20R0003 Atch 18 Q and A 200609.pdf

PDF 466 KB Posted

Attached to
Whiteman AFB Multiple Award Task Order Contract (MATOC) - FA462520R0003 Federal contract opportunity
Solicitation number
FA462520R0003
Issued by
Department of the Air Force Global Strike Command

About this file

This document contains questions and answers regarding a solicitation for a Multiple Award Task Order Contract at Whiteman Air Force Base. The contract is a 100% small business set-aside for commercial and institutional building construction services with a NAICS code of 236220 and size standard of $39.5 million. The services required include multi-disciplined construction and design projects involving repair, renovation, alteration, new construction, and singular design efforts of real property facilities on base. The contract will be awarded to three small businesses as an indefinite delivery, indefinite quantity contract valued between $100-250 million over a nine year period including a five year base and two two-year options. Awardees will compete for firm fixed price task orders. Relevant experience includes similar design, construction, repair, renovation, and maintenance projects between $1-7.5 million in magnitude and complexity.

View the file

Other files for this federal contract opportunity

Other files attached to Whiteman AFB Multiple Award Task Order Contract (MATOC) - FA462520R0003, newest first.
File Type Posted
20R0003 Atch L-4 Construction Cost Breakdown - Amended.xls XLS spreadsheet
20R0003 Atch 20 Q and A 200622.pdf PDF
Solicitation Amendment FA462520R00030012 SF 30.pdf PDF
20R0003 Atch 19 ISV Attendees.pdf PDF
Solicitation Amendment FA462520R00030011 SF 30.pdf PDF
Solicitation Amendment FA462520R00030010 SF 30.pdf PDF
20R0003 Atch 15 Q and A 200520.pdf PDF
20R0003 Atch 17 WAFB IFS Appendix.pdf PDF
20R0003 Atch 1 SOW 20May20.docx.pdf PDF
Solicitation Amendment FA462520R00030009 SF 30.pdf PDF
Attachment 14 509 SF Fast Pass Request.pdf PDF
Solicitation Amendment FA462520R00030008 SF 30.pdf PDF
Attachment 13 509 MDG Public Health Travel Risk Assessment Form.pdf PDF
Solicitation Amendment FA462520R00030007 SF 30.pdf PDF
20R0003 Atch 12 Q and A 200512.pdf PDF
20R0003 Atch 1 SOW 11May20.pdf PDF
20R0003 Atch L-2 Transmittal Letter.pdf PDF
20R0003 Atch L-1 Past Performance Questionaire.pdf PDF
20R0003 Atch 10 Q and A 200507.pdf PDF
Q and A 200507 Atch 3 - Storage Room Floor.jpeg JPEG file
Solicitation Amendment FA462520R00030006 SF 30.pdf PDF
Q and A 200507 Atch 1 - Bldg 3008 AHU Schedule.PNG PNG image
Q and A 200507 Atch 2 - Restroom Floor.jpeg JPEG file
20R0003 Atch L-3 Consent Letter.pdf PDF
20R0003 Atch L-4 Construction Cost Breakdown.xls XLS spreadsheet
Solicitation Amendment FA462520R00030005 SF 30.pdf PDF
20R0003 Atch 8 Q and A 200506.pdf PDF
20R0003 Atch L-4 Construction Cost Breakdown.xls XLS spreadsheet
Solicitation Amendment FA462520R00030004 SF 30.pdf PDF
20R0003 Atch 8 Q and A 200430.pdf PDF
20R0003 Atch 5 Q and A 200420 REVISED.pdf PDF
Solicitation Amendment FA462520R00030003 SF 30.pdf PDF
20R0003 Q and A 200420.pdf PDF
Solicitation Amendment FA462520R00030002 SF 30.pdf PDF
Solicitation Amendment FA462520R00030001 SF 30.pdf PDF
20R0003 Atch L-1 Past Performance Questionaire.pdf PDF
20R0003 Atch L-3 Consent Letter.pdf PDF
20R0003 Atch 3 Whiteman AFB Climatology Data.pdf PDF
Solicitation - FA462520R0003.pdf PDF
20R0003 Atch L-4 Construction Cost Breakdown.xls XLS spreadsheet
20R0003 Atch 2 Rep Project SOO 02Jan20.pdf PDF
20R0003 Atch 1 SOW 02April20.pdf PDF
20R0003 Atch L-2 Transmittal Letter.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Whiteman AFB MATOC Solicitation Q&A

FA462520R0003

6/09/2020

Q1: For FACTOR 2 – PAST EXPERIENCE, since design fees are typically below $1 million, can the Offeror include a project example from our design firm with whom we have a Teaming Arrangement, for a task order with a construction cost between the $1 million - $7.5 million range?

A1: Yes.

The following verbiage has been added to Section L, Paragraph 4.3.f. "If the project is a Design Only effort, the construction cost estimate must also be included."

Section M, Paragraph 2.2.a.i The first sentence has been changed to read: "Design, Design-Build, or Design Bid Build multi-disciplined project with a construction cost between $1M - $7.5 M unless the contract is an IDIQ.

Section M Paragraph 2.2.b The word "Projects" has been replaced with "Experience". Sentences ii and vi have also been updated.

Section M Paragraph 2.3.b The second sentence has been changed to read: "Relevant projects are defined as; projects which are similar in scope (design, repair, alteration, renovation, maintenance, and/or minor construction projects on various real property facilities across multiple disciplines);

construction cost magnitude (between $1 million and $7.5 million); and complexity (projects requiring multiple disciplines, including design work) as the effort described in this solicitation."

Q2: Section 3.0 FACTOR 1 – KEY PERSONNEL 3.2.b. states “Offeror shall provide identification of each proposed key person by position, title, and name.” Should the title be in accordance to the in individual’s job title at the company they work or the title of their role on the proposed project?

A2: Their role on the proposed project.

Q3: In FACTOR 3 – PAST PERFORMANCE, 5.4.a. Companies with multiple offices will have multiple CAGE and DUNS in accordance with each location. This is due to some government agencies requiring an office location in a certain area in order to submit on projects. Please confirm that in submitting our company experience, the contracts were under the local office CAGE and DUNS, will not be an issue since the CAGE and DUNS will be different than that listed on the Proposal Data Sheet.

A3: The evaluation will be conducted in accordance with FAR 15.305(a)(2)(iii). If Past Performance or Past Experience is submitted from a predecessor company, the Offeror must demonstrate how the predecessor company will affect the performance of the Offeror.

Q4: In Reference to questions embedded in FAR guidance in Sections I-K, are we expected to provide answers along with the bid or will this information be provided once contract is awarded? For example: Page 28 of 66 Item 3(d) Domestic or Foreign Material, Page 33 of 66 Item 2(e) Related to Drawings. If so, can you provide further clarification?

A4: Offerors must complete the required Reps and Certs and submit them with their proposal. The clauses referenced in this question: "252.217-7027" and "52.225-11" are not required to be completed and submitted with the proposal. Please advise if further clarification is required.