This is a Questions and Answers document for solicitation FA4626-25-R-0001, DSN/CSN Demo Dorm 631, which clarifies various aspects of the design-build demolition project.

Key details include: a site visit scheduled for December 18, 2024 at 11:00 a.m. MST, with interested parties required to submit a Contractor Entry Authorization List by December 9, 2024; the proposal deadline has been extended to January 23, 2025, with questions due by January 9, 2025. The document clarifies technical requirements including: timber piles must be cut 10' below ground surface with the remaining 20' left in place; the contractor is responsible for terminating HTHW feed and removing service piping; demolished concrete and CMU materials must be removed from site and disposed of off-base; and the scope includes both 100% design work and demolition/site improvements under the same contract.

View the file

Other files for this federal contract opportunity

Other files attached to DSN/CSN Demo Dorm 631, newest first.
File Type Posted
Solicitation Amendment - FA462625R00010005.pdf PDF
Solicitation Amendment FA462625R00010005 SF 30.pdf PDF
3_1991 Concrete Duct Bank.pdf PDF
9_QA Demo Dorm 631 (Revised 15Jan25).pdf PDF
Solicitation Amendment FA462625R00010004 SF 30.pdf PDF
Solicitation Amendment - FA462625R00010004.pdf PDF
3_2009 Peaked Roof Plan.pdf PDF
10_Dorm 631 Photos.pdf PDF
8_WD MT20250066 (03Jan25).pdf PDF
Solicitation Amendment FA462625R00010003 SF 30.pdf PDF
9_QA Demo Dorm 631 (14Jan25).pdf PDF
Solicitation Amendment - FA462625R00010003.pdf PDF
2_Design Build SOW (Revised 14Jan25).pdf PDF
7_Past Performance Reference Sheet (Revised 14Jan25).docx DOCX document
6_Sections L and M (Revised 14Jan25).pdf PDF
Solicitation Amendment - FA462625R00010002.pdf PDF
2_Design Build SOW (Revised 19Dec24).pdf PDF
Solicitation Amendment FA462625R00010002 SF 30.pdf PDF
3_Bldg 631 Utility Site Plan (Revised 19Dec24).pdf PDF
3_Bldg 631 Site Plan Map (Revised 19Dec24).pdf PDF
Site Visit Sign in_18Dec24.pdf PDF
9_QA Demo Dorm 631 (17Dec24).pdf PDF
9_QA Demo Dorm 631 (12Dec24).pdf PDF
7_Past Performance Reference Sheet (Revised 09Dec24).docx DOCX document
9_QA Demo Dorm 631 (09Dec24).pdf PDF
Solicitation Amendment - FA462625R00010001.pdf PDF
Solicitation Amendment FA462625R00010001 SF 30.pdf PDF
7_Past Performance Reference Sheet.docx DOCX document
9_QA Demo Dorm 631.pdf PDF
6_Sections L and M (Revised 02Dec24).pdf PDF
Newest CEAL CES 21 Oct 2024.xlsx XLSX spreadsheet
3_1975 Plans.pdf PDF
8_WD MT20240066 (01Nov24).pdf PDF
Solicitation - FA462625R0001.pdf PDF
5_ACM LBP Reports.pdf PDF
3_1996 Reno As Builts.pdf PDF
6_Sections L and M.pdf PDF
2_Design Build SOW.pdf PDF
1_Combined Specifications.docx DOCX document
7_Past Performance Reference Sheet.docx DOCX document
4_Submittal Schedule.xlsx XLSX spreadsheet
3_2005 Plans.pdf PDF
3_Bldg 631 Site Plan Map.pdf PDF
3_Bldg 631 Utility Site Plan.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 1 Will scaffold be needed for this project? That is up to the Contractor. 1

2 Is a site visit scheduled for the DSN/CSN Demo Dorm 631 bid?

A site visit has been scheduled for 18 December 2024 at 11:00 a.m. Mountain Standard Time (MST), see FAR Clause 52.236-27, Site Visit (Construction)(Alt I) for address of meeting location.

All interested parties must submit a signed Contractor Entry Authorization List (CEAL) with the required information to the Contract Administrator (Mr. Cody Babinecz) no later than 11:00 a.m.

MST on 09 December 2024. A blank CEAL is provided in the attachments section of the solicitation in SAM.gov. If there are any questions or concerns, please contact Mr. Babinecz via email or telephone (information available in SAM).

An amendment will be issued to extend the deadline for questions to 09 January 2025 and the proposal due date to 23 January 2025.

Do the wood piling timbers have to be removed completely, or cut off 3’ from existing exposure?

Please cut the timber piles off at 10' below ground surface and remove. The remaining 20' can stay in the ground.

Will MAFB assist in terminating HTHW feed to the building or do we just blind flange the lines to the building?

The contractor will be responsible for terminating the HTHW feed to the building. Contractor shall cut piping between main distribution piping taps and the service pipe isolation valves, and cap. All HTHW Service piping/everything from the isolation valves to the building will be demolished/removed.

All work shall be done by welding. Leave as much straight pipe between the distribution pipe tap and isolation valves as possible, for allowance to tie back into the taps if ever required

Can any of the onsite concrete or CMU demo be used to fill the basement?

No, all the concrete and other demolished building materials must be removed from the site and disposed of off base.

6 Are questions 3-5 part of the design build package? Yes 1

7 Is the Tunnel out of the basement still there? Do we have to remove it? 1

Is this a design only project or is this a design-build project? (Will the demolition and improvements take place under this contract)?

This is a design-build project. Under this contract, the contractor(s) will be required to provide a 100% design and perform demolition/site improvements.

FA4626-25-R-0001

DSN/CSN Demo Dorm 631