FA462517R0007_Reno_Bldg_527_QA_dated_27_Jun_2017.3.pdf

PDF 63 KB Posted

Attached to
Renovate Bldg 527 A&FRC Federal contract opportunity
Solicitation number
FA4625-17-R-0007
Issued by
Department of the Air Force Global Strike Command

About this file

FA462517R0007_Reno Bldg 527_QA dated 27 Jun 2017.3

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Bldg 527 A&FRC, newest first.
File Type Posted
Atch_1,_17R0007_Reno_Bldg_527_QA_dated_1Mar18.docx DOCX document
Atch_2,_17R0007_WAFB_Reno_Bldg_527_Atch_8_Ktr_Major_Cat_Price_Brkdwn_Rev_28Feb18.pdf PDF
Atch_4,_14_Dwgs,_Renovate_BLDG_527-Rev_1-1Mar2018.pdf PDF
17R0007_Reno_Bldg_527_SF30_Amend__12,_Dwgs_&_Q&A_dated_1Mar18.pdf PDF
Atch_3,_087100_SF_-_REVISED_DOOR_HARDWARE_SCHEDULE_(003).pdf PDF
17R0007_Reno_Bldg_527_SF30_Amend__11,_Extension,_Q&A_dated_23_Feb.pdf PDF
Atch_3_Specification_Section_26_12_19.10,_Three-Phase_Pad-Mounted_Transformers.pdf PDF
Atch_4_Specification_Section_33_71_02,_Underground_Electrical_Distribution.pdf PDF
Atch_2_Revised_Electrical_One_Line_Diagram.pdf PDF
Atch_1_FA462517R0007_Reno_Bldg_527_QA_dated_23Feb18.pdf PDF
17R0007_Reno_Bldg_527_Amend_10,_SF30_QA_dated_16Feb18.pdf PDF
FA462517R0007_Reno_Bldg_527_QA_dated_18Feb16.pdf PDF
17R0007_Reno_Bldg_527_3rd_Site_Visit_Sign-In_Sheet,_Atch_2.pdf PDF
17R0007_Reno_Bldg_527_Rev._Floor_Plans,_Welcome_Ctr_131st_Area,_Atch_1.pdf PDF
17R0007_Reno_Bldg_527_SF30_Amend__9,_3rd_Site_Visit_Rev_Floor_Plans.pdf PDF
FA462517R0007_Reno_Bldg_527_Amend_8_SF30.pdf PDF
FA462517R0007_Reno_Bldg_527_Brick_Staining_Spec,_Atch_3.docx DOCX document
FA462517R0007_Reno_Bldg_527_QA_dtd_29_Jan_18,_Atch_2.docx DOCX document
FA462517R0007_Reno_Bldg_527_As-builts,_Atch_1.zip ZIP file
FA462517R0007_Reno_Bldg_527_Amend__6,_Extend_Offer_Date.pdf PDF
FA462517R0007_Reno_Bldg_527_QA_dated_14_Jul_2017.pdf PDF
FA462517R0007_Reno_Bldg_527_Amend__5_SF30.pdf PDF
FA462517R0007_Reno_Bldg_527_Second_Site_Visit_Sign-in_Sheet.pdf PDF
Amend__3,_HVAC_As-builts_SHEET_003_M1_MECH_DEMO_PLAN.pdf PDF
Amend__3,_WAFB_Plumbing_HVAC_Design_Requirements.pdf PDF
Amend__3,_HVAC_As-builts_SHEET_001_CV1_COVER_SHEET.pdf PDF
Amend__3,_HVAC_As-Builts_SHEET_006_M4_MECH_SCHEDULES_DIAGRAMS.pdf PDF
Amend__3,_WAFB_Fire_Emergency_Services_Design_Guide.pdf PDF
Amend__3,_HVAC_As-builts_SHEET_002_ME1_MEP_SYMBOLS_LEGENDS.pdf PDF
Amend__3,_HVAC_As-Builts_SHEET_004_M2_MECH_IMPROVE_PLAN.pdf PDF
FA462517R0007_Reno_Bldg_527_Amend__03,_2nd_Round_Q&A.pdf PDF
Amend__3,_HVAC_As-Builts_SHEET_008_E2_ELECTRICAL_IMPROVE_PLAN.pdf PDF
Amend__3,_HVAC_As-Builts_SHEET_005_M3_MECH_DETAILS.pdf PDF
Amend__3,_Telecomm_Ubstall_Criteria_for_Facility_Design_Renovation.pdf PDF
Amend__3,_HVAC_As-Builts_SHEET_007_E1_ELECTRICAL_DEMO_PLAN.pdf PDF
Amend__3,_HVAC_As-Builts_SHEET_009_LF1.2_GRD_LOOP_WELL_FIELD_LAY_PLAN.pdf PDF
FA462517R0007_Reno_Bldg_527_Amend__02,_Sign-in_Sheet.pdf PDF
FA462517R0007_Reno_Bldg_527_Site_Visit_Sign-in_Sheet.pdf PDF
FA462517R0007_Reno_Bldg_527_Amend__1,_Q&A.pdf PDF
FA462517R0007_Reno_Bldg_527_Q&A,_dated_12_Jun_2017.docx DOCX document
17-R-0007_WAFB_Reno_Bldg_527_Atch_7_100_prcnt_Design_Drwgs_Full_Set_3May16.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_SF_1442_RFP_2Jun17.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_Atch_9_Staging_Area_26Apr17.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_Atch_5_AF_3065,_Progress_Report_Blank_27Apr17.xlsx XLSX spreadsheet
17-R-0007_WAFB_Reno_Bldg_527_Atch_3_Local_Info_Atch_1,_General_Rqmts_27Apr17.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_Atch_1_WD_MO170012_28Apr17.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_Atch_8_Ktr_Major_Cat_Price_Brkdwn_27Apr17.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_Atch_6_Design_Specifications_3May16.pdf PDF
17-R-0007_WAFB_Reno_Bldg_527_Atch_4_AF_3064,_Progress_Schedule_Blank_27Apr17.xlsx XLSX spreadsheet
17-R-0007_WAFB_Reno_Bldg_527_Atch_2_Local_Info_27Apr17.pdf PDF
Show all 50

Renovate Bldg 527 A&FRC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

27 Jul 17

Bldg 527 Renovation Q&A

1. QUESTION: On the Presol Notice in FBO this solicitation is noted as a Total Small Business set-aside, but I could not see where that is noted on the RFP. Please clarify that this is a Total Small Business set.

ANSWER: Yes, this is total small business set-aside.

2. QUESTION: Pg. 58. B. Bid – Insert proposed pricing on the SF 1442 CLIN 0001. - Is pricing to be noted on the SF 1442 and Attachment 8?

ANSWER: Yes, annotate total pricing on the SF 1442 CLIN 0001 and complete Attachment 8’s Contractor Major Category Price Breakdown for evaluation purposes only. Attachment 8’s price breakdown will not include all costs associated with CLIN 0001, but will only be for the categories identified in Attachment 8. This price breakdown will not include overhead and profit.

3. QUESTION: Please clarify that binders are not required - just four (4) CD's total (see chart below)

Pg. 56. PART I - TECHNICAL CAPABILITY …… Submit Original with one (1) and (1) sanitized copy with Offerors CAGE code only.

Pg. 59. B. INFORMATION REGARDING SUBMISSION OF PROPOSALS: Electronic submission of proposals is required

Is the following correct?

CD

Original

CD

Copy

CD

Redacted

Copy

Part I - Technical Capability 1 1 1

Part II - Price Proposal 1 0 0

ANSWER: Correct, binders are not required and your chart above correctly reflects the CDs required with proposal submission.

4. QUESTION: When is the cut-off date & time for questions?

ANSWER: A date and time will be determined following the site visit of 15 Jun 2017, and posted along with site visit notes in an amendment.

5. QUESTION: If this is an all-electronic submission, can a scan of the Bid Bond be placed as the last item in the Price Proposal? And the original of the bid bond be submitted with the CD's?

ANSWER: Yes, a scanned copy of the Bid Bond may be placed on the Price Proposal CD and the original document be submitted with the proposal submission.

6. QUESTION: Regarding Division 1 requirements: the specifications attachment refers Div. 1 to

WAFB Contracting, and there are no Div. 1 specifications listed in the RFP or other attachments, only the technical requirements in the RFP Section L. Please confirm those are the only requirements.

ANSWER: Division 1 requirements are 509 CONS’ contract specific requirements. The Government may add sections at some point to Division 1, but currently everything in that division is Contracting related, such as the RFP Section L and Section M.

7. QUESTION: Can we get a set of as built of the existing mechanical systems to be removed?

ANSWER: Yes, as-built drawings of the existing mechanical system are attached to Amendment 0003.

8. QUESTION: Will there need to be isolation valves installed at the phase lines on the HVAC lines?

ANSWER: Isolation valves will probably need to be installed for the phasing, but not necessarily at the phase lines. That will depend upon the phasing plan by the contractor. If isolation valves are installed, they will need to be accessible at the conclusion on the project.

9. QUESTION: Will there need to be isolation valves installed at the phase lines on the Plumbing lines?

ANSWER: Isolation valves will probably need to be installed for the phasing, but not necessarily at the phase lines. That will depend upon the phasing plan by the contractor. If isolation valves are installed, they will need to be accessible at the conclusion on the project.

10. QUESTION: If the contractor installs triple duty valves in the HAVC piping will there need to be isolation valves installed above them?

ANSWER: Isolation valve shall be installed; however, triple duty valves are not authorized to be used in accordance with UFC 3-410-01.

11. QUESTION: Will the chiller require a separate 120v circuit for freeze protection?

ANSWER: Yes.

12. QUESTION: Who is to provide the glycol feed system div.22 or div 23?

ANSWER: The glycol feed system is specified in division 23; however, it is up to the contractor to determine which subcontractor will provide the glycol system.

13. QUESTION: Will the glycol feed system need to be a duel unit to feed the chilled and hot water systems?

ANSWER: Yes

14. QUESTION: How far back do we need to remove the ground source piping?

ANSWER: TO BE ANSWERED

15. QUESTION: On Sheet A-001 Note 3 states "On walls designated as P1/T2, install wall tile to

4'6" AFF and paint above" However the elevations on sheet A-301 Show the tile full height.

Please advise.

ANSWER: The elevations shown on sheet A-301 are designated as T2 on Sheet A-001.

16. QUESTION: On Sheet E-201 Plan note #1 says contractor shall provide telecommunications provisions and equipment as prescribed in the 509th communications squadron telecommunications installation criteria for facility design & Renovation Tab K. My question is, is this document available?

ANSWER: Yes, the Telecommunications Installation Criteria for Facility Design & Renovation is attached to Amendment 0003.

17. QUESTION: Spec Section 260573 in calling for a Fault Current Coordination Study. Since we have a complete design system do we need the coordination study?

ANSWER: Yes

18. QUESTION: Spec Section 264113 is calling for a Lightning Protection System, is this required?

ANSWER: No

19. QUESTION: Spec. Section 260519 has a section for using type MC (Metal Clad) cable, Is Type

MC cable allowed?

ANSWER: Only in areas where it is not feasible to put conduit. For example, areas where drywall isn’t furred out enough for to fit behind it.

20. QUESTION: Spec. Section 260519.3.D.2 shows minimum size Wire to be #12, however

260519.5.A.2 shows minimum wire size to be #10. Please Clarify.

ANSWER: Use the proper wire size to achieve NEC drop limits. For this purpose of this specific question, 12AWG is the minimum.

21. QUESTION: Spec Section 260519.5.A.1 shows minimum size conduit to be ¾” however

260533.3.1A2 shows minimum size conduit to be ½”. Please Clarify.

ANSWER: Minimum conduit size is ½ inch, but should be sized appropriately to meet NEC throughout the facility.

22. QUESTION: Will Simplex Grinnell be acceptable manufacture for Fire alarm System and

Mass Notification?

ANSWER: Yes, Simplex Grinnell is one of the acceptable manufacturers.

23. QUESTION: Reference drawing E-201 note 5. Notes states to extend copper cable to new location. It appears the existing copper cable lengths are not adequate to extend into room 147.

Will splicing onto existing copper cable and leaving splice case on wall in room 145 be acceptable? If not please forward information on cable pair count, routing and distance from Bldg. 527 to base system interface point.

24. QUESTION: Is the intent of the government for the contractor to temporarily relocate the incoming telecommunication service and temporarily connect all existing telecommunication outlets in phase 2 and phase 3 to facilitate work in phase 1? Incoming communication service (fiber & copper) will be off line and relocated in phase 1. Has the government anticipated the down time during this process?

25. QUESTION: Is the intent of the government for the contractor to provide temporary power to serve all existing circuits located in phase 2 and phase 3 areas to facilitate work in phase 1?

Existing service feed and 1200A disconnect will be removed and offline during phase 1. Has the government anticipated the down time during this process?

ANSWER: Yes, interruptions to power should be minimal with temporary power for the rest of the facility throughout phase 1. Down times should be minimized, but short outages typical of transfer to temp power are anticipated (weekends preferred).

26. QUESTION: Is the intent of the government for the contractor to provide temporary Fire

Alarm system to serve all existing devices located in phase 2 and phase 3 areas to facilitate work in phase 1? Has the government anticipated the down time during this process?

ANSWER: The existing fire alarm system shall remain in service until the new system is installed.

Any downtime shall be minimal and must be scheduled as an outage.

27. QUESTION: Is the intent of the government to commission and test the new Fire Alarm system multiple times? Current phasing schedule will require new FA system to be online in phase 1 area prior to occupants relocating into the area. With the current phasing schedule there will be 3 separate commission/test required for the Fire Alarm system, phase 1, phase 2 and final entire facility. During the final test, all Fire Alarm devices and all requirements for the entire facility system will need to be tested. Has the government anticipated the down time for this testing?

ANSWER: Yes, the contractor will have to commission and test the new Fire Alarm system multiple times as the phases are being constructed if the existing system is not maintained.

28. QUESTION: Will the communication and power outlets located in the new modular walls be installed by the modular wall supplier with a single point of connection at each homerun location? Or, will these devices and outlets be installed on-site by the electrical contractor in chase and openings provided in modular walls?

29. QUESTION: Under door hardware cylinders/lock cores are noted to be specified in other sections. What section can we find this information in? If not available in specs please confirm if we will need to accommodate a large or small format core.

ANSWER: Lock core shall be small format interchangeable core compatible with Best locking system.

30. QUESTION: Under door hardware 2.1 A notes to field verify existing hardware in areas to receive new doors and hardware. Match existing adjacent hardware to remain. The hardware schedule in Part 3 shall be considered the minimum requirements pertaining to quality and function. Should we be quoting Part 3 or field verifying existing hardware?

31. QUESTION: Lighting ceiling plan has designation LV$ but the symbols legend does not clarify what “LV” designates. Reference rooms 128 and 171. Please clarify.

ANSWER: $LV is a wall switch as designated on sheet E-402 under Lighting Control Device Schedule.

32. QUESTION: Finishes not provided on schedule for doors in demountable partitions.

33. QUESTION: No elevations called out for demountable walls, finishes and wall types unspecified. Please provide elevations and finish schedule.

ANSWER: TO BE ANSWERED

34. QUESTION: Please confirm East wall in room 157 is to be demountable.

ANSWER: Yes it is.

35. QUESTION: Please confirm ceiling height(s).

ANSWER: Ceiling heights are shown on sheet A-103.

36. QUESTION: Are there any elevations showing wall type/finish selection available for the moveable/modular walls?

37. QUESITON: Can you please clarify what items E & F are referring to under Section 102219 –

Moveable Walls, 1.3 Design Requirements?

ANSWER: TO BE ANSWERED

38. QUESTION: Regarding detailed phasing plan being requested, is this to be submitted with bid proposal?

ANSWER: Per Section L Instruction to Offerors and Section M Evaluation for Award, it is the responsibility of the offeror to identify all necessary project/work elements to include the required three-phased construction approach detailed in Drawing G-101. Upon award, the successful offeror shall provide a detailed phasing plan as a submittal for review and approval by the government.

39. QUESTION: Can bid submittal be postponed another week due to July 4th Holiday week? It is difficult to get pricing from suppliers during holiday weeks.

ANSWER: See Amendment 0003, bid proposal due date is now due 27 Jul 2017 at 1:00pm.

40. QUESTION: Are there required completion dates for each phase?

ANSWER: No, the overall Period of Performance is not to exceed 395 days for all work completion.

41. QUESTION: The Design Specifications for this project list several approved manufactures under 281111 - Building Fire Alarm System that are not approved for use on Whiteman AFB per the 2014 Edition of the Whiteman Design Guide and also does not list two manufactures that are approved by the Design Guide. Per the Design Guide the only fire panel manufactures acceptable on WAFB are Siemens, Simplex or Notifier. Are we to use the manufactures listed in the project specifications or are we to use those listed in the Whiteman AFB Design Guide?

It appears that if we are to use both resources, the only manufacturer that we could use would be Notifier as it is listed in both publications.

ANSWER: The manufacturers shall be in accordance with “Whiteman Fire Emergency Services Design Guide” dated 4 May 2017, Amendment 0003 attachement. Section 281111, Building Fire Alarm system and Mass Notification System, Para 2.1 shall be changed as follows:

2.1 MANUFACTURERS

A. Subject to compliance with requirements, provide products manufactured by the following manufacturers as indicated on the Drawings:

1. Monaco

2. Fike

3. Notifier

4. Simplex

5. Firelite

6. Siemens

7. Approved Equal

a. Approved equals will not be considered unless formally submitted during the bidding process as an RFI.