Atch H Spec 028301-Lead Paint Removal Specification.pdf

PDF 56 KB Posted

Attached to
Demolition Multiple Award Contract (DMAC) Federal contract opportunity
Solicitation number
FA4620-11-Q-B002
Issued by
Department of the Air Force Air Mobility Command

About this file

Please review. The specification for Lead Paint Removal.

View the file

Other files for this federal contract opportunity

Other files attached to Demolition Multiple Award Contract (DMAC), newest first.
File Type Posted
Amendment 3 with revised PWS dtd 23 June 2011.pdf PDF
Amendment 0002 as 0006.pdf PDF
PWS 10-0171 Bldg 1710 Rev 13June.pdf PDF
Atch G Spec 028300-Asbestos Removal and Related Work.pdf PDF
Atch E HazMat Survey 10-0171.pdf PDF
Amend 1 remove LDs fix set aside.pdf PDF
RFP attach 6 orientation seminar PWS.pdf PDF
Atch 5 Demo Bldg 1710 DMAC Seed PWS and attachments.pdf PDF
DMAC LIQUIDAM Template PWS appendix B.xlsx XLSX spreadsheet
DMAC RFP Attach 4 WD 05-2565 rev 10.pdf PDF
11-Q-B002.pdf PDF
11-Q-B002 attach 1 DMAC PWS w appendix A.pdf PDF
DMAC RFP attch 2 PPQ.pdf PDF
RFP attach 3 Reps Certs.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEMOLISH BUILDING 1710 ATTACHMENT H

LEAD-BASED PAINT BLDG COMPONENT

GJKZ 10-0171 REMOVAL, BLDG DEMO & RELATED WORK

1021.10 028301 - 1

SECTION 02 83 01 - LEAD-BASED PAINT BUILDING COMPONENT REMOVAL, BUILDING

DEMOLITION AND RELATED WORK

PART 1 - GENERAL

1.1 DESCRIPTION OF WORK

A. Certain surfaces at FAFB Bldg. 1710 have been identified as being coated with lead based paint

(LBP). The results of the LBP inspection conducted at Building 1710 are contained in the report Lead Paint Survey Building 1710 Demolition Project, June 7, 2011, prepared by Environmental Risk Management. This report provides information on the substrates that were tested and the results. A complete copy of the report is included herewith as part of this specification section.

1. The interior and exterior steel door jambs, roof drain piping, boiler pressure tank, electrical breaker boxes, electrical lighting equipment in the restroom, exterior storage room window grate and automobile wheel bolted to the building were not sampled and are assumed to have lead paint and are required to be salvaged. The Contractor must salvage these metal building components with lead paint.

2. The equipment must be sent to a properly licensed salvage company and the salvage company must be notified in writing of the presence of lead paint on the salvage components.

Copies of signed acknowledgement documents must be submitted to the 92 CONS Contracting Officer. See photographic log for identification of building components to be salvaged in Appendix C of the Lead Paint Survey Building 1710 Demolition Project, June 7, 2011, prepared by Environmental Risk Management.

3. The steel door jambs identified to be salvaged must removed and abated of asbestos-containing sealer caulks by asbestos certified workers as outlined in the Building 1710 asbestos specification prior to salvage activities.

4. FAFB Building 1710 lead paint building component TCLP-Lead sample analytical results were below the Washington State Dangerous Waste Regulation (WAC 173-303) TCLP-Lead threshold for leachable lead of 5 PPM and are not classified as a hazardous waste and can be disposed of as general construction debris. See TCLP Lead Analytical report in Appendix B of Lead Paint Survey Building 1710 Demolition Project, June 7, 2011, prepared by Environmental Risk Management for analytical information.

5. FAFB requires that the lead painted CMU block and concrete in the interior restroom area not be recycled due to the presence of lead paint on the walls and ceilings. The Contractor may choose to remove the paints from this room prior to building demolition to recycle the CMU block and concrete If the Contractor chooses to recycle the remainder of the concrete and CMU block building, all lead-containing components must be removed prior to demolition for the recycling of the concrete or CMU block.

6. The Contractor will have a Certified Industrial Hygienist to certify that the Lead Abatement Contractor’s lead-based paint work plan, and the air sampling plan are in compliance with the contract specifications as well as all applicable regulations.

7. The Contractor will have an independent 3rd Party Industrial Hygienist on-site to perform testing, including but not limited to, fence line or work area perimeter dust monitoring and final inspections.

1021.10 028301 - 2

B. The Contractor is responsible for performing the work in accordance with this specification, with all referenced documents included as part of this specification, and with all applicable Federal, state and local regulations governing work involving lead based paint. Wherever there is a conflict or overlap of requirements, the most stringent provisions shall apply.

C. All work that disturbs lead paint, including but not limited to, manual demolition, removal of paint from concrete walls or ceilings, removal of building components shall comply with this Section.

D. It is the intent of the Work to remove intact building materials that are coated in lead based paint for salvage and the cleanup of any paint debris associated with building demolition. The Contractor is responsible to review the lead paint sampling report referenced above for specific interior and exterior locations of lead-painted surfaces.

E. The work of this section consists of, but is not limited to:

1. Furnishing all labor, materials, facilities, equipment, services, and insurance necessary to perform the work in accordance with this section and with all Federal, state and local regulations;

2. Completion of required regulatory notifications;

3. Installation of required regulatory warning signs and maintenance of work area/site security;

4. Preparation of work area, including installation of decontamination areas as required;

5. Provision of engineering controls and dust control work methods to prevent the release of dust generated by lead-based paint removal work or other activities that may disturb lead-based paint to adjacent areas or the outdoors.

6. Clean-up and final decontamination of all work areas;

7. Implementation of a worker protection and training program in compliance with all applicable regulations;

8. Proper storage (including signage, secondary containment, etc.), labeling, transportation and disposal of all waste generated as part of activities in compliance with all applicable regulations

F. The Contractor is responsible for ensuring that all personnel performing work under this section shall be properly trained in accordance with all Federal, state and local regulations, including but not limited to the Occupational Health & Safety Administration’s (OSHA) Lead Exposure in Construction Standard (29 CFR 1926.62). The Contractor is required to provide proof of training of any and all employees completing the work of this section as part of an initial Lead Paint Contractor Submittal Package at least 10 days prior to the start of Work.

G. It is the Contractor’s responsibility to determine the most efficient method to legally perform this

Work. Unless specifically noted, this Specification does not dictate specific methods to be implemented in the performance of the Work.

1021.10 028301 - 3

H. The Contractor will have an independent 3rd Party Industrial Hygienist on-site to perform testing, including. but not limited to, fenceline or work area perimeter dust monitoring and final inspections. The Lead Abatement Contractor shall coordinate their work schedule closely with the Contractor and shall cooperate fully with the 3rd Party Industrial Hygienist.

I. The Lead Abatement Contractor will clean all work areas of any visible debris at the end of each workday using a HEPA vacuum and will collect and store all lead waste (e.g., lead paint chips) on site in secured container(s) that are properly labeled and meet all regulatory requirements.

Disposal of removed lead based paint waste and debris coated with intact lead based paint is further specified in Paragraph 3.10.

1.2 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in text by basic designation only. The list provided below is not intended to be all inclusive of each regulation prevailing over the work. The latest version of the document listed shall govern the work performed.

B. Occupational Safety and Health Administration (OSHA)

1. General Industry Standards, 29 CFR 1910.

2. Lead Standard for General Industry, 29 CFR 1910.1025 .

3. Respiratory Protection, 29 CFR 1910.134.

4. Hazard Communication, 29 CFR 1910.1200.

5. Specifications for Accident Prevention (Sign and Tags), 29 CFR 1910.245.

6. Construction Industry Standards, 29 CFR 1926.

7. Construction Industry Lead Standard, 29 CFR 1926.62.

C. Environmental Protection Agency (USEPA)

1. United States Environmental Protection Agency Regulations, 40 CFR Part 261.

D. Department of Housing and Urban Development (HUD)

1. Lead- Based Paint Regulations, 24 CFR Parts 35, 36, 37.

2. Guidelines for the Evaluation and Control of Lead- Based Paint Hazards in Housing.

E. Washington Industrial Safety and Health Act's (WISHA)

1. Standard for Lead in Construction, WAC 296-155-176.

F. Washington Administrative Code - Hazardous Waste and Toxics Reduction (HWTR)

1021.10 028301 - 4

1. Dangerous Waste Regulations, WAC 173-303

1.3 DEFINITIONS

A. Lead Abatement/Removal: Any measure designed to permanently eliminate lead- based paint hazards in accordance with standards established by the EPA Administrator pursuant to Title IV of the Toxic Substances Control Act (TSCA). Abatement strategies include: removal of lead-based paint; enclosure of lead- based paint; encapsulation of lead- based paint (with a product that has been shown to meet standards established or recognized pursuant to Title IV of TSCA);

replacement of building components coated by lead- based paint; removal of lead- contaminated dust; removal or covering of lead- contaminated soil with a durable covering (not grass or sod, which are considered interim control measures); as well as all preparation, cleanup, disposal, post- abatement clearance testing, record- keeping, and monitoring (if applicable).

B. Lead Abatement Area: The exterior of the building or an area isolated from the building interior by containment demarcated for lead-paint work activities.

C AIHA: American Industrial Hygiene Association

D. Action Level: An action level is an indoor air concentration which should prompt consideration of the need to implement a recommended response. The Action Level for lead is 30 ug/m3 (0.3 mg/m3)

E. Change Room: The area of a worker decontamination facility used for removing protective equipment prior to entering the clean room.

F. Clean Room: The area of a worker decontamination facility used for donning protective equipment and storing street clothes.

G. Containment: Means a process for protecting other workers, residents, and the environment by isolating areas from exposures to lead dust and debris created during abatement in a work area.

H. Contractor: Refers to the General Contractor and/or Subcontractor responsible for the Work under contract with the Fairchild AFB 92 CONS.

I. DOT: United States Department of Transportation

J. 3rd Party Industrial Hygienist: The third party industrial hygienist shall be subject to approval as specified in paragraph SUBMITTALS and shall be (1) have prior experience in the health and safety aspects of an asbestos removal project, or (2) have a minimum of three years prior experience in industrial hygiene relating to asbestos work.

K. Engineer: FAFB 92 CONS Contracting Officer or his/her agent, or any personnel authorized by

FAFB.

L. EPA: United States Environmental Protection Agency

M. Fairchild AFB 92 CONS Contracting Officer: A representative of Fairchild AFB.

N. Hazardous Waste Level of Lead: The RCRA Toxicity Characteristic Leachate Procedure (TCLP) standard is 5.0 mg/L (PPM).

1021.10 028301 - 5

O. HEPA Filter: High Efficiency Particulate Air Filter

P. High Phosphate Detergent: Detergent which contains at least five percent (5%) tri- sodium phosphate (TSP) or other equally effective cleaning agent.

Q. Lead-based: Refers to paints, glazes, another surface coverings containing a toxic level of lead.

R. MSDS: Materials Safety Data Sheets

S. OSHA: Occupational Safety and Health Administration

T. PEL: Permissible Exposure Limit. The PEL for lead is 50 ug/m3 (0.05 mg/m3) for an 8-hour exposure.

U. RCRA: Resource Conservation and Recovery Act

V. Toxic Level of Lead in Surface Coatings: 1.0 milligram or more per square centimeter (mg/cm2) by XRF methods, or 5,000 g/g (0.5%) by laboratory testing, as defined in HUD Regulation and the Lead- Based Paint Poisoning Prevention Act.

W. TSCA: Toxic Substance Control Act

X. TSP: Tri-Sodium Phosphate

Y. TCLP: Toxicity Characteristic Leachate Procedure

Z. VOC: Volatile Organic Compound

1.4 LOCATION OF WORK AND SITE CONSTRAINTS

A. Any areas where lead-based paint disturbance or removal activities are occurring shall be restricted to authorized personnel. Once work commences, access to the work area shall be strictly limited to the Contractor’s authorized personnel, the FAFB 92 CONS Contracting Officer or his/her agent, or any personnel authorized by FAFB. Only those persons with specific permission of FAFB shall enter the work area (excepting those government officials performing their official duties and allowed by regulation to enter).

B. Temporary Utilities: Currently there are no electricity sources available at Building 1710. The

Contractor will be required to provide temporary power as well as bathroom facilities during the lead based paint work period.

C. Prior to the commencement of work and at the AFB 92 CONS Contracting Officer’s request, the

Contractor, Lead Abatement Contractor, along with representatives and agents of Fairchild AFB shall meet to discuss the scope and schedule of work, security, and access to building.

1.5 QUALIFICATIONS, ROLES AND RESPOSIBILITIES

A. The Contractor, or Lead Abatement Subcontractor, performing any of the Work detailed in this specification must have a current State of Washington Department of Commerce Lead Abatement License. A copy of the license shall be provided to the 92 CONS Contracting Officer at least 10

1021.10 028301 - 6 days prior to the start of the work of this section as part of an initial Lead Paint Abatement Contractor Submittal Package. For lead-paint abatement work that will be sub-contracted, the Contractor is responsible to ensure that the Lead Abatement Subcontractor has reviewed and will strictly adhere to this specification, all reference documents, and with all Federal, state and local regulations.

B. Lead Abatement Subcontractor. The Lead Abatement Subcontractor for abatement must have successfully completed at least three abatement projects involving all requirements elements of abatement work, including worker protection, medical monitoring, work area preparation, clean-up and clearance. Only properly licensed lead abatement contractors are allowed to work on Fairchild AFB property.

C. The Lead Abatement Subcontractor shall employ a competent licensed supervisor with at least three years lead hazard control supervisory experience on projects of similar scope and magnitude who shall be responsible for all work involving lead- based paint abatement as described in the specifications and defined in applicable regulations, and have full- time daily supervision of the same.

D. Certified Industrial Hygienist. The CIH shall be required to certify that the Lead Abatement Contractor’s lead work plan, and the air sampling plan are in compliance with the contract specifications as well as all applicable regulations.

E. General Contractor. The General Contractor will be responsible for providing a 3rd Party Industrial Hygienist and ensuring the Lead Abatement Contractor is compliant with contract specifications and regulatory compliance.

F. 3rd Party Industrial Hygienist. The 3rd Party Industrial Hygienist shall be responsible for performing the final lead work cleanup inspections and final visual clearance of the lead work areas.

G. Lead Abatement Contractor Supervisor. The Lead Abatement Contractor Supervisor shall ensure the correct number of air samples, prepare daily work logs, keep daily entry/exit logs, and perform all other duties required of the competent person including: interpret the air sampling results and number of samples to ensure they are consistent with the lead work plan and air monitoring plans, and provide daily oversight for compliance with the lead work plan and air monitoring plans, as well as all applicable regulations.

H. Approved Labs. The approved labs shall analyze all air samples and document the results.

1.6 CONTRACTOR RESPONSIBILITY

A. The Contractor shall assume full responsibility and liability for the compliance of all federal, state and local regulations pertaining to:

1. Worker safety and hygiene.

2. Protection of workers, the public, FAFB personnel, building components, and the environment against potential lead exposure or contamination.

3. Transportation and disposal of lead contaminated waste.

B. The Contractor shall be responsible for determining airborne lead concentrations for each task performed that will impact building materials coated with lead-based paint.

1021.10 028301 - 7

C. The Contractor shall be responsible for establishing a regulated work area for each task performed that will impact building materials coated with lead-based paint.

D. Work Areas Affected - In general, the following activities are minimum requirements of this Section and affect the demolition performed on the painted components:

1. No torch cutting, mechanical sanding or stripping or abrasive methods shall occur on painted surfaces without the use of HEPA vacuum attachments.

2. No demolition activities may occur that increase the workers' exposure above the Action Level of 30 µg/m3. Contractor shall fully comply with the OSHA lead standard at 29 CFR 1926.62.

3. All workers shall be informed of the components to be demolished that have been identified as containing lead.

E. The Contractor shall provide appropriate respiratory protection, protective clothing, and engineering controls to minimize the exposure of employees to airborne lead. All work involving the disturbance of paints containing lead at the site and all work where employees may be exposed to lead in excess of the Action Level of 30 µg/m3 shall be performed by workers that have received appropriate lead training and personal protective equipment.

F. The Contractor shall be responsible for proper clean-up procedures, handling and disposal of the waste and materials generated in accordance with the methods described in this Section. The Contractor shall collect all wastes resulting from the work and perform appropriate sampling as required by RCRA and other applicable regulations for the proper packaging, handling, shipment and off-site waste disposal. The Contractor shall provide the 92 CONS Contracting Officer with all results of waste characterization and all transport and disposal manifests.

G. The Contractor shall be responsible to make all arrangements for the proper transportation and disposal of lead contaminated materials as described in Section 3.09 and Section 3.10.

H. The Contractor shall have an individual on-site designated to perform the duties of the “Competent Person” as specified by OSHA 29 CFR 1926.62. The competent person shall be a person who is capable of identifying existing and predictable lead hazards in the surroundings or working conditions and who has the authorization to take prompt corrective measures to eliminate them.

I. The Contractor shall provide laboratory analytical services for the analysis of lead samples. The laboratory shall be accredited by the American Industrial Hygiene Association (AIHA) and be a successful participant in the AIHA Proficiency Analytical Testing (PAT) program. The Contractor shall perform monitoring and sampling as follows:

1. Personal air sampling in accordance with OSHA 29 CFR 1926.62.

2. 3rd Party Industrial Hygienist air sampling along the fence line or work area perimeter dust monitoring.

3. Waste characterization (i.e., TCLP lead) samples of paint debris and disposables (tyvek suits, respirator cartridges, plastic sheeting, paint debris, etc) from lead-based paint work activities as required by RCRA.

1021.10 028301 - 8

1.7 SCHEDULING

A. The Contractor shall develop an abatement schedule for each phase of work prior to the Pre- Construction Conference. The 92 CONS Contracting Officer may choose to alter the work sequence as they see fit.

B. The Contractor shall update the schedule and submit any schedule changes for review by the 92

CONS Contracting Officer at the weekly construction meetings.

C. There shall be a sufficient number of trained and qualified workers, foremen and superintendents to accomplish the work within the required schedule. No untrained or fully qualified person shall be employed to speed up completion of the abatement work.

1.8 PERMITTING AND INSPECTION

A. The Contractor is responsible for obtaining and/or filing any permits, notifications, and/or approvals and for making any regulatory notifications required to perform the work of this section. The Contractor shall deliver a copy of all permits, approvals and notifications to the 92 CONS Contracting Officer as part of their initial Lead Paint Contractor Submittal Package.

B. The Contractor shall allow the work of this contract to be inspected if required by local, state, federal and any other authorities having jurisdiction over such work. The Contractor shall immediately notify the 92 CONS Contracting Officer and shall maintain written evidence of such inspection for review by the 92 CONS Contracting Officer.

C. The Contractor shall incur the cost of all fines resulting from regulatory non-compliance as issued by federal, state, and local agencies. The Contractor shall incur the cost of all work requirements mandated by federal, state, and local agencies as a result of regulatory noncompliance or negligence.

D. The Contractor shall, at his/her own cost and expense, comply with all laws, ordinances, rules, and regulations of federal, state, regional and local authorities regarding handling and storing of lead waste material.

E. In the case of an emergency, the Contractor shall contact local fire, police, hospitals or local emergency response teams and inform them of the type of hazardous waste activity and ask for assistance in the event of an accident.

F. During the course of the project, the Contractor shall maintain the following on-site: (1) a suitable fire extinguisher(s) near the work area; (2) an immediate means of communication with a regulatory agency in the event of an emergency; and (3) a list of contacts and phone numbers including regulatory agencies.

G. The Contractor is responsible to ensure that all employees on-site are trained on how to deal with typical emergencies and accidents that may occur during the course of work. The Contractor shall identify an on-site emergency coordinator to ensure that emergency procedures are carried out in the event an emergency arises.

H. The Contractor shall keep and maintain a "Right to Know Manual” that is easily accessible to all employees.

1021.10 028301 - 9

1.9 SUBMITTALS

A. The Contractor shall submit each item in this Article according to the Conditions of the Contract and Submittals, for information only, unless otherwise indicated.

B. All submittals shall be submitted to the 92 CONS Contracting Officer prior to the start of work.

C. The Contractor shall submit a Lead-Based Paint Work Plan describing the procedures to be employed for complying with this Section and OSHA regulation 29 CFR 1926.62. Include detailed description of methods to be used for removal of lead painted building components, paint debris clean-up activities, containment, packaging, transportation, and disposal of lead paint.

D. The Contractor shall submit a Site Safety Plan which includes a set of emergency procedures and include provisions for the following:

1. Evacuation of injured workers;

2. Emergency and fire exit routes from all work areas, including local telephone numbers for fire and medical emergency personnel; and

3. Employee work logs.

The Site Safety Plan shall be posted in a conspicuous place at the work site so that it is available to all employees.

E. The Contractor shall provide sample literature for proposed protective clothing to be used on this project.

F. The Contractor shall provide Respiratory Protection System(s) including literature describing sample respirators, hoses and certificate with system literature for the air supply system from manufacturer stating that air supply system meets specifications on quality, quantity and escape time. These submittals are required only if supplied air respiratory protection is used.

G. The Contractor shall provide certification of compliance with OSHA requirements including but not limited to medical surveillance, record keeping and personal monitoring.

H. The Contractor shall provide Material Safety Data Sheets (MSDS) on all materials and chemicals to be used on the project.

I. The Contractor shall provide copies of manifests and receipts acknowledging disposal of all hazardous and non- hazardous waste material from the project showing delivery date, quantity, and appropriate signatures.

PART 2 - PRODUCTS

2.1 MATERIALS AND EQUIPMENT

A. Polyethylene sheet in a roll size to minimize the frequency of joints shall be delivered to job site with factory label indicating 6 mil conforming to ASTM Standard Specification for Polyethylene Film and Sheeting, ASTM D- 2103.

1021.10 028301 - 10

B. Polyethylene disposable bags shall be six (6) mil with pre-printed label. Tie wraps for bags shall be plastic, five (5) inches long (minimum), pointed and looped to secure filled plastic bags.

C. Tape or adhesive spray will be capable of sealing joints in adjacent polyethylene sheets and for attachment of polyethylene sheet to finished or unfinished surfaces of dissimilar materials and capable of adhering under both dry and wet conditions, including use of amended water.

D. Impermeable containers are to be used to receive and retain any lead containing or contaminated materials until disposal at an acceptable disposal site. (The containers shall be labeled in accordance with EPA and DOT standards.

E. Vacuum units, of suitable size and capacities for project, shall have HEPA filter(s) capable of trapping and retaining at least 99.97% of all monodispersed particles of 0.3 micrometers in diameter.

PART 3 – EXECUTION

3.1 GENERAL

A. The Contractor shall evaluate each work activity to determine if employee exposure to lead may occur.

B. Until the Contractor documents that employee exposures are below the OSHA PEL for each type of activity where lead is present, including but not limited to manual demolition of structures, preparation of surfaces for painting, clean-up activities, or at any other time when exposure to lead is a possibility, the Contractor shall provide the following:

1. Appropriate respiratory equipment as required by OSHA 29 CFR 1926.62(f).

2. Appropriate personal protective equipment as required by 29 CFR 1926.62(g).

3. Change areas as required by 29 CFR 1926.62 (i)(2).

4. Hand washing facilities as required by 19.26.62 (i)(5).

5. Biological monitoring as required by 29 CFR 19.26.62(j)(1)(i).

6. Training as required by 29 CFR 1926.62 (l)(1)(i), 29 CFR 1926.62(l)(2)(ii) and 29 CFR

1926.21

3.2 AIR MONITORING

A. The Contractor shall determine worker’s exposure to airborne lead for each phase of work, i.e., removal of building components, cleaning of work areas, etc. Personal air sampling shall be conducted at the start of each phase of work. Initial personal exposure monitoring shall be performed on employees who are anticipated to have the highest exposures for each activity.

1021.10 028301 - 11

B. Airborne lead sampling performed as required by OSHA regulation 29 CFR 1926.62 shall be full-shift sampling collected in the breathing zone of the worker being monitored. The Contractor shall ensure that all workers wear suitable respiratory protection at all times, if exposure to airborne lead is a possibility.

C. The Contractor will have an independent 3rd Party Industrial Hygienist on-site to perform testing, including but not limited to, fence line or work area perimeter dust monitoring.

3.3 WORK AREA PREPARATIONS

A. Isolate work area from adjacent areas of the building. Post caution signs meeting the specifications of OSHA regulation 29 CFR 1926.62 (k) at any location or approach to a location where airborne lead concentrations may exceed the Action Level of 30 µg/m3. Caution signs shall be posted at a sufficient distance from the work area to permit an employee to read the sign and take the necessary precautionary measures to avoid exposure. Additional caution signs may need to be posted following construction of workplace enclosure barriers (if applicable).

B. Protect all facility equipment and objects in the work area from lead contamination and damage from conduct of the work.

C. Provide clean change area equipped with separate storage facilities for protective work clothing and equipment and for street clothes.

D. Provide hand washing and shower facilities for employees whose exposure to lead is above the

PEL.

E. Ensure proper fall protection equipment and procedures are used during each phase of the work, including erection of scaffolding. Provisions shall be used to protect workers from falling equipment, materials and debris.

3.4 WORK CONSTRAINTS

A. The Contractor shall provide required respiratory and personal protective equipment to all employees who may be exposed to airborne lead in excess of 30 µg/m3.

B. Lead-based paint removal operations where airborne lead concentrations exceed 30 µg/m3 shall be performed within a fully contained work enclosure and require decontamination facilities.

C. Lead-based paint removal operations where airborne lead concentrations exceed 50 µg/m3 shall be performed within a fully contained work enclosure, under negative pressure with required decontamination facilities.

D. Paint removal activity shall be engineered and conducted such that the least amount of airborne dust is generated. The Contractor shall ensure that all dust is contained within the work area and does not contaminate the building, equipment in the building, or the environment.

E. Engineering controls employed to contain dust generated by paint removal activity may include, but not be limited to, sealing all openings to the work area with impermeable barriers, dust

1021.10 028301 - 12 collection equipment with HEPA filtration and mechanical ventilation equipped with HEPA filtration to maintain negative pressure in the work area with respect to adjacent areas of the building.

3.5 AUTHORITY TO STOP WORK

A. The 92 CONS Contracting Officer has the authority to issue a stop work order at any time the 92 CONS Contracting Officer determines that conditions are not within the specifications and applicable regulations. The stoppage of work shall continue until conditions have been abated and corrective steps have been taken to the satisfaction of the 92 CONS Contracting Officer.

Standby-time required to resolve violations shall be at the Contractor’s expense, and any fines, etc., for hazardous conditions or non-compliance will be at the Contractor’s expense and will not be justification for change orders or time extension.

B. Stop work orders may be issued for, but not be limited to, the following:

1. Respirable dust levels measured outside the lead work area exceed established background levels.

2. Area air samples analyzed for lead in accordance with NIOSH Method 7082 exceed established background levels.

3.6 INTERIOR LEAD REMOVAL

A. Interior de-leading may also include the intact removal of lead painted building components as identified in other specification sections. The Contractor shall remove lead painted building components in a manner that does not generate airborne lead contaminated dust. These components shall be segregated from other demolition waste and disposed of in accordance with this section.

B. One layer of polyethylene sheeting will be laid on the floor adjacent to areas where lead based paint building component removal will be performed. In addition, the Contractor will use polyethylene sheeting to effectively separate all work areas to ensure that no paint chips and/or dust generated during the work is allowed to migrate beyond the work area.

C. All visible debris shall be cleaned up at the end of each workday. Prior to removal, all protective polyethylene sheeting will be HEPA vacuumed.

D. Re-cleaning will be required until an inspection performed indicates no visible dust or debris remains in the work area.

E. If visible suspect debris is observed outside of the work area, re-cleaning will be required until a level of no visible dust or debris is achieved and final inspection from the 92 CONS Contracting Officer as outlined in section 3.08 are achieved.

3.7 FINAL INSPECTION

A. Notify the 92 CONS Contracting Officer 24 hours in advance of completion of cleaning activities and removal of debris from the work area.

1021.10 028301 - 13

B. The 92 CONS Contracting Officer will visually inspect the work area for visible dust, debris or contamination. The Contractor shall perform all additional cleaning of the work area required by the 92 CONS Contracting Officer at the Contractor’s expense.

C. The “clearance criteria” to indicate that the work area is “clean” shall be based on a visual inspection.

D. The Contractor shall have an independent 3rd Party Industrial Hygienist on-site to perform periodic inspections and final inspections prior to notifying the 92 CONS Contracting Officer for final visible inspection.

3.8 RECYCLING OF BUILDING MATERIALS

A. The Contractor is responsible for any required testing and for the ultimate reuse of materials generated from the Work of this section. These materials include any painted building components.

B. The Contractor may salvage metal building components and mechanical equipment with lead paint. The equipment must be sent to a properly licensed salvage company and the salvage company must be notified in writing of the presence of lead paint on the salvage components.

Copies of signed acknowledgement documents must be submitted to the 92 CONS Contracting Officer.

3.9 DISPOSAL/TREATMENT

A. The Contractor is responsible for any required testing and for arranging for the ultimate off-site recycling and/or disposal of all waste generated from the Work of this section. This waste may include, but is not limited to lead paint chips, wastewater, and dust from HEPA filters and from damp sweeping, solvents and caustics used in any stripping process, wash water, disposable work clothes and respirator filters.

B. The Contractor shall provide results of all testing conducted of the waste materials to the 92

CONS Contracting Officer.

C. Disposal/Treatment of Lead Contaminated Material.

1. The Contractor must comply fully with all federal, state and local regulations concerning the testing, handling, hauling, labeling, and disposal of all lead paint waste (i.e., paint chips, wastewater, disposable protective clothing, polyethylene sheeting, etc.) generated during this project.

a. At a minimum, the Contractor shall collect and submit samples to an AIHA Certified

Laboratory for TCLP analysis (EPA Method 1311 in accordance with Appendix II of 40 CFR 261). The Contractor shall collect and analyze at least one sample from each media scheduled for disposal. The Contractor is advised that additional testing may be required by the disposal facility and it is the Contractor’s responsibility to determine the types and

1021.10 028301 - 14 quantity of testing required. All expenses for sample collection and analysis shall be incurred by the Contractor.

b. All visible paint and painted debris shall be removed from the ground surface within and surrounding the work site prior to building demolition. All paint and painted debris material shall be tested and properly disposed off-site.

c. Lead-containing material that meets the characteristics of a hazardous waste (i.e., lead

TCLP standard is 5 mg/L), or by “definition” is a hazardous waste, shall be disposed or treated in accordance with applicable hazardous waste regulations.

D. For all other lead waste (chips, lead dust, waste water, filters, solvents, work clothes, etc.), the Contractor shall store waste in appropriate, compatible containers/drums for disposal as hazardous waste and shall be labeled and stored in accordance with all applicable regulations.

The Contractor shall also submit to the FAFB 92 CONS Contracting Officer the name, address and proof of permit for the recycling/disposal facility that has agreed to accept the containerized lead waste at least 5 days prior to shipment.

E. The Contractor is responsible for completing all disposal documents, which may include, but are not limited to, waste profiles, hazardous waste manifests and land ban restriction forms. Fairchild Air Force Base shall be designated at the Generator on all documents and shall sign the documents as such. Note that Fairchild AFB is registered as a generator of hazardous waste under several EPA ID numbers; the Contractor shall 92 CONS Contracting Officer for the appropriate EPA# and Generator status. Copies of all disposal documents shall be delivered to the 92 CONS Contracting Officer and for review at least 5 days prior to shipment. Coordination for the 92 CONS Contracting Officer/Generator’s signature on hazardous waste disposal documents shall be made through the 92 CONS Contracting Officer.

F. For lead waste that is being shipped and disposed of using a hazardous waste manifest, the

Contractor shall provide the bottom three copies of the manifest to the Fairchild AFB 92 CONS Contracting Officer at the time of shipment for distribution to the appropriate agencies.

END OF SECTION 028301