FA462517R0007_Reno_Bldg_527_QA_dated_14_Jul_2017.pdf
PDF 110 KB Posted
- Attached to
- Renovate Bldg 527 A&FRC Federal contract opportunity
- Solicitation number
- FA4625-17-R-0007
About this file
FA462517R0007_Reno_Bldg_527_QA_dated_14_Jul_2017.pdf
View the file
Other files for this federal contract opportunity
Show all 50
Renovate Bldg 527 A&FRC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
14 July 2017
Bldg 527 Renovation Q&A
1. QUESTION: On the Presol Notice in FBO this solicitation is noted as a Total Small Business set-aside, but I could not see where that is noted on the RFP. Please clarify that this is a Total
Small Business set.
ANSWER: Yes, this is total small business set-aside.
2. QUESTION: Pg. 58. B. Bid – Insert proposed pricing on the SF 1442 CLIN 0001. - Is pricing to be noted on the SF 1442 and Attachment 8?
ANSWER: Yes, annotate total pricing on the SF 1442 CLIN 0001 and complete Attachment 8’s
Contractor Major Category Price Breakdown for evaluation purposes only. Attachment 8’s price breakdown will not include all costs associated with CLIN 0001, but will only be for the categories identified in Attachment 8. This price breakdown will not include overhead and profit.
3. QUESTION: Please clarify that binders are not required - just four (4) CD's total (see chart below)
Pg. 56. PART I - TECHNICAL CAPABILITY …… Submit Original with one (1) and (1) sanitized copy with Offerors CAGE code only.
Pg. 59. B. INFORMATION REGARDING SUBMISSION OF PROPOSALS: Electronic submission of proposals is required
Is the following correct?
CD
Original
CD
Copy
CD
Redacted
Copy
Part I - Technical Capability 1 1 1
Part II - Price Proposal 1 0 0
ANSWER: Correct, binders are not required and your chart above correctly reflects the CDs required with proposal submission.
4. QUESTION: When is the cut-off date & time for questions?
ANSWER: A date and time will be determined following the site visit of 15 Jun 2017, and posted along with site visit notes in an amendment.
5. QUESTION: If this is an all-electronic submission, can a scan of the Bid Bond be placed as the last item in the Price Proposal? And the original of the bid bond be submitted with the
CD's?
ANSWER: Yes, a scanned copy of the Bid Bond may be placed on the Price Proposal CD and the original document be submitted with the proposal submission.
6. QUESTION: Regarding Division 1 requirements: the specifications attachment refers Div. 1 to
WAFB Contracting, and there are no Div. 1 specifications listed in the RFP or other attachments, only the technical requirements in the RFP Section L. Please confirm those are the only requirements.
ANSWER: Division 1 requirements are 509 CONS’ contract specific requirements. The
Government may add sections at some point to Division 1, but currently everything in that division is Contracting related, such as the RFP Section L and Section M.
7. QUESTION: Can we get a set of as built of the existing mechanical systems to be removed?
ANSWER: Yes, as-built drawings of the existing mechanical system are attached to Amendment
0003.
8. QUESTION: Will there need to be isolation valves installed at the phase lines on the HVAC lines?
ANSWER: Isolation valves will probably need to be installed for the phasing, but not necessarily at the phase lines. That will depend upon the phasing plan by the contractor. If isolation valves are installed, they will need to be accessible at the conclusion on the project.
9. QUESTION: Will there need to be isolation valves installed at the phase lines on the Plumbing lines?
ANSWER: Isolation valves will probably need to be installed for the phasing, but not necessarily at the phase lines. That will depend upon the phasing plan by the contractor. If isolation valves are installed, they will need to be accessible at the conclusion on the project.
10. QUESTION: If the contractor installs triple duty valves in the HAVC piping will there need to be isolation valves installed above them?
ANSWER: Isolation valve shall be installed; however, triple duty valves are not authorized to be used in accordance with UFC 3-410-01.
11. QUESTION: Will the chiller require a separate 120v circuit for freeze protection?
ANSWER: Yes.
12. QUESTION: Who is to provide the glycol feed system div.22 or div 23?
ANSWER: The glycol feed system is specified in division 23; however, it is up to the contractor to determine which subcontractor will provide the glycol system.
13. QUESTION: Will the glycol feed system need to be a duel unit to feed the chilled and hot water systems?
ANSWER: Yes
14. QUESTION: How far back do we need to remove the ground source piping?
ANSWER: TO BE ANSWERED
Nearest point that will be accessible for future access.
15. QUESTION: On Sheet A-001 Note 3 states "On walls designated as P1/T2, install wall tile to
4'6" AFF and paint above" However the elevations on sheet A-301 Show the tile full height.
Please advise.
ANSWER: The elevations shown on sheet A-301 are designated as T2 on Sheet A-001.
16. QUESTION: On Sheet E-201 Plan note #1 says contractor shall provide telecommunications provisions and equipment as prescribed in the 509th communications squadron telecommunications installation criteria for facility design & Renovation Tab K. My question is, is this document available?
ANSWER: Yes, the Telecommunications Installation Criteria for Facility Design & Renovation is attached to Amendment 0003.
17. QUESTION: Spec Section 260573 in calling for a Fault Current Coordination Study. Since we have a complete design system do we need the coordination study?
ANSWER: Yes
18. QUESTION: Spec Section 264113 is calling for a Lightning Protection System, is this required?
ANSWER: No
19. QUESTION: Spec. Section 260519 has a section for using type MC (Metal Clad) cable, Is Type
MC cable allowed?
ANSWER: Only in areas where it is not feasible to put conduit. For example, areas where drywall isn’t furred out enough for to fit behind it.
20. QUESTION: Spec. Section 260519.3.D.2 shows minimum size Wire to be #12, however
260519.5.A.2 shows minimum wire size to be #10. Please Clarify.
ANSWER: Use the proper wire size to achieve NEC drop limits. For this purpose of this specific question, 12AWG is the minimum.
21. QUESTION: Spec Section 260519.5.A.1 shows minimum size conduit to be ¾” however
260533.3.1A2 shows minimum size conduit to be ½”. Please Clarify.
ANSWER: Minimum conduit size is ½ inch, but should be sized appropriately to meet NEC throughout the facility.
22. QUESTION: Will Simplex Grinnell be acceptable manufacture for Fire alarm System and
Mass Notification?
ANSWER: Yes, Simplex Grinnell is one of the acceptable manufacturers.
23. QUESTION: Reference drawing E-201 note 5. Notes states to extend copper cable to new location. It appears the existing copper cable lengths are not adequate to extend into room 147.
Will splicing onto existing copper cable and leaving splice case on wall in room 145 be acceptable? If not please forward information on cable pair count, routing and distance from Bldg. 527 to base system interface point.
24. QUESTION: Is the intent of the government for the contractor to temporarily relocate the incoming telecommunication service and temporarily connect all existing telecommunication outlets in phase 2 and phase 3 to facilitate work in phase 1? Incoming communication service (fiber & copper) will be off line and relocated in phase 1. Has the government anticipated the down time during this process?
25. QUESTION: Is the intent of the government for the contractor to provide temporary power to serve all existing circuits located in phase 2 and phase 3 areas to facilitate work in phase 1?
Existing service feed and 1200A disconnect will be removed and offline during phase 1. Has the government anticipated the down time during this process?
ANSWER: Yes, interruptions to power should be minimal with temporary power for the rest of the facility throughout phase 1. Down times should be minimized, but short outages typical of transfer to temp power are anticipated (weekends preferred).
26. QUESTION: Is the intent of the government for the contractor to provide temporary Fire
Alarm system to serve all existing devices located in phase 2 and phase 3 areas to facilitate work in phase 1? Has the government anticipated the down time during this process?
ANSWER: The existing fire alarm system shall remain in service until the new system is installed.
Any downtime shall be minimal and must be scheduled as an outage.
27. QUESTION: Is the intent of the government to commission and test the new Fire Alarm system multiple times? Current phasing schedule will require new FA system to be online in phase 1 area prior to occupants relocating into the area. With the current phasing schedule there will be 3 separate commission/test required for the Fire Alarm system, phase 1, phase 2 and final entire facility. During the final test, all Fire Alarm devices and all requirements for the entire facility system will need to be tested. Has the government anticipated the down time for this testing?
ANSWER: Yes, the contractor will have to commission and test the new Fire Alarm system multiple times as the phases are being constructed if the existing system is not maintained.
28. QUESTION: Will the communication and power outlets located in the new modular walls be installed by the modular wall supplier with a single point of connection at each homerun location? Or, will these devices and outlets be installed on-site by the electrical contractor in chase and openings provided in modular walls?
The modular wall supplier is to provide walls that have the power and comms prewired in the system.
29. QUESTION: Under door hardware cylinders/lock cores are noted to be specified in other sections. What section can we find this information in? If not available in specs please confirm if we will need to accommodate a large or small format core.
ANSWER: Lock core shall be small format interchangeable core compatible with Best locking system.
30. QUESTION: Under door hardware 2.1 A notes to field verify existing hardware in areas to receive new doors and hardware. Match existing adjacent hardware to remain. The hardware schedule in Part 3 shall be considered the minimum requirements pertaining to quality and function. Should we be quoting Part 3 or field verifying existing hardware?
Delete 2.1 A. All new hardware per Spec. Part 3.
31. QUESTION: Lighting ceiling plan has designation LV$ but the symbols legend does not clarify what “LV” designates. Reference rooms 128 and 171. Please clarify.
ANSWER: $LV is a wall switch as designated on sheet E-402 under Lighting Control Device Schedule.
32. QUESTION: Finishes not provided on schedule for doors in demountable partitions.
Demountable doors to be equal to manufacturers Enclose swinging wood doors.
33. QUESTION: No elevations called out for demountable walls, finishes and wall types unspecified. Please provide elevations and finish schedule.
Tenant wanted solid walls with no glass and solid wood doors. It was discussed that this was not wholly compatible with WAFB’s design intent to move towards modular walls and the open concept.
We were to spec around Haworth Enclose. Because of extremely low budget for this project it was discussed to pull modular walls out and provide as equipment.
PCWM can discuss with WAFB to establish wall pattern(s) and door type if desired.
34. QUESTION: Please confirm East wall in room 157 is to be demountable.
ANSWER: Yes it is.
35. QUESTION: Please confirm ceiling height(s).
ANSWER: Ceiling heights are shown on sheet A-103.
36. QUESTION: Are there any elevations showing wall type/finish selection available for the moveable/modular walls?
Moveable.Modular Wall Requirements:
MOVEABLE SOLID WALLS: All moveable walls that do not border a corridor shall be a solid wall provided with 2 tile segements on each side. The tile segments shall be laminate faced tiles of different colors. The top of the bottom tile and bottom of the top tile shall be located at 2’-3” a.f.f.
Color selections for the tiles shall made from Grade B samples. Solid wall panels shall provide a STC rating of 45.
MOVEABLE GLASS WALLS: All walls fronting onto a corridor shall be full height glass walls with tempered glass.
DOORS IN MOVEABLE WALLS: All doors shall be a metal frame swinging type with a glass inset. All glass to be tempered. Hardware to be as listed in the door schedule.
FILM FOR GLASS SURFACES: All glass shall be covered with a film that improves privacy without being total opaque. Film shall be as required to mimic etched glass with a transparency level and pattern to be determined by the owner.
SPECIAL PRIVACY REQUIREMENTS: Rooms 165 through 171 shall be comprised of solid walls with 2 laminate tile segments each side and all doors shall be solid wood.
37. QUESITON: Can you please clarify what items E & F are referring to under Section 102219 –
Moveable Walls, 1.3 Design Requirements?
Trims are to be integral with wall and not surface mounted.
38. QUESTION: Regarding detailed phasing plan being requested, is this to be submitted with bid proposal?
ANSWER: Per Section L Instruction to Offerors and Section M Evaluation for Award, it is the responsibility of the offeror to identify all necessary project/work elements to include the required three-phased construction approach detailed in Drawing G-101. Upon award, the successful offeror shall provide a detailed phasing plan as a submittal for review and approval by the government.
39. QUESTION: Can bid submittal be postponed another week due to July 4th Holiday week? It is difficult to get pricing from suppliers during holiday weeks.
ANSWER: See Amendment 0003, bid proposal due date is now due 27 Jul 2017 at 1:00pm.
40. QUESTION: Are there required completion dates for each phase?
ANSWER: No, the overall Period of Performance is not to exceed 395 days for all work completion.
41. QUESTION: The Design Specifications for this project list several approved manufactures under 281111 - Building Fire Alarm System that are not approved for use on Whiteman AFB per the 2014 Edition of the Whiteman Design Guide and also does not list two manufactures that are approved by the Design Guide. Per the Design Guide the only fire panel manufactures acceptable on WAFB are Siemens, Simplex or Notifier. Are we to use the manufactures listed in the project specifications or are we to use those listed in the Whiteman AFB Design Guide?
It appears that if we are to use both resources, the only manufacturer that we could use would be Notifier as it is listed in both publications.
ANSWER: The manufacturers shall be in accordance with “Whiteman Fire Emergency
Services Design Guide” dated 4 May 2017, Amendment 0003 attachement. Section 281111, Building Fire Alarm system and Mass Notification System, Para 2.1 shall be changed as follows:
2.1 MANUFACTURERS
A. Subject to compliance with requirements, provide products manufactured by the following manufacturers as indicated on the Drawings:
1. Monaco
2. Fike
3. Notifier
4. Simplex
5. Firelite
6. Siemens
7. Approved Equal
a. Approved equals will not be considered unless formally submitted during the bidding process as an RFI.
42. QUESTION: What is the correct Fire Alarm Notification equipment utilization to be?
ANSWER: See the above answer to Question 41.
43. QUESTION: The plans indicate modification of the existing sprinkler system to accommodate the new room layouts and ceilings. The plans do not indicate modification or replacement of the existing fire protection riser, mains or feeders. A sprinkler head layout is not indicated on the reflected ceiling plans.
1. The detail cuts indicate 1” branches from the existing feeders
(existing horizontal runs off of the main).
2. The heads shall be spaced per NFPA 13 for a normal hazard office building.
3. The water supply (flow) from the street will be adequate.
4. The existing fire protection riser assembly will be adequate.
5. The existing fire protection mains and feeders will be adequate.
Is the above understanding correct?
ANSWER:
Drawings and Specs provide schematic overall design (210010 1.5).
Contractor shall provide signed and sealed “working Plans” and hydraulic calcucations for complete design (210010 1.6 C.)
44. QUESTION: How many cables will be in each faceplate? 2, 3 or 4?
ANSWER: Four (4)
45. QUESTION: Does the Government intend on issuing any Division 1 specifications prior to the bid? Division 1 specifications are critical to the preparation of a project schedule. Normally, Division 1 provides information regarding preconstruction activities and meetings, the construction document / materials submission process and government review/approval durations, and project close out and acceptance procedures required by the CO for final acceptance. All of these activities take time and are critical to establish the necessary task durations in order to achieve the contract completion date prescribed by the contract proposal.
ANSWER:
46. QUESTION: Please confirm that the Government will retain the services of the project
Commissioning Agent, (CxA) as stated in specification section 230800. Will the CxA only commission the HVAC systems or will the other mechanical, plumbing and electrical systems also be included as a building wide commissioning prior to government acceptance of the project? What durations of time will be required by the CxA to perform their work?
ANSWER:
47. QUESTION: Does the Government have the hydrant flow tests conducted within the last 12 months as required by specification section 210010? If not, should the contractor assume that adequate flow and pressure exist at the building service entry point in the preparation of our cost proposal?
ANSWER: Contractor is required to provide hydrant flow test as part of fire suppression design.
48. QUESTION: What permits and fees are applicable to this project?
ANSWER: There are no additional fees required for any permits. The only permits required are local permit for “Excavation.”
49. QUESTION: We have found 2 ½” Type K waterline and fittings to be difficult if not impossible to obtain what alternatives will the Government accept?
ANSWER:
Recommend staying with 2 ½ Type K. May be modified during construction if not available.
50. QUESTION: What is the deadline to submit additional RFI’s?
ANSWER: Deadline for additional questions will be provided in Amendment 4.
51. QUESTION: Due to the small scale of this project, will an AISC certified fabricator and erector be required per the specs (051200-1.6)?
ANSWER:
Most reasonable size shops are AISC and this does help establish a qualified contractor.
52. Please issue any available as-built drawings to better aid us in our proposal, especially related to
MEP items.
ANSWER:
53. After reviewing the Phasing plan, it appears swapping Phase 1 and Phase 2 will provide a better work flow, especially for the Mechanical items. Will the swapping of these phases be acceptable?
ANSWER:
Contractor to set up detailed phasing plan.
Original concept was to have Smitty move once and that is how Phase 1 was decided.
Temporary heating and cooling was discussed. Option for contractor to provide switchover between phases during tenant move also discuss.
Swapping Phase 1 and 2 per the question above would be less problematic since Phase 1 areas
(Current Shop and Storage) are conditioned with Roof Top Units. Smitty would move to the existing Shop and Storage prior to start of construction. After the Phase 2 areas (built as the 1st
Phase) are complete, Smitty would move into the Classroom areas. Smitty would need to move once more after completion of Phase 1 (Built as Phase 2).
LACK OF EXTERIOR REPAIR:
The original budget during design for this projects was about 2.1 million and we were minimize design scope creep that would increase the budget. Replacement of the aluminum entrance, new roof and an exterior facelift were not included in our scope of work. Exterior work was limited to only what was necessary to accommodate the interior remodeled spaces.
The primary public faces of 527 (North and West) are basically brick and prefinished metal storefront and fascia. The East and south faces at the service drive is where most of the older components needing repainting are located. Sheet A-201 General Finish Notes and the notes on the elevations call out what is to be painted and its need for preparation.
File details come from the government source that posted it. Updated .