Answers to Contractors questions during SABER Pre-Bid Conference.docx

DOCX document 13 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER)
Solicitation number
FA4608-11-R-0020
Issued by

About this file

Attached are the Answers to the contractors questions during the SABER Pre-Bid Conference.

View the file

Other files

File Type Posted
Amendment 1.pdf PDF
Attachment 6 - Insurance.doc DOC document
Attachment 4 - Wage Determination Building LA10.doc DOC document
Attachment 5 - AF66.doc DOC document
Attachment 4A - Wage Determination HEAVY LA2.docx DOCX document
Attachment 4B - Wage Determination HIGHWAY LA13.docx DOCX document
Attachment 2 - Environmental.doc DOC document
Attachment 3 - BAFBI 33-2.doc DOC document
Attachment 10 - Past Performance Survey.docx DOCX document
Official SABER Solicitation.pdf PDF
Attachment 7 - Storm Water.doc DOC document
Attachment 8 - AFI 32-1001.doc DOC document
Attachment 1 - Revised SOW 29 Apr 2011.doc DOC document
Attachment 9 - Reservation Form.doc DOC document
SABER Pre-Proposal Conference Sing in Sheet.pdf PDF
Pre-Bid Conference Slide - 29 July 2011.pdf PDF
Attachment 1 - Revised SOW 29 Apr 2011.doc DOC document
Attachment 8 - AFI 32-1001.doc DOC document
SABER Draft Solicitation.doc DOC document
Attachment 7 - Storm Water.doc DOC document
Attachment 6 - Insurance.doc DOC document
Attachment 4 - Wage Determination.doc DOC document
Attachment 3 - BAFBI 33-2.doc DOC document
Attachment 9 - Reservation Form.doc DOC document
Attachment 10 - Past Performance Survey.docx DOCX document
Attachment 5 - AF66.doc DOC document
Attachment 2 - Environmental.doc DOC document
Pre Solicitation Notice modification 1.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Answers to Contractors questions during SABER Pre-Bid Conference 29 July 2011

1. Award Date- What is the anticipated award date?

Answer: Anticipating January 1, 2012 but it could be later. The date depends on how long the approval from AFGSC takes.

2. 4Clicks- Is this something we purchase or it available on a Government website?

Answer: This program can be purchased directly from the manufacture on the web (http://www.4clicks.com/). 4Clicks uses R.S. MEANS system. The 4Clicks program offers good features for the Government and easy to use. The contractor has to provide the software to the Government and provide training. One benefit will be that only those involved with SABER will have access to the program.

3. Office Space- Is the Air Force providing space to be leased or does the contractor have to provide a trailer or temp office?

Answer: Yes, the Government will provide a space (lay down area). The contractor is responsible for providing their own trailer and connections to utilities. The Government will provide utilities for the sight.

4. Forth Coming Projects- Can you give an example of forthcoming projects?

Answer: Currently there are no seed projects. At the time of award there will be a project for 2K. We are looking at projects made up of multiple trades. Just keep in mind that the contractor awarded the contract will need to ensure they can handle more than one job at a time, have enough superintendents and subcontractors.

5. Bonding- Will bonding be released as a percentage of completion of projects?

Answer: Bonding is required for task-orders over $30K. The Government will receive bonding for each task order even, which could be multiple task orders simultaneously.

6. PowerPoint- Are we able to get a copy of the PowerPoint?

Answer: Yes, a copy of the PowerPoint will be posted on FedBizOps.

7. Attendees- Can we have a list of attendees?

Answer: Yes, a list of attendees will be posted on FedBizOps.

8. Past Performance- The past performance were to at your office by 27 July 11, has the date been extended?

Answer: Yes, the Past Performance due date will be extended.

9. Bonding- What is the maximum bonding capacity for this project?

Answer: The number of task orders issued will dictate the amount of bonding needed.