FA462517R0007_Reno_Bldg_527_QA_dated_18Feb16.pdf
PDF 82 KB Posted
- Attached to
- Renovate Bldg 527 A&FRC Federal contract opportunity
- Solicitation number
- FA4625-17-R-0007
About this file
FA462517R0007_Reno Bldg 527_QA dated 18Feb16
View the file
Other files for this federal contract opportunity
Show all 50
Renovate Bldg 527 A&FRC has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
16 February 2018
Bldg 527 Renovation Q&A
1. QUESTION: On the Presol Notice in FBO this solicitation is noted as a Total Small Business set-aside, but I could not see where that is noted on the RFP. Please clarify that this is a Total Small Business set.
ANSWER: Yes, this is total small business set-aside.
2. QUESTION: Pg. 58. B. Bid – Insert proposed pricing on the SF 1442 CLIN 0001. - Is pricing to be noted on the SF 1442 and Attachment 8?
ANSWER: Yes, annotate total pricing on the SF 1442 CLIN 0001 and complete Attachment 8’s Contractor Major Category Price Breakdown for evaluation purposes only.
Attachment 8’s price breakdown will not include all costs associated with CLIN 0001, but will only be for the categories identified in Attachment 8. This price breakdown will not include overhead and profit.
3. QUESTION: Please clarify that binders are not required - just four (4) CD's total (see chart below)
4. Pg. 56. PART I - TECHNICAL CAPABILITY …… Submit Original with one (1) and (1) sanitized copy with Offerors CAGE code only.
5. Pg. 59. B. INFORMATION REGARDING SUBMISSION OF PROPOSALS: Electronic submission of proposals is required.
6. Is the following correct?
CD
Original
CD
Copy
CD
Redacted Copy
Part I - Technical Capability 1 1 1
Part II - Price Proposal 1 0 0
ANSWER: Correct, binders are not required and your chart above correctly reflects the CDs required with proposal submission.
7. QUESTION: When is the cut-off date & time for questions?
ANSWER: A date and time will be determined following the site visit of 15 Jun 2017, and posted along with site visit notes in an amendment.
8. QUESTION: If this is an all-electronic submission, can a scan of the Bid Bond be placed as the last item in the Price Proposal? And the original of the bid bond be submitted with the CD's?
ANSWER: Yes, a scanned copy of the Bid Bond may be placed on the Price Proposal CD and the original document be submitted with the proposal submission.
9. QUESTION: Regarding Division 1 requirements: the specifications attachment refers Div.
1 to WAFB Contracting, and there are no Div. 1 specifications listed in the RFP or other attachments, only the technical requirements in the RFP Section L. Please confirm those are the only requirements.
ANSWER: Division 1 requirements are 509 CONS’ contract specific requirements. The Government may add sections at some point to Division 1, but currently everything in that division is Contracting related, such as the RFP Section L and Section M.
10. QUESTION: Can we get a set of as built of the existing mechanical systems to be removed?
ANSWER: Yes, as-built drawings of the existing mechanical system are attached to Amendment 0003.
11. QUESTION: Will there need to be isolation valves installed at the phase lines on the HVAC lines?
ANSWER: Isolation valves will probably need to be installed for the phasing, but not necessarily at the phase lines. That will depend upon the phasing plan by the contractor. If isolation valves are installed, they will need to be accessible at the conclusion on the project.
ANSWER (Revised): Phasing has been eliminated; therefore, this question is no longer valid.
12. QUESTION: Will there need to be isolation valves installed at the phase lines on the Plumbing lines?
ANSWER: Isolation valves will probably need to be installed for the phasing, but not necessarily at the phase lines. That will depend upon the phasing plan by the contractor. If isolation valves are installed, they will need to be accessible at the conclusion on the project.
ANSWER (Revised): Phasing has been eliminated; therefore, this question is no longer valid.
13. QUESTION: If the contractor installs triple duty valves in the HAVC piping will there need to be isolation valves installed above them?
ANSWER: Isolation valve shall be installed; however, triple duty valves are not authorized to be used in accordance with UFC 3-410-01.
14. QUESTION: Will the chiller require a separate 120v circuit for freeze protection?
ANSWER: Yes.
15. QUESTION: Who is to provide the glycol feed system div.22 or div 23?
ANSWER: The glycol feed system is specified in division 23; however, it is up to the contractor to determine which subcontractor will provide the glycol system.
16. QUESTION: Will the glycol feed system need to be a duel unit to feed the chilled and hot water systems?
ANSWER: Yes
17. QUESTION: How far back do we need to remove the ground source piping?
ANSWER: Nearest point that will be accessible for future access.
18. QUESTION: On Sheet A-001 Note 3 states "On walls designated as P1/T2, install wall tile to 4'6" AFF and paint above" However the elevations on sheet A-301 Show the tile full height. Please advise.
ANSWER: The elevations shown on sheet A-301 are designated as T2 on Sheet A-001.
19. QUESTION: On Sheet E-201 Plan note #1 says contractor shall provide telecommunications provisions and equipment as prescribed in the 509th communications squadron telecommunications installation criteria for facility design & Renovation Tab K.
My question is, is this document available?
ANSWER: Yes, the Telecommunications Installation Criteria for Facility Design & Renovation is attached to Amendment 0003.
20. QUESTION: Spec Section 260573 in calling for a Fault Current Coordination Study. Since we have a complete design system do we need the coordination study?
ANSWER: Yes
21. QUESTION: Spec Section 264113 is calling for a Lightning Protection System, is this required?
ANSWER: No
22. QUESTION: Spec. Section 260519 has a section for using type MC (Metal Clad) cable, Is Type MC cable allowed?
ANSWER: Only in areas where it is not feasible to put conduit. For example, areas where drywall isn’t furred out enough for to fit behind it.
23. QUESTION: Spec. Section 260519.3.D.2 shows minimum size Wire to be #12, however 260519.5.A.2 shows minimum wire size to be #10. Please Clarify.
ANSWER: Use the proper wire size to achieve NEC drop limits. For this purpose of this specific question, 12AWG is the minimum.
24. QUESTION: Spec Section 260519.5.A.1 shows minimum size conduit to be ¾” however 260533.3.1A2 shows minimum size conduit to be ½”. Please Clarify.
ANSWER: Minimum conduit size is ½ inch, but should be sized appropriately to meet NEC throughout the facility.
25. QUESTION: Will Simplex Grinnell be acceptable manufacture for Fire alarm System and Mass Notification?
ANSWER: Yes, Simplex Grinnell is one of the acceptable manufacturers.
26. QUESTION: Reference drawing E-201 note 5. Notes states to extend copper cable to new location. It appears the existing copper cable lengths are not adequate to extend into room
147. Will splicing onto existing copper cable and leaving splice case on wall in room 145 be acceptable? If not please forward information on cable pair count, routing and distance from Bldg. 527 to base system interface point.
ANSWER: Yes splicing onto existing copper cable and leaving a splice case on wall in room 145 is acceptable.
27. QUESTION: Is the intent of the government for the contractor to temporarily relocate the incoming telecommunication service and temporarily connect all existing telecommunication outlets in phase 2 and phase 3 to facilitate work in phase 1? Incoming communication service (fiber & copper) will be off line and relocated in phase 1. Has the government anticipated the down time during this process?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
28. QUESTION: Is the intent of the government for the contractor to provide temporary power to serve all existing circuits located in phase 2 and phase 3 areas to facilitate work in phase 1? Existing service feed and 1200A disconnect will be removed and offline during phase 1.
Has the government anticipated the down time during this process?
ANSWER: Yes, interruptions to power should be minimal with temporary power for the rest of the facility throughout phase 1. Down times should be minimized, but short outages typical of transfer to temp power are anticipated (weekends preferred).
ANSWER (Revised): Phasing has been eliminated; therefore, this question is no longer valid.
29. QUESTION: Is the intent of the government for the contractor to provide temporary Fire Alarm system to serve all existing devices located in phase 2 and phase 3 areas to facilitate work in phase 1? Has the government anticipated the down time during this process?
ANSWER: The existing fire alarm system shall remain in service until the new system is installed. Any downtime shall be minimal and must be scheduled as an outage.
ANSWER (Revised): Phasing has been eliminated; therefore, temporary fire alarm system is not required. The contractor will be required to perform a walk through the building at the end of each day to ensure there are no issues.
30. QUESTION: Is the intent of the government to commission and test the new Fire Alarm system multiple times? Current phasing schedule will require new FA system to be online in phase 1 area prior to occupants relocating into the area. With the current phasing schedule there will be 3 separate commission/test required for the Fire Alarm system, phase 1, phase 2 and final entire facility. During the final test, all Fire Alarm devices and all requirements for the entire facility system will need to be tested. Has the government anticipated the down time for this testing?
ANSWER: Yes, the contractor will have to commission and test the new Fire Alarm system multiple times as the phases are being constructed if the existing system is not maintained.
ANSWER (Revised): Phasing has been eliminated; therefore, the contractor will only be required to commission/test the fire alarm system upon completion.
31. QUESTION: Will the communication and power outlets located in the new modular walls be installed by the modular wall supplier with a single point of connection at each homerun location? Or, will these devices and outlets be installed on-site by the electrical contractor in chase and openings provided in modular walls?
ANSWER: The modular wall supplier is to provide walls that have the power and communication prewired in the system.
32. QUESTION: Under door hardware cylinders/lock cores are noted to be specified in other sections. What section can we find this information in? If not available in specs please confirm if we will need to accommodate a large or small format core.
ANSWER: Lock core shall be small format interchangeable core compatible with Best locking system.
33. QUESTION: Under door hardware 2.1 A notes to field verify existing hardware in areas to receive new doors and hardware. Match existing adjacent hardware to remain. The hardware schedule in Part 3 shall be considered the minimum requirements pertaining to quality and function. Should we be quoting Part 3 or field verifying existing hardware?
ANSWER: Delete 2.1 A. All new hardware per Spec. Part 3.
34. QUESTION: Lighting ceiling plan has designation LV$ but the symbols legend does not clarify what “LV” designates. Reference rooms 128 and 171. Please clarify.
ANSWER: $LV is a wall switch as designated on sheet E-402 under Lighting Control Device Schedule.
35. QUESTION: Finishes not provided on schedule for doors in demountable partitions. Please provide finishes.
ANSWER: Demountable doors to be equal to manufacturers Enclose by Haworth Inc.
swinging wood doors.
36. QUESTION: No elevations called out for demountable walls, finishes and wall types unspecified. Please provide elevations and finish schedule.
ANSWER: Moveable Modular Wall Requirements:
MOVEABLE SOLID WALLS: All moveable walls that do not border a corridor shall be a solid wall provided with 2 tile segments on each side. The tile segments shall be laminate faced tiles of different colors. The top of the bottom tile and bottom of the top tile shall be located at 2’-3” a.f.f. Color selections for the tiles shall made from Grade B samples. Solid wall panels shall provide a STC rating of 45.
MOVEABLE GLASS WALLS: All walls fronting onto a corridor shall be full height glass walls with tempered glass.
DOORS IN MOVEABLE WALLS: All doors shall be a metal frame swinging type with a glass inset. All glass to be tempered. Hardware to be as listed in the door schedule.
FILM FOR GLASS SURFACES: All glass shall be covered with a film that improves privacy without being total opaque. Film shall be as required to mimic etched glass with a transparency level and pattern to be determined by the owner.
SPECIAL PRIVACY REQUIREMENTS: Rooms 165 through 171 shall be comprised of solid walls with 2 laminate tile segments each side and all doors shall be solid wood.
37. QUESTION: Please confirm East wall in room 157 is to be demountable.
ANSWER: Yes it is.
38. QUESTION: Please confirm ceiling height(s).
ANSWER: Ceiling heights are shown on sheet A-103.
39. QUESTION: Are there any elevations showing wall type/finish selection available for the moveable/modular walls?
ANSWER: Moveable Modular Wall Requirements:
MOVEABLE SOLID WALLS: All moveable walls that do not border a corridor shall be a solid wall provided with 2 tile segments on each side. The tile segments shall be laminate faced tiles of different colors. The top of the bottom tile and bottom of the top tile shall be located at 2’-3” a.f.f. Color selections for the tiles shall made from Grade B samples. Solid wall panels shall provide a STC rating of 45.
MOVEABLE GLASS WALLS: All walls fronting onto a corridor shall be full height glass walls with tempered glass.
DOORS IN MOVEABLE WALLS: All doors shall be a metal frame swinging type with a glass inset. All glass to be tempered. Hardware to be as listed in the door schedule.
FILM FOR GLASS SURFACES: All glass shall be covered with a film that improves privacy without being total opaque. Film shall be as required to mimic etched glass with a transparency level and pattern to be determined by the owner.
SPECIAL PRIVACY REQUIREMENTS: Rooms 165 through 171 shall be comprised of solid walls with 2 laminate tile segments each side and all doors shall be solid wood.
40. QUESITON: Can you please clarify what items E & F are referring to under Section 102219 – Moveable Walls, 1.3 Design Requirements?
ANSWER: Trims are to be integral with wall and not surface mounted.
41. QUESTION: Regarding detailed phasing plan being requested, is this to be submitted with bid proposal?
ANSWER: Per Section L Instruction to Offerors and Section M Evaluation for Award, it is the responsibility of the offeror to identify all necessary project/work elements to include the required three-phased construction approach detailed in Drawing G-101. Upon award, the successful offeror shall provide a detailed phasing plan as a submittal for review and approval by the government.
ANSWER (Revised): Phasing has been eliminated; therefore, this question is no longer valid.
42. QUESTION: Can bid submittal be postponed another week due to July 4th Holiday week?
It is difficult to get pricing from suppliers during holiday weeks.
ANSWER: See Amendment 0003, bid proposal due date is now due 27 Jul 2017 at 1:00pm.
43. QUESTION: Are there required completion dates for each phase?
ANSWER: No, the overall Period of Performance is not to exceed 395 days for all work completion.
ANSWER (Revised): No, the overall Period of Performance is not to exceed 270 days for all work completion.
44. QUESTION: The Design Specifications for this project list several approved manufactures under 281111 - Building Fire Alarm System that are not approved for use on Whiteman AFB per the 2014 Edition of the Whiteman Design Guide and also does not list two manufactures that are approved by the Design Guide. Per the Design Guide the only fire panel manufactures acceptable on WAFB are Siemens, Simplex or Notifier. Are we to use the manufactures listed in the project specifications or are we to use those listed in the Whiteman AFB Design Guide? It appears that if we are to use both resources, the only manufacturer that we could use would be Notifier as it is listed in both publications.
ANSWER: The manufacturers shall be in accordance with “Whiteman Fire Emergency Services Design Guide” dated 4 May 2017, Amendment 0003 attachment. Section 281111, Building Fire Alarm system and Mass Notification System, Para 2.1 shall be changed as follows:
2.1 MANUFACTURERS
A. Subject to compliance with requirements, provide products manufactured by the following manufacturers as indicated on the Drawings:
1. Monaco
2. Fike
3. Notifier
4. Simplex
5. Firelite
6. Siemens
7. Approved Equal
a. Approved equals will not be considered unless formally submitted during the bidding process as an RFI.
45. QUESTION: What is the correct Fire Alarm Notification equipment utilization to be?
ANSWER: See the above answer to Question 41.
46. QUESTION: The plans indicate modification of the existing sprinkler system to accommodate the new room layouts and ceilings. The plans do not indicate modification or replacement of the existing fire protection riser, mains or feeders. A sprinkler head layout is not indicated on the reflected ceiling plans.
1. The detail cuts indicate 1” branches from the existing feeders
(existing horizontal runs off of the main).
2. The heads shall be spaced per NFPA 13 for a normal hazard office building.
3. The water supply (flow) from the street will be adequate.
4. The existing fire protection riser assembly will be adequate.
5. The existing fire protection mains and feeders will be adequate.
Is the above understanding correct?
ANSWER: Drawings and Specs provide schematic overall design (210010 1.5).
Contractor shall provide signed and sealed “working plans” and hydraulic calculations for complete design (210010 1.6 C.)
47. QUESTION: How many cables will be in each faceplate? 2, 3 or 4?
ANSWER: Four (4) cables in each faceplate.
48. QUESTION: Does the Government intend on issuing any Division 1 specifications prior to the bid? Division 1 specifications are critical to the preparation of a project schedule.
Normally, Division 1 provides information regarding preconstruction activities and meetings, the construction document / materials submission process and government review/approval durations, and project close out and acceptance procedures required by the CO for final acceptance. All of these activities take time and are critical to establish the necessary task durations in order to achieve the contract completion date prescribed by the contract proposal.
ANSWER: See the answer to Question #6.
49. QUESTION: Please confirm that the Government will retain the services of the project Commissioning Agent, (CxA) as stated in specification section 230800. Will the CxA only commission the HVAC systems or will the other mechanical, plumbing and electrical systems also be included as a building wide commissioning prior to government acceptance of the project? What durations of time will be required by the CxA to perform their work?
ANSWER: The Commissioning Agent (CxA) will not be retained by the Government. The CxA will be an independent subcontractor by the Prime Contractor that has no association with other subcontractors performing the work. The CxA is only required for the HVAC commissioning. The other system will have to be commissioned by the appropriate discipline prior to acceptance by the Government. Since the CxA is hired by the Prime Contractor, the duration will be as required by the Prime Contractor to maintain schedule.
Section 230800, paragraph 1.4 is revised as follows:
1.4 COMMISSIONING TEAM
A. Members Appointed by Contractor(s):
1. CxA: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The CxA shall be an independent subcontractor hired directly by the General Contractor to perform duties of detailed in this section.
2. Individuals, each having the authority to act on behalf of the entity he or she represents, explicitly organized to implement the commission process through coordinated action. The commissioning team shall consist of, but not be limited to, representatives of Contractor, including Project superintendent and subcontractors, installers, suppliers, and specialists deemed appropriate by the CxA.
B. Members Appointed by Owner:
1. Representatives of the facility user and operation and maintenance personnel.
2. Architect and engineering design professionals.
50. QUESTION: Does the Government have the hydrant flow tests conducted within the last 12 months as required by specification section 210010? If not, should the contractor assume that adequate flow and pressure exist at the building service entry point in the preparation of our cost proposal?
ANSWER: For the sake of the cost proposal the Contractor is to assume the flow and pressure is adequate but the Contractor is required to provide hydrant flow test as part of fire suppression design.
51. QUESTION: What permits and fees are applicable to this project?
ANSWER: There are no additional fees required for any permits. The only permits required are local permit for “Excavation.”
52. QUESTION: We have found 2 ½” Type K waterline and fittings to be difficult if not impossible to obtain. What alternatives will the Government accept?
ANSWER: No alternative at this time. The Government requires 2 ½ Type K waterline and fittings. This may be modified during construction if not available.
53. QUESTION: What is the deadline to submit additional RFI’s?
ANSWER: Deadline for additional questions will be provided in Amendment 4.
54. QUESTION: Due to the small scale of this project, will an AISC certified fabricator and erector be required per the specs (051200-1.6)?
ANSWER: Yes, AISC certification is required.
55. QUESTION: Please issue any available as-built drawings to better aid us in our proposal, especially related to MEP items.
ANSWER: Additional as-built drawings are attached to Amendment 0008
56. QUESTION: After reviewing the Phasing plan, it appears swapping Phase 1 and Phase 2 will provide a better work flow, especially for the Mechanical items. Will the swapping of these phases be acceptable?
ANSWER: Contractor to set up detailed phasing plan. Original concept was to have Smitty move once and that is how Phase 1 was decided.
Temporary heating and cooling was discussed. Option for contractor to provide switchover between phases during tenant move also discuss.
Swapping Phase 1 and 2 per the question above would be less problematic since Phase 1 areas (Current Shop and Storage) are conditioned with Roof Top Units. Smitty would move to the existing Shop and Storage prior to start of construction. After the Phase 2 areas (built as the 1st Phase) are complete, Smitty would move into the Classroom areas. Smitty would need to move once more after completion of Phase 1 (Built as Phase 2).
ANSWER (Revised): Phasing has been eliminated; therefore, this question is no longer valid..
57. QUESTION: I have a question in reference to gaining access to the base in order to turn in the Bid Proposal CD’s and Bid Bonds. What is the process for hand delivery of the package? Do you have a base access form that should be submitted in advance, for approval? If so, could you please provide a copy?
ANSWER: Offerors are cautioned that Whiteman AFB, MO has visitor control procedures requiring individuals not affiliated with the installation to obtain a visitor pass prior to entrance. SOME DELAY SHOULD BE ANTICIPATED WHEN HANDCARRYING PROPOSALS. Offerors should allow sufficient time to obtain a visitor pass and arrive at the bid depository PRIOR to the time specified for receipt. Offerors shall coordinate with Lt Beamer, 660-687-5416 if base access is required for proposal receipt to 509 CONS.
58. QUESTION: During the site visit yesterday at Building 527, we noticed the existing soffit on the East and South exterior sides are badly deteriorated with a large area of rotten wood and peeling paint for the soffit in the south-east corner. Drawing number A-201, East and South Elevations, have notes to paint Wood Fascia, Soffit and, Gutters and downspouts. The wood fascia and soffit on the East and South sides of the building have deteriorated wood that is unacceptable to paint without replacing the existing wood. The total square footage area of rotten wood is unknown. Please provide further identification for proper repair of this condition.
ANSWER: The paint on the soffit and gutters is peeling but the plywood substrate on the soffits appears to be in fairly good condition. The different materials will need to be scraped, sanded and primed with the appropriate products before final paint can be applied.
59. QUESTION: Once the original proposal receipt has been delivered to 509 CONS on CD, how may we submit a revised Bid Schedule for pricing or modification to our proposal, if needed?
ANSWER: Electronic modifications are allowed as long as the original proposal has been received by 509 CONS. E-mail modifications to proposals will be accepted, however they must be received in this office prior to solicitation closing date. The e-mail address is 509cons.sollgca@us.af.mil.
60. QUESTION: RFP Page 59 – Section L “General Information” A.1. – A page is defined as 8 ½ x 11:
Question 1a: For the required schedules, can we submit them on pages that are 11 x 17?
ANSWER: Yes; Sub-factor 2’s Construction Schedule may be submitted as
Question 1b: And can they be outside of the page count, as attachments?
ANSWER: No; Section L, Part I’s identified limits apply…no more than 15 pages total for Sub-factors 1, 2 and 4 and no more than 10 pages total for Sub-factor 3.
Question 1c: If they are to be within the page count, can they be counted as one page?
ANSWER: No; Section L, Part I’s identified limits apply…no more than 15 pages total for Sub-factors 1, 2 and 4 and no more than 10 pages total for Sub-factor 3.
61. QUESTION: I would like to confirm that our proposal submission is to contain the following: 3 CDs total: 1 – Original Bid Bond; 1 – Original and copy of the SF 1442
ANSWER: CORRECTION TO QUESTION 3 ANSWERED PREVIOUSLY –
Per the SF 1442 INFORMATION REGARDING SUBMISSION OF PROPOSALS, all proposals and related documents will be submitted via CD/disc to 509 CONS unless otherwise noted. The CD/disc must arrive at the designated time specified in the solicitation to be considered responsive, and considered in the evaluation process. All of the required mailto:509cons.sollgca@us.af.mil documents and data per the SF 1442, PART I–TECHNICAL CAPABILITY and PART II– PRICE PROPOSAL must be submitted via CD/disc.
As to the number of CDs/discs submitted will depend on the size of the files submitted for PART I and PART II requirements. Individual CDs/discs are not required for each part.
Ensure all files on the CDs/discs are properly labelled. In addition, a copy of the Bid Bond may be included by CD/disc, but the original Bid Bond with a raised seal is required with submission of an Offeror’s proposal.
59. QUESTION: We have a question on the existing electrical service. The drawings indicate that we are supposed to install a new 1200 Amp Main Switchboard next to the existing to be demolished 1200 Amp Main Disconnect and splice on to the 1200 Amp service at that location. From the site visit, it appears that there is a single 4" conduit that feeds a bus duct going into the top of the 1200 Amp disconnect. Based on this we are questioning whether there is actually a 1200 Amp service to the building. Can you confirm that there is a 1200 Amp service running into Mechanical Room 145 that we can splice on to? And if there is not, what should be provided in our bid for this portion of the work?
ANSWER: The electrical service along with the building transformer appear to be undersized. a minimum 425kVA transformer is required with 9 x 500kcmil cables for the three phases, 3 x 500 kcmil for 100% rated neutrals, and 3 x 2/0 for ground to B527. The feeder needs to be upsized to this size due to the ~80 feet distance from the transformer to the MPDP in order to meet NEC voltage drop requirements. The transformer pad will have to be enlarged; new service with conduit run to the facility; and a new transformer installed.
This will have to be scheduled to not interfere with UMB back which is fed from the same transformer.
60. QUESTION: The sign schedule calls for a total of 11 signs, reference drawing A-001, will signs for modular wall system rooms and offices be required? If so, what type of sign is required? Will signs for restroom 138 and 139 be required?
ANSWER: Signs are not required for the modular wall system rooms and offices under this contract. Yes, signs are required for restrooms 138 and 139. The signs should match the signs specified for 160 and 161.
61. QUESTION: Will testing of the aluminum framed entrance be needed, and, if so, what is the testing requirement?
ANSWER: No
62. QUESTION: Under door hardware 2.1 A notes to field verify existing hardware in areas to receive new doors and hardware. Match existing adjacent hardware to remain. The hardware schedule in Part 3 calls for Best manufacturer with model numbers. Is using Best manufacture acceptable with different models that are standard for demountable partitions?
ANSWER: Yes
63. QUESTION: Does the concrete wall which is the East Wall of the Thrift Shop (D6) remain?
ANSWER: Yes the concrete wall remains and gets furred out with wall type C3 per wall types schedule on sheet A-102.
64. QUESTION: Is the South Wall of the Thrift Shop a concrete wall (D5) and does it remain?
ANSWER: Yes the concrete wall remains and gets furred out with wall type C3 per wall types schedule on sheet A-102.
65. QUESTION: How many linear feet of saw cuts are there as outlined in Note #19. How wide of a channel are we cutting out?
ANSWER: You would need to cut approximately 320 lineal feet of trench to reach all floor boxes and the trench width will only be as much as required to place the new work.
66. QUESTION: On the South Wall of the current bathrooms (B5&6) there is an opening described in Note #10/ How wide is the new opening? If it is less than 8 foot, can we saw cut the opening to 8 foot and then can we reinstall new concrete block to the size needed?
ANSWER: The exterior brick opening width will need to be 6’-4 1/2” wide per door schedule on A-001, door 148. You will not want to remove more width than the hollow metal frame will require on the exterior, the concrete block could be cut wider and replaced with concrete block if necessary.
67. QUESTION: During the various phases, restroom facilities may not be available within the building for the occupants use. What is the Government’s expectation in this regard? If restroom facilities are to be maintained by the contractor, will a portable trailer unit outside the building be acceptable?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
68. QUESTION: On drawing A-104, Roof Plan, the drawing indicates that the old RTU penetrations are to be capped in a “weathertight tight manner”, are we correct that the existing curb is to remain? Is wood construction permitted? Is the RTU area to be insulated?
Will the government provide any further details regarding their expectation of the cap construction?
ANSWER: Existing curbs are to be removed metal decking installed and rigid insulation the same thickness as existing is to be installed along with dense deck cover board and a glue down TPO patch by a contractor that is certified by Firestone to install TPO roofing.
69. QUESTION: Will exposed exterior steel lintels be required to be hot dipped galvanized?
ANSWER: Yes
70. QUESTION: What is the relocation time required by the government between the construction phases?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
71. QUESTION: RB1 is indicated in Bathrooms 162/163 on the finish schedule. Since the walls and floors are ceramic tile in these rooms, please confirm you want rubber base in these rooms and not a tile base.
ANSWER: Bathrooms 160 & 161 have wall tile full height of wall on the wet walls and wall tile up to 4’-6” above finished floor on the rest of the walls so they would all have tile base not rubber base.
72. QUESTION: During the Phase 3 Area use as a classroom, what does the Government intend for restrooms? Is the contractor to provide restroom facilities during this temporary use period?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
73. QUESTION: What level of restoration of the Phase 3 area does the Government expect prior to using the area for classrooms? Do floor, walls, & ceiling require patching, painting, etc.
after the space demolition prior to turnover for use as temporary classrooms?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
74. QUESTION: Is the contractor responsible for any and all costs regarding tenant relocations including; moving furniture, temporary phones and data drops, and temporary wall partitions for offices?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
75. QUESTION: The demising line between Phase 1 and 2 located at column lines 1 to 2 and down page to column line D does not make any sense as the new rooms in this area are split in half +/- and extend beyond column line 2 towards column line 3. Does the Government intend on completing these rooms in two different phases of work? How will these spaces be occupied? Should this area be included in the present Phase 1 work area?
ANSWER: Phasing has been eliminated; therefore, this question is no longer valid.
76. QUESTION: Several questions in addendum 5 are indicated as “To be answered.” Will answers to questions # 23, 24, 45, 46 be provided in an upcoming addendum?
ANSWER: Yes, they are answered.
77. QUESTION: Addendum 5 question #33 requested elevations and finish schedule for the demountable walls. The answer did not provide this information. Will the elevations/finish schedule be issued in the forthcoming addendum?
ANSWER: Question #33 has now been answered.
78. QUESTION: Following up on addendum 5 question #51, please confirm an AISC certified fabricator will be required per the specs and a non-certified AISC fabricator will not be acceptable.
ANSWER: An AISC certified fabricator is required.
79. QUESTION: Following up on addendum 5 question #53, please confirm it will be acceptable for the Contractor to propose an alternate phasing plan for Phases I & II to provide for a better work flow. Phase III to remain as shown.
ANSWER (Revised): Phasing has been eliminated; therefore, this question is no longer valid.
80. QUESTION: I was wondering if Edwards (EST) is approved for the fire alarm and mass notification?
ANSWER: Edwards (EST) is not an approved fire alarm and mass notification system for Whiteman AFB. Question #41 listed the approved systems.
81. QUESTION: (Now that the project is not under phased construction without occupancy.)
Can the existing fire protection and fire suppression be removed and then installed new thereafter without requiring continuous protection?
ANSWER: Yes, the existing fire detection/alarm system and fire suppression may be removed and then installed without requiring continuous protection. The contractor will be required to perform a walk-though of the building at the end of each day to ensure there are no issues and must also ensure they have procedures to contact the Fire Department in case of emergency.
82. QUESTION: Is there any asbestos that needs to be removed prior to demolition? If there an Environmental Survey that has been done?
ANSWER: All asbestos that has been identified has been removed
83. QUESTION: Are we able to work on weekends?
ANSWER: Weekend work may be accomplished with prior approval of the Contracting Officer based upon the type of work being approved. Contractor must submit request for weekend work to the Contracting Officer two weeks prior to the anticipated work.
84. QUESTION: Demolition Plan Note 19. Since the Temporary wall plan has changed, is there still any sawcutting on the floors? If so, how many linear feet, and how wide is the channel?
ANSWER: Yes, there is still floor cutting required. The actual width and length shall be determined by the General Contractor to perform the work.
85. QUESTION: Is the system going to be a complete tear out back to the discharge side of the backflow?
ANSWER: All steel piping is required to be Schedule 40, not Schedule 10 (all inclusive).
The entire suppression system will required to be replace back to the discharge side of the backflow.
86. QUESTION: If this is not the case what parts of the system are to stay (riser, mains, branch lines etc.)?
ANSWER: See answer to number 85.
87. QUESTION: Is painting of exposed fire sprinkler piping by painter or fire suppression contractor?
ANSWER: We do not designate which subcontractor performs the work. That is a decision for the General Contractor.
88. QUESTION: Is demo of fire sprinkler piping in fire suppression scope of work?
ANSWER: Demo for fire sprinkler piping is a decision for the General Contractor.
89. QUESTION: Are flexible connections to sprinkler heads required?
ANSWER: Sprinkler heads shall be connected via steel piping.
90. QUESTION: Is job requiring “Buy-American” or “Domestic Construction” for materials?
ANSWER: "Buy American" is always required and the Buy American clause (52.225-9) was incorportated into the soliciation.
91. QUESTION: Is Schedule 10 steel piping acceptable?
ANSWER: Schedule 10 steel is not acceptable. All steel piping must be Schedule 40 (all inclusive).