TE-07 - Contractor Drawing and GIS Data Standards.pdf

PDF 107 KB Posted

Attached to
Simplified Acquisition of Base Engineer Requirements (SABER)
Solicitation number
FA4661-10-R-0002
Issued by

About this file

SOW Technical Exhibit 07 (of 10) Contractor Drawing and GIS Data Standards

View the file

Other files

File Type Posted
08-0082 SOW —
05-0032 - Concept Drawing —
05-0032 - Concept Drawing —
DYESS SABER SOLICITATION FA4661-10-R-0002.pdf PDF
UFC 4-010-01 - DoD Minimum Aniterrorism Standards for Buildings.pdf PDF
05-0032 - Concept Drawing —
05-0032 09-0106 SOO —
SABER Q A.pdf PDF
basewallmap2007image.pdf PDF
TE-08 - Work Clearance Request.pdf PDF
08-0082 SOW.pdf PDF
TX Demo Reno Notification Form.pdf PDF
TE-10 - DAFB Technical Specifications.pdf PDF
Asbestos Survey 7422 - 31 Aug 09.pdf PDF
DYS-W-1201 - Sheet 2 of 5.PDF PDF
AF Form 66 Submittal Requirements.pdf PDF
05-0032 - Concept Drawing-Final-10.pdf PDF
05-0032 09-0106 SOO.pdf PDF
05-0032 - Concept Drawing-Kitch-4.pdf PDF
05-0032 - Concept Drawing-Arch-3.pdf PDF
TX100300 03-19-2010 TX300 Building.pdf PDF
TE-05 - Applicable Codes Regulations and Standards.pdf PDF
TE-02 - Construction Data Worksheet.pdf PDF
05-0032 - Concept Drawing-Built-In Cab-5.pdf PDF
Attach 3 - Question Form.pdf PDF
TE-06 - SABER SOW Package Format.pdf PDF
TX100028 3-12-2010 TX28 Heavy and Highway.pdf PDF
TX Demo Reno Notification Form Instructions.pdf PDF
Attach 5 - Reservation Form.pdf PDF
TX100307 03-12-2010 TX307 Residential.pdf PDF
05-0032 - Concept Drawing-Floor-7.pdf PDF
TE-01 - Applicable Contractor Coefficient Requirements.pdf PDF
DYS-W-1201 - Sheet 1 of 5.PDF PDF
05-0032 - Concept Drawing-Fire CO Det-8.pdf PDF
Attach 4 - Past Performance Questionnaire —
DYS-W-1201 - Sheet 4 of 5.PDF PDF
05-0032 - Concept Drawing-Cover-1.pdf PDF
SOW-SABER Statement of Work FA4661-10-R-0002.pdf PDF
05-0032 - Concept Drawing-Bath-6.pdf PDF
DYS-W-1201 - Sheet 5 of 5.PDF PDF
05-0032 - Concept Drawing-Comm-9.pdf PDF
08-0082 AF Form 66.pdf PDF
DYS-W-1201 - Sheet 3 of 5.PDF PDF
UFC 3-600-01 - DESIGN-FIRE PROTECTION.pdf PDF
08-0082 SOO Atch 1.pdf PDF
FA4661-10-R-0002 SOLICITATION.pdf PDF
TE-03 - Equipment Warranty-Guarantee Record.pdf PDF
TE-04 - List of Acronyms.pdf PDF
TE-09 - Definitions.pdf PDF
05-0032 - Concept Drawing-Demo-2.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Exhibit 7

CONTRACTOR DRAWING AND GEOSPATIAL INFORMATION SYSTEM (GIS)

DATA STANDARDS

TE-7 Page 1 of 6

NOTE: All labor, equipment, materials, and rentals/fees required to provide Drawing and

Geospatial Information System Data shall be at no additional cost to the Government and considered field overhead, therefore part of the Contractor’s coefficient.

1. Worksite Drawings. The contractor shall: continually maintain accurate record of all approved changes, corrections, deviations, and discoveries of previously unknown or non-included conditions, and modifications from the plans and details of the approved SOW Package drawings, and shall immediately redline update.

1.1. Underground Utilities. Where underground utilities are installed, note the elevation of the utility installed every 30 feet. Where new utilities cross-existing utilities, note the elevation of the new and existing utility and the vertical and/or horizontal separation. Where new utilities run parallel to new and existing utilities, note the elevation at which installed and the horizontal and/or vertical separation between utilities.

2. GIS Data. The contractor shall use conventional surveying and other methods, such as total station or Global Positioning System (GPS) for collection of As-Built information at an accuracy level IAW Geospatial Positioning Accuracy Standards, Part 3: National Standard for Spatial

Data Accuracy, published by the Federal Geographical Data Committee (FGDC), dated July

1998. This document can be found at http://www.fgdc.gov/standards/status/sub1_3.html. All survey data provided shall be provided to the Government in a digital format with an attached

Survey Report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams, and field survey data. A Survey Control

Database (consisting of a survey marker database and a survey traverse database) shall be produced for all survey control points established under this contract, and delivered in a .dbf or

ASCII comma-delimited format. If GPS is used, the contractor shall use survey grade GPS, at an accuracy level of +/- 2cm, when appropriate, to collect data to be overlaid onto the installations orthographic and/or base map. All map and worksite plan coordinates shall be mated (geo-referenced) to earth surface grid coordinates (Northings and Eastings in WGS 1984 UTM Zone

14 North Meters for horizontal and NAVD 88 for vertical).

2.1. All locational feature data (points, lines, polygons) collected shall be delivered in ESRI

ARCGIS (shapefile, Geodatabase) format along with the original source files. The Geospatial files shall have an external spatial reference file (.prj) attached specifying the parameters of the coordinate system used (as provided by the government). All topologically correct geospatial data shall overlay on the installations latest orthorectified imagery provided by the government.

All accuracy errors shall be reported to the contract project manager.

2.2. Feature Attributes. The contractor shall identify the classification, type, size, location, ID number, and any other necessary attributes (specified by the Government) for all surveyed, mapped, designed, or proposed features. All symbol libraries, font libraries, text sizes, text formats, and text placements should be prepared in accordance with Spatial Data Standards for

Facilities, Infrastructure and Environment (SDSFIE). The contractor shall not develop new libraries without prior written approval from the Government.

http://www.fgdc.gov/standards/status/sub1_3.html

TE-7 Page 2 of 6

2.3. All graphic and non-graphic data will be collected in the format defined by the CADD/GIS

Technology Center’s Spatial Data Standards/Facility Management Standards for Facilities, Infrastructure, and Environment (SDSFIE) release 2.6 (or the most current version available), except where modified by the Government. This document can be found at http://tsc.wes.army.mil/products/tssds-tsfms/tssds/projects/sds/.

2.4. The contractor shall provide metadata files for all locational data produced under this contract. The metadata file shall conform to the Federal Geographic Data Committee’s “Content

Standard for Digital Geospatial Metadata, Version 2.0” (or latest version) found at http://www.fgdc.gov/standards/. The output from metadata generator software shall be the standard format for all metadata files created under this contract. In addition, the metadata data shall be provided in ASCII text format. The digital metadata files shall be provided to the

Government along with each product deliverable, unless otherwise approved in writing by the

Government.

2.5. All exterior and interior features shall include electronic imagery to be included with all

GIS and CADD features conforming to standards as outlined in 1.2.4 and 1.3.3.

3. Computer Aided Drafting and Design (CADD) Data. All design, surveying, drawings, maps, and details provided under this contract shall be developed using Computer Aided

Drafting and Design (CADD) software and procedures conforming to the following criteria:

3.1. CADD Standards: The contractor shall prepare all drawings, details, and data IAW 7CES

DAFB CADD Template (standard drawing size shall be Architectural “D” size), and IAW the

Tri-Service Spatial Architectural/Engineering/Construction (A/E/C) Computer Aided Design and

Drafting (CADD) Standards. The Contractor shall submit a written request for approval of any deviations from the Government's established CADD standards. The Contractor shall request in writing for Government approval any deviations from the 7CES DAFB CADD Template.

3.1.1. Government Provided Templates. The Government will provide: electronic seed/prototype files; electronic detail library; electronic symbol library; electronic text and font library; and the electronic line style/type library.

3.2. CADD Software Compatibility: The Contractor shall ensure all project drawings are generated utilizing CADD software compatible to the latest edition utilized by 7 Civil Engineer

Squadron, Project Development Section, DAFB (current target system is Microsoft Windows based AutoCAD Map 2008) in three-dimensional AutoCAD native electronic digital format

(.dwg). The contractor shall ensure that all digital files and data, to include base files, reference files, and cell libraries, are compatible with the Government's target system (to include basic and advanced CADD software, platform, and database software). [Note: Compatible is defined as data that can be accessed directly by the target system without translation, preprocessing, or post-processing of the electronic digital data files.]

3.3. CADD Deliverables: All CADD deliverables shall be GIS compatible IAW paragraph 2, and conform to the following requirements:

http://tsc.wes.army.mil/products/tssds-tsfms/tssds/projects/sds/ http://www.fgdc.gov/standards/

TE-7 Page 3 of 6

3.3.1. Edges of all digitized maps shall exactly match those of all adjacent drawings.

3.3.2. All digital representations of common boundaries for all graphic features shall be equal, regardless of level and/or layer. Each feature within a drawing theme shall be represented by a single graphic element (e.g. polygon or line/string).

3.3.3. Lines/strings, which represent the same graphic element, shall be continuous (i.e. not broken or segmented), unless that segmentation represents a specific visual line type.

Lines/strings representing the same type of data shall not cross except at intersections.

3.3.4. Polygons shall close (i.e. the first x- and y-coordinates must exactly match the last x- and y-coordinates). Each polygon shall have a single unique centroid where attributes (i.e. an attribute table) can be attached. Polygons of the same coverage shall not overlap and shall cover the area of interest completely (i.e. no gaps in coverage).

3.3.5. All graphic elements that connect shall exactly connect digitally, without overlaps or gaps.

3.3.6. Straight lines shall only be represented beginning and ending “x” and “y” coordinate points. Lines/strings shall not cross back on themselves, or be of zero length.

3.3.7. All map and worksite plan coordinates shall be mated (geo-referenced) to earth surface grid coordinates (Northings and Eastings in WGS 1984 UTM Zone 14 North Meters for horizontal and NAVD 88 for vertical).

3.4. Non-Graphical Database Information: The Contractor shall prepare all non-graphical database information in Oracle native format compatible with the Government target system

IAW paragraph 3.2. The Contractor shall maintain all linkages of non-graphical data: with graphic elements, relationships between database tables, and report formats. All database tables shall conform to the structure and field-naming guidance provided by the most current version of

CADD/GIS Technology Center’s Spatial Data Standards/Facility Management Standards for

Facilities, Infrastructure, and Environment (SDSFIE) release 2.6, unless otherwise specified by the Government. This document can be found at http://tsc.wes.army.mil/products/tssds-tsfms/tssds/projects/sds/.

3.5. Electronic Digital Media (EDM) Deliverables: The Contractor shall submit all EDMs in

CD-R or DVD-R format.

3.5.1. External Labeling Requirements. As a minimum, the labels shall reflect:

3.5.1.1. The Contract Number, Task Order Number (when applicable), Government assigned

Project Number, and date.

3.5.1.2. Format and version of operating system software.

TE-7 Page 4 of 6

3.5.1.3. Name and version of utility software used for preparation and transfer to the EDM (e.g., compression/decompression).

3.5.1.4. Sequence number of the EDM.

3.5.1.5. List of files on the EDM.

3.5.1.6. All label information will be included on the CD as a text file titled “CD Label”.

3.5.2. EDM Preparation Requirements. Prior to file transfer to the EDM the Contractor shall:

3.5.2.1. Remove all extraneous graphics outside the border area and set the active parameters to a standard setting or those in the Government-furnished seed file.

3.5.2.2. Ensure all reference files are attached without device or directory specifications.

3.5.2.3. Ensure to include all required graphic and non-graphic files (i.e., color tables, pen tables, font libraries, cell libraries, user command files, plot files, etc.). The Contractor shall provide on the EDM, all cells/blocks not previously provided as part of the Government templates.

3.5.2.4. Ensure all support files are co-located in the same directory, and references to those files do not include device or directory specifications.

3.5.2.5. Include any standard sheets (i.e., abbreviation and standard symbol sheets) necessary as required to present a complete project.

3.5.2.6. Document all developed fonts, tables, not provided in the Government templates. The contractor shall obtain Government approval prior to substituting any Government template fonts, line types, tables, and cells/blocks.

3.5.2.7. Produce each drawing sheet with its own separate plot file compatible to the plotter configuration used by the 7 Civil Engineer Squadron.

3.5.3. Drawing Development Documentation. Include complete documentation concerning development of each drawing in the first eight levels/layers IAW the Tri-Service Spatial

Architectural/Engineering/ Construction (A/E/C) Computer Aided Design and Drafting (CADD)

Standards. The following information for each drawing shall also be included in the non-plot level/layer, X-****-NPLT:

3.5.3.1. Data input method (e.g., keyed in, total station instrument download (include name and model)).

3.5.3.2. Drawing development history (e.g., date started, modification date(s) with description of item(s) modified, author's name)

TE-7 Page 5 of 6

3.5.3.3. The names of the reference, cells/blocks, symbols, details, tables, and schedule files required for the finished drawing.

3.5.3.4. Level/layer assignments and lock settings.

3.5.3.5. Text fonts, line styles/types used, and pen settings.

3.5.4. EDM Transmittal Letter. The Contractor shall provide a transmittal letter dated and signed by the appropriate Contractor's representative for each EDM. Letter shall include:

3.5.4.1. Information included on the external label of each EDM, the total number delivered, and a list of the names and descriptions of the files included.

3.5.4.2. Instructions for transferring the files from the EDM.

3.5.4.3. Virus-Free Certification. The contractor shall provide: certification that all EDM are free of computer viruses; the name(s) and release date(s) of the virus-scanning software used for analysis; the date the virus-scan was performed; and the operator's name. The Contractor’s version of virus-scanning software shall be the most current release by that manufacturer.

3.5.5. Plot File Development and Project Documentation Information Letter. The Contractor shall provide, in conjunction with the EDM Transmittal Letter:

3.5.5.1. Documentation of the plot file for each drawing required to duplicate the creation of the plot file by the Government. This documentation shall include: the plotter configuration (e.g., name and model of plotter), pen settings, drawing orientation, drawing size, and any other special instructions.

3.5.5.2. Instructions of how to generate plotted, or paper copy drawings from the plot files.

3.5.5.3. List of all pre-approved deviations from the Government's template.

3.5.5.4. List of all new figures, symbols, tables, schedules, details, and other cells/blocks created for the projects, which were not provided to the Contractor with the Government-furnished materials, and any associated properties.

3.5.5.5. List of all non-IGES crosshatch/patterns used.

3.5.5.6. List of all database files associated with each drawing, and the description and documentation of the database format and schema design.

3.5.5.7. Data will be provided in the formats listed in paragraph 2.1 compatible with Dyess

AFB current GIS data.

TE-7 Page 6 of 6

4. Government Provided Data. The Government will provide the contractor with data and information concerning all necessary and pertinent functions and principal features of the identified project when available. These items may include:

4.1. The installation's latest geo-referenced digital planimetric data and/or base map in ESRI

Arc/Info format, or best format available, with associated data files.

4.2. The installation’s latest orthorectified imagery and specified geospatial parameters

(coordinate system, datum, projection, distance units).

4.3. A copy of CADD/GIS Technology Center’s Spatial Data Standards/Facility Management

Standards for Facilities, Infrastructure, and Environment (SDSFIE) release 2.6 (or latest version) on CD-ROM.

4.4. A copy of “Geospatial Positioning Accuracy Standards, Part 3: National Standard for

Spatial Data Accuracy,” published by the Federal Geographic Data Committee (FGDC) in

Adobe Acrobat Reader (.pdf) format.

4.5. Frequency settings for the Real-Time Kinematic (RTK) GPS Base Station and the preferred

GPS receiver specifications.

4.6. Any other data or schematics deemed necessary for project completion, pending approval from the Government.

4.7. One electronic copy of Tri-Service A/E/C CADD Standards on CD-ROM.

4.8. One electronic copy of 7 CES DAFB CADD Standards on CD-ROM.

4.9. Electronic seed/prototype files containing the Government's preset standard settings, or workspaces (e.g., working units, color table library, line style/type library, level/layer structures, text font library, symbol cells/blocks) for use by the Contractor. The seed/prototype files will be provided on CD-ROM.

4.10. Electronic reference files containing the Government's standard border sheets. Reference files will be provided on CD-ROM.

4.11. Electronic cell/block or reference files containing the Government's standard project details on CD-ROM.

5. As-Built Drawings/Deliverables. At the time of beneficial occupancy, the contractor shall submit As-Built data incorporating all requirements of this standard. The As-Built

Drawings/Deliverables (plans, surveys, studies, imagery, designs, etc.) shall be IAW paragraph

3. Worksite Redline Drawings shall not be used as a substitute for this requirement.

File details come from the government source that posted it. Updated .