DMAC LIQUIDAM Template PWS appendix B.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Demolition Multiple Award Contract (DMAC) Federal contract opportunity
Solicitation number
FA4620-11-Q-B002
Issued by
Department of the Air Force Air Mobility Command

About this file

Appendix B.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Physical Work Phase

LIQUIDATED DAMAGES BREAKDOWN-APPENDIX B
Demolition Multiple Award Contract (DMAC)
PAYHOURSHOURLYTOTAL
GRADEPER DAYRATE (1)PER DAY
CIVIL ENGINEERING (CES)
COR MANAGEMENTGS-120.25HR$ 63.28$ 15.82

TECHNICAL REPRESENTATIVE GS-11 0.50 HR $ 52.71 $ 26.36

CONTRACTING OFFICER REPRESENTATIVE GS-9 1.00 HR $ 43.69 $ 43.69

TOTAL CIVIL ENGINEERING: $ 85.87

CONTRACTING (CONS)

CONTRACTING MANAGEMENT GS-12 0.25 HR $ 63.28 $ 15.82

CONTRACTING OFFICER GS-11 0.50 HR $ 52.71 $ 26.36

CONTRACT ADMINISTRATOR GS-9 1.00 HR $ 43.69 $ 43.69

TOTAL CONTRACTING: $ 85.87

TOTAL LIQUIDATED DAMAGES: (CES + CONS) $ 171.73

DAILY RATE:$ 126
Total Liquidated Damages multiplied by 22 (average # of work days per month)
divided by 30 (average # of days per month) rounded to the nearest dollar.
If the contractor fails to complete the work within the time specified in the contract, the contractor shall pay to
the Government as liquidated damages the sum of $126 for the first day of delay and $126 for each day thereafter.