client provide for this aspect of the project?

See above….N/A

Within the definition of adequate supervision, what level of supervisory staff is required for this job?

Job foreman is adequate. Must be able to coordinate with Yuba county environmental health during permitting and site inspections.

Do you require a Quality Control Manager for this project? No - as long as contractor has C-57 license for drilling wells in CA

Do you require a Safety Manager with OSHA 30 an EM-385 training? No

Do you require an on-site supervisor and what are their job duties and qualifications?

Contractor must provide responsible party that is able to coordinate with Yuba county environmental health during permitting and site inspections.

Site Access: The plans and specifications have identified several wetland spots near the proposed well locations. What kind of access will be available to the well sites during the year and how will that access be impacted by rains and other weather conditions?

There will be limited availibility for access during the "Limited Operating Period". No work will be conducted between 1 November and 1 May, unless specifically approved by the Beale AFB Natural Resources Manager (NRM); if weather continues to be fair. Work continuation is dependent on prevailing conditions, forecasted weather, and whether or not activities will damage soil or vegetative cover. The NRM must be contacted to obtain permission to work after each storm event. Permission to work after 1 November will not be granted once wetlands are activated (standing water present). The only outdoor work allowed 12 hours before or after a storm event is the inspection, installation, and/or maintenance of erosions controls.

What size well, in terms of the casing diameter and completed well depth is required for the Well 1 replacement well?

We defer to the experienced well contractor to provide recommendation on well size to meet the 1,200 gpm requirement.

For awareness, current wells are 16" dia casing, with 75Hp pumps at a depth of approximately 300ft. We anticipate new well will be of similar size and dimensions.

What casing material and perforation style is required for the Well 1 replacement well?

Due to depths anticipated, and in accordance with CA DWR Water Well Construction criteria, section 12, it is preferred to have steel casing.

What drilling method is required for Well 1? As the subject matter expert, we leave this to the qualified C57 licensed contractor to provide recommendation.

Is isolated zone sampling and testing a component of the Well 1 Project? If so, how many zones will there be?

Do not know what this is. Well 1 is located in an established well field with a reliable aquafer. It is not anticipated that zone sampling and testing is required. This is a replacement of an exiting and functioning well only.

What water quality standard is the Well 1 Water required to meet? Although the water is processed at a water treatment facility on base, for permitting purposes see CA DWR well criteria, secton 15 on water quality, Appendix D. Also see Chapter 15, "Domestic Water Quality" of Title 22 California Administrative Code.

What are the requirements for the filter pack materials for the replacement Well 1?

Filter pack shall be selected based on aquifer materials and shall be selected in conjunction with the screen size. The filter pack and screen size shall be determined by the contractor to provide sediment free water at the required GPM.

What is the sanitary seal depth requirement for Well 1? As the subject matter expert, we expect that the qualified C57 licensed contractor will know and verify this information, however, according to CA well standards, the minimum depth per section 9 is 50 ft for community wells.

Working Hours: some of the drilling processes such as well drilling, zone sampling, and well development will need to run around the clock. What are the conditions for working hours on this project?

With prior coordination, this can be worked with the Gov't since none of these wells are in occupied buildings.

Is there a Buy American Made Materials requirement for this job? Yes, Clause "52.225-9 Buy American-Construction Materials" clause is included in the solicitation.

Submittals: what is the turnaround time on submittals for the well drilling process?

Materials submission approval should take no longer than 5 business days. Design and drawing are not a requirement and should have no impact on the drilling process.

What level of turbidity is acceptable for the development water? Please refer to Yuba County water well permit criteria for drinking and agricultural well turbities. Plan on providing a settlement tank to minimize the release of tubid water to the canal. Sludge/solids will need to be disposed of offsite.

What permits are required for discharging the development water into the Yuba County ditches and the creek?

The government is reasearching on the permit to flush wells in canal, and will be responsible for obtaining the permit.

Where is the option for drilling, developing, and equipping Well #9? I did not see that in the specifications.

Well no.9 will not be included within the requirement.

Site Visit Questions Answers

The road to Ag well B5 is made of gravel and long. Is there another way to get materials and equipment to the site?

There is a gate off the main road, located on the main fence line that may be accessed to drop off materials and equipment

Where is the B5 well to be located? The contractor may place the well anywhere, as long as it's located 100 feet away from the main fence line, and not built directly on top of drainage on site. Exact location to be confirmed onsite with environmental representatives.

Is there any Unidentified Explosive Ordinances monitoring the B5 area?

No known UXO in the B5 vicinity. If any discovered, contractor is expected to cease work and notify 9 CES immediately.

What is the Government's level of expectation for design for the Ag wells?

There are no design elements tied to the Agricultural wells.

What is the Government's level of expectation for design for the Utility well?

There is very limited design for the utility wells, as indicated on the SOW. Only a red line drawing showing the location of the new well, and the electrical and utility line hook ups. Design is limited to requirements of UFGS 331113.

At Ag well H2, there is no gate. How should the contractor enter the designated area?

Temporarily taking down the barbed wire during construction is acceptable, as long as contractor leave the area as previously found

Is the contractor responsible for removal of waste and cuttings from all well sites?

Yes

How are the Government's depths determined for each well? Depths are based on historical data and actual well operating depths.

Does the contractor need to coordinate and get permits through Yuba county?

Yes, the requirement states that the contractor will be responsible in obtaining the correct permits through the county and state of California. This includes submitting required well completion report to the state as required.

Are there any freeze controls for the Ag well? No.

Are any of the Ag wells sites within the vernal pools? Well #9. Well #1 and CVIA wells are adjacent to vernal pools, therefore the need for runoff control measures.

At Ag Well H2 site, will any construction ground protection mats be required to cross from the road, over the ditch, into the well development site?

yes, these are runoff ditches that will need to be maintained for runoff. Field does not require ground protection.

Are any of the Ag wells online? No, they are all independent.

Is a new trough part of the requirement for Ag Pasture wells? SOW 5.3.7 and 5.4.7 state: provide a new concrete water trough.

What pad is necessary for the water trough at pasture wells? SOW 5.3.8 and 5.4.8 state: Grade and install 15x15 foot gravel pad.

Who is responsible for the water storage tank for pasture AG wells? SOW 5.3.3 and 5.4.3 state: (contractor will) provide a new on-site 1,500 gallon poly storage tank.

At the CVIA well, who determines the electrical pot (transformer) is the right size?

The contractor. In the event that the electrical pot cannot be used, there is an option in the contract to replace the transformer.

Will the new CVIA Agricultural well the only well hooked up to the electrical pot transformer?

Yes.

What is the process for testing the current pressurized tank at the

CVIA?

This is up to the expertise of the contractor.

Option 2 is to replace CVIA pressurized tank with a 1500 gallon poly tank. Is this correct? We are only asking because a poly tank will not function the same as a metallic tank, as far as pressurizing is concerned.

SOW - Contract Options

2) Requires the complete replacement and integration of the new poly tank and pressurization system.

Refer to SOW for details

Will the contractor have free access through locked gates at utility well number 1?

Yes.

Does the contractor need to obtain permits for flushing clean water into the county neighboring Brophy canals at Utility well no1 site?

The government is reasearching on the permit to flush wells in canal, and will be responsible for obtaining the permit.

What is currently wrong with Utility Well number 1? Well has sediment in effluent due to age and high bacteria levels due to not having annular seals.

Do all existing pipes stay at Utility well number 1 site? yes Does Utility well number 1 require drinking water test? Title 22? yes What year was the liner installed in Utility Well no 1? Originally drilled in 1942, redrilled in 1981, 14" liner installed in 1999.

What is the existing electrical system at Utility Well no 1? 3 phase, 240 volt, with a 75 horse power.

Are there any lead paint concerns at utility well no.1 site? Not at this time. It is the contractor's responsibility for hazmat testing.

Please review SOW "1.6 Environmental and Disposal Considerations"