Attachment 16 - Sample Project SOW Misc. Repair.pdf

PDF 206 KB Posted

Attached to
Facility Enhancement and Maintenance IDIQ
Solicitation number
FA441827R0001
Issued by

About this file

This is a Statement of Work (SOW) for a mechanical system replacement task under the Facility Enhancement & Maintenance IDIQ (FEM) contract vehicle.

The work involves the replacement of one hydronic Air Handling Unit (AHU-1, designated "Rookies") located in the attic of Building 325 at Joint Base Charleston, South Carolina (100 Hill Blvd.). The project is scheduled for November 2026. The contractor must provide all labor, materials, equipment, tools, transportation, and storage necessary to complete the work. The demolition phase requires removal of the existing AHU-1 including all associated hydronic piping back to isolation valves, control valves, dampers, actuators, and AHU controls. The new work phase specifies installation of a replacement AHU with the following performance specifications: 3,300 CFM supply capacity, 2,150 CFM outside air capacity, 230,400 BTUH cooling capacity, and 113,700 BTUH heating capacity. The new AHU must include a native BACnet controller integrated with the existing Building Management System, a Variable Frequency Drive (VFD) with direct drive fan assembly rated at maximum 60Hz, chilled water specifications of 45°F entering water temperature with 10°F temperature differential, hot water specifications of 140°F entering water temperature with 20°F temperature differential, and 460V/3-phase electrical service. The GPM valve requirement is 46.2.

View the file

Other files

File Type Posted
Attachment 1 - Statement of Work (4 Nov 26).pdf PDF
Attachment 22 - UFGS 01 33 29 Sustainability Requirements and Reporting.pdf PDF
Attachment 28 - SCA WD 2015-4439 Rev 31 - Sumter.pdf PDF
Attachment 27 - SCA WD 2015-4463 Rev 36 - Orangeburg.pdf PDF
Attachment 18 - Sample Project Price Worksheet.xlsx XLSX spreadsheet
Attachment 21 - JBLG Integrated Solid Waste Management Plan.pdf PDF
Solicitation Amendment - FA441827R00010001.pdf PDF
Attachment 2 - Price List - Schedule B.xlsx XLSX spreadsheet
Attachment 24 - UFGS 01 57 19 Temporary Environmental Controls.pdf PDF
Attachment 25 - Tier I Carpet Vendors.pdf PDF
Attachment 29 - 27R0001 Questions and Answers.pdf PDF
Attachment 19 - Section L Offeror Instructions.pdf PDF
Attachment 26 - SCA WD 2015-4427 Rev 35 - Berkeley Charelston Dorchester.pdf PDF
Attachment 23 - UFGS 01 74 19 - Construction Waste Management and Disposal.pdf PDF
Solicitation Amendment FA441827R00010001 SF 30.pdf PDF
Attachment 13 - USAF Carpet Ordering Guide - 2023.pdf PDF
Attachment 10 - JB CHS Approved Paint Colors.pdf PDF
Attachment 9 - Contract Security Handbook.pdf PDF
Attachment 4 - SC20260022 Berkeley.pdf PDF
Attachment 8 - PPQ.pdf PDF
Attachment 3 - SC20260016 Orangeburg.pdf PDF
Attachment 14 - Sample Project SOW (Floorcovering).pdf PDF
Attachment 20 - Evaluation Factors (Section M).pdf PDF
Attachment 17 - Sample Project - AB B325 Floorplans.pdf PDF
Attachment 11 - Technical Exhibit for Base Signage.pdf PDF
Attachment 5 - SC20260023 Charleston.pdf PDF
Attachment 7 - SC20260030 Sumter.pdf PDF
Attachment 15 - Sample Project SOW (Protective Coating).pdf PDF
Attachment 6 - SC20260024 Dorchester.pdf PDF
Attachment 12 - UFC Protective Coatings and Paints.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Facility Enhancement & Maintenance IDIQ (FEM)

MAINTENANCE & REPAIRS

Building 325 – Air Base Commons

100 Hill Blvd., Joint Base Charleston, SC November 2026

GENERAL: The work to be performed is a mechanical system replacement of an Air Handler Unit. The contractor shall provide all labor, materials, equipment, tools, transportation, and storage for this mechanical system replacement work requested. (Section 3.2)

LOCATION: Building 325, 100 Hill Blvd., Joint Base Charleston, SC.

SCOPE OF WORK: The work includes replacement of one (1) hydronic Air Handling Units in the attic.

DEMO

1) Demo 1 ea. existing AHU-1 (Rookies)

a) Include all hydronic piping back to the isolation valves for the AHU.

b) Include control valves, dampers and actuators associated with the AHU.

c) Include AHU controls associated with each AHU.

NEW WORK

1) Provide and Install 1 new AHU with the following capacities:

• Include native BacNet controller and integrate with existing BMS system

• Include VFD with direct drive fan assembly, max 60hz for rated CFM

• Chilled Water: 45° EWT, 10° △T

• Hot Water: 140° EWT, 20° △T

• Electrical: 460V/3ø

-End-

AHU-1

Supply CFM 3300

OA CFM 2150

Cool Total

BTUH

230,400

GPM/Valve 46.2 Heat Total

BTUH

113,700