Attachment 22 - Past Performance Questionaire (PPQ) v1.2 (Final) -- 20250210.docx

DOCX document 43 KB Posted

Attached to
FA466425R0001 - SABER MAC IDIQ B+4 @ March ARB Federal contract opportunity
Solicitation number
FA466424R0004
Issued by
Department of the Air Force Reserve Command

About this file

This is a Past Performance Questionnaire (PPQ) template for the Air Force Reserve Command's Streamline Acquisition Base Engineering Requirement (SABER) program at March Air Reserve Base, with responses due by February 28, 2025. The questionnaire is designed to evaluate contractors' past performance on previous contracts that demonstrate their ability to perform SABER work.

The PPQ contains 24 performance evaluation questions covering areas such as project management, quality control, problem resolution, schedule adherence, and small business compliance. Respondents must rate contractors on a scale from Exceptional to Unsatisfactory across these criteria. The document is specifically tied to solicitation FA466425R0001, which is an 8(a) small business set-aside IDIQ contract with a $7.5 million ceiling for construction, maintenance, repair, and renovation projects at March ARB. The questionnaire will be used as source selection information for evaluating potential contractors.

View the file

Other files for this federal contract opportunity

Other files attached to FA466425R0001 - SABER MAC IDIQ B+4 @ March ARB, newest first.
File Type Posted
Attachment 01 - SABER MAC IDIQ Master SOW v1.9 (Final) -- 20250207.pdf PDF
Attachment 12 - Environmental Protection Specs and Guidance -- 20241211.pdf PDF
Attachment 17 - SABER MAC IDIQ RFP Section L v1.7 (Final) -- 20250210.pdf PDF
Attachment 18 - SABER MAC IDIQ RFP Section M v1.5 (Final) -- 20250210.pdf PDF
Attachment 20 - Coefficient Pricing Worksheet Instructions v1.7 (Final) -- 20250210.pdf PDF
Attachment 26 - SABER MAC IDIQ RFI Answers v1.7 (Final) -- 20250210.pdf PDF
Attachment 03 - SABER MAC IDIQ Master Specs VOL 2 v1.2 (Final) -- 20250207.pdf PDF
Attachment 14 - MARB Base Pass Request v1.0 (Final) -- 20240712.pdf PDF
Attachment 15 - SABER MAC IDIQ Ordering Instructions v1.4 (Final) -- 20250210.pdf PDF
Attachment 21 - Conflict of Interest Statement v1.1 (Final) -- 20250207.pdf PDF
Attachment 23 - SABER MARB Relevant Contracts v1.1 (Final) -- 20250207.pdf PDF
Attachment 25 - Past Performance Subcontractor Consent Letter v1.0 (draft) -- 20210520.pdf PDF
Attachment 00 - FA466425R0001-0005 - Amendment SF1442 v1.7 (conformed) -- 20250210.pdf PDF
Attachment 02 - SABER MAC IDIQ Master Specs VOL 1 v1.2 (Final) -- 20250207.pdf PDF
Attachment 10 - SABER Submittal Register -- 20250203.pdf PDF
Attachment 11 - Environmental Protection Plan -- 20240514.pdf PDF
Attachment 13 - MARB Contractor Handout v1.1 (Final) -- 20241113.pdf PDF
Attachment 16 - DOL WD DBA CA2025-0025 Mod3 -- 20250207.pdf PDF
Attachment 19 - Coefficient Pricing Worksheet v3.3 (Final) -- 20250210.xlsx XLSX spreadsheet
Attachment 24 - Financial Institution Reference Sheet v1.1 (draft) -- 20210520.pdf PDF
Attachment 03 Coefficient Pricing Worksheet updated as of Oct 4 2024.xlsx XLSX spreadsheet
Attachment 08 - Section L Instructions to Offerors_Updated Oct 4 2024.docx DOCX document
Solicitation Amendment FA466425R00010001 SF 30.pdf PDF
Attachment 10 - Past Performance Questionaire (PPQ)_Updated Oct 4 2024.docx DOCX document
Attachment 03 - Coefficient Pricing Worksheet_Updated Oct 4 2024.xlsx XLSX spreadsheet
Q and A KTR RFI_Final.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Controlled Unclassified Information When completed, this document is Source Selection Information IAW FAR 2.101 and 3.104.

Section L Attachment: Past Performance Questionnaire – Attachment 22 of FA466425R0001 The 452nd MSG PK Contracting Squadron of the Air Force Reserve Command is in the process of competitively selecting a source for a Streamline Acquisition Base Engineering Requirement (SABER) program.

One of the considerations in proposal evaluation is the verification of the offerors past performance on contracts or other work efforts which reflect the offeror's ability to perform on the proposed effort. We depend on information received from organizations such as yours, which have had first-hand experience with the offeror, for the evaluation of the offeror's performance on those contracts or work efforts.

Our areas of interest regarding the offeror are summarized in the enclosed questionnaire. To meet our acquisition milestones, we request your written response no later than 28 Feb 2025 after your receipt of this letter.

To assist you in preparing your response and expediting your reply, the questionnaire may be filled out electronically and submitted with your proposal. Please email jon.aaron@us.af.mil if you have any questions. Your completed questionnaire will become a part of the official source selection records.

Your assistance is greatly appreciated, and your prompt response will be one of the keys to the successful and timely completion of this Source Selection.

Signed_________________________ Jon D. Aaron (Procuring Contracting Officer)

1 Attachment Past Performance Questionnaire

Section 1: Contract Identification

A. Contractor (Company/Division):

B. Contractor Cage Code:

C. Contract Number:

D. Contract Type (e.g., FFP, FPIF, CPIF, CPFF, etc.):

E. Program Title:

F. Brief Program Description:

G. Program Phase (e.g., Engineering & Manufacturing Development (EMD)):

H. Period of Performance

1. Original Schedule (assuming all options exercised):

Beginning Date _________ through ____________

2. Current Schedule (assuming all options exercised):

Beginning Date _________ through ____________

3. Reason for difference (if applicable):

I. Contract Dollar Value

1. Original maximum contract dollar value (assuming all options exercised): $

2. Current maximum contract dollar value (assuming all options exercised): $

3. Reasons for difference between original and current contract dollar value (if applicable):

J. Description of work performed:

K. Was this a competitively awarded contract? ☐ Yes ☐ No

L. Contractor’s Role: ☐ Prime Contractor ☐ Subcontractor ☐ Key Personnel

Note: If offeror holds or has held other contracts with your agency/organization in the last three (3) years, please complete separate Past Performance Questionnaire forms for those contracts as well.

Section 2: Customer or Agency Identification

A. Customer or agency name:

B. Customer or agency description (if applicable):

C. Geographic description of work performed under this contract (i.e., local, nationwide, worldwide, other Commands):

Section 3: Respondent Identification

A. Respondent’s name:

B. Respondent’s title:

C. Respondent’s phone/fax number/e-mail address:

D. Length of time (number of years/months) respondent worked on subject contract and description of responsibility/position/role:

E. Other suggested points of contact:

Section 4: Performance Information

In the table below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. Provide supporting information for each response in the space provided. Attach additional pages if more space is needed. The performance rating scale is defined as follows:

Code Performance Rating

E EXCEPTIONAL – Performance meets contractual requirements and exceeds many requirements to the Government’s benefit. The contractual performance being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

V VERY GOOD – Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

S SATISFACTORY – Performance meets contractual requirements. The contractual performance being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

M MARGINAL – Performance does not meet some contractual requirements. The contractual performance being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

U UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

N/A NOT APPLICABLE – Unable to provide a rating. Contract did not include performance for this aspect, performance was not observed, or information was not available. Do not know.

Note: The following are SAMPLE questions. Past Performance evaluation teams MUST construct a simple and concise Past Performance Questionnaire, tailored to seek out key information tied to the significant aspects of the planned acquisition. Avoid questions that can be answered with a “yes” or “no” but instead include probing and direct questions to draw out the required information desired.

The Contractor:
E
V
S
M
U
N/A

1. Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.

SUPPORTING INFORMATION:

2. Demonstrated the ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.

3. Delegated authority to project managers and supervisors commensurate with contract requirements.

4. Home office participated in solving significant local problems.

5. Followed approved quality control plan.

6. Provided effective quality control and/or inspection procedures to meet contract requirements.

7. Corrected deficiencies in timely manner and pursuant to their quality control procedures.

8. Provided timely resolution of contract discrepancies.

9. Identified problems as they occurred.

10. Suggested alternative approaches to problems.

11. Displayed initiative to solve problems.

12. Developed realistic progress schedules.

13. Met established project schedules.

14. Provided timely resolution of warranty defects.

15. Was responsive to contract changes.

16. Provided adequate project supervision.

17. Obtained consent of surety for increases in bonding as work-in-progress increased.

18. Paid subcontractors/suppliers in a timely manner.

19. Provided accurate and complete line item cost proposals including all aspects of work required for each task.

20. Cooperated with Government personnel after award.

21. Met or exceeded small business and small disadvantaged business goals set forth in the approved subcontracting plan.

22. How would you rate the contractor's overall performance on this contract?

23. Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain.

EXPLANATION:

☐ Yes ☐ No

24. Would you award another contract to this contractor? If not, explain.

EXPLANATION:

☐ Yes ☐ No

IF THIS WAS A GOVERNMENT CONTRACT:

Did this contract include FAR 52.219-9, Small Business Subcontracting Plan?

☐ Yes ☐ No

If yes, did the contractor comply with the clause? Please explain.

Did this contract include FAR 52.219-8, Utilization of Small Business Concerns?

☐ Yes ☐ No

If yes, did the contractor comply with the clause? Please explain.

Additional remarks:

[click and pick the date]

Respondent’s Signature Date

Controlled Unclassified Information Page 8 of 8