This is a Statement of Work for a floorcovering project under the Facility Enhancement & Maintenance IDIQ (FEM) contract vehicle. The work involves the removal and installation of approximately 8,028 square feet of floor covering at Building 325, Air Base Commons, located at 100 Hill Blvd., Joint Base Lindsey Graham, South Carolina, with a project date of June 2026.

The contractor shall provide all labor, materials, equipment, tools, transportation, and storage necessary to complete the work. Primary scope items include: (1) lifting and relocating approximately one system furniture piece (Removable Stage) and removing approximately 8,028 square feet of existing floor covering; (2) preparing the floor to acceptable industry standards, including ensuring subflooring is smooth, true, and level, and repairing any holes, cracks, depressions, or rough areas using materials recommended by the floorcovering or adhesive manufacturer; and (3) providing and installing new carpet tiles with adhesive covering 892 square yards in the Magnolia Ballroom, with samples provided for customer selection. The contractor must adhere to all applicable federal, state, and local regulations, commercial practices, and manufacturer specifications. Work areas may remain occupied by employees during execution, and the contractor must employ safe work practices, prevent damage to wall surfaces during removal, use low volatile organic compound (VOC) materials, maintain proper ventilation, and keep the work area clean daily.

View the file

Other files

File Type Posted
Attachment 1 - Statement of Work (4 Nov 26).pdf PDF
Attachment 22 - UFGS 01 33 29 Sustainability Requirements and Reporting.pdf PDF
Attachment 28 - SCA WD 2015-4439 Rev 31 - Sumter.pdf PDF
Attachment 16 - Sample Project SOW Misc. Repair.pdf PDF
Attachment 27 - SCA WD 2015-4463 Rev 36 - Orangeburg.pdf PDF
Attachment 18 - Sample Project Price Worksheet.xlsx XLSX spreadsheet
Attachment 21 - JBLG Integrated Solid Waste Management Plan.pdf PDF
Solicitation Amendment - FA441827R00010001.pdf PDF
Attachment 2 - Price List - Schedule B.xlsx XLSX spreadsheet
Attachment 24 - UFGS 01 57 19 Temporary Environmental Controls.pdf PDF
Attachment 25 - Tier I Carpet Vendors.pdf PDF
Attachment 29 - 27R0001 Questions and Answers.pdf PDF
Attachment 19 - Section L Offeror Instructions.pdf PDF
Attachment 26 - SCA WD 2015-4427 Rev 35 - Berkeley Charelston Dorchester.pdf PDF
Attachment 23 - UFGS 01 74 19 - Construction Waste Management and Disposal.pdf PDF
Solicitation Amendment FA441827R00010001 SF 30.pdf PDF
Attachment 13 - USAF Carpet Ordering Guide - 2023.pdf PDF
Attachment 10 - JB CHS Approved Paint Colors.pdf PDF
Attachment 9 - Contract Security Handbook.pdf PDF
Attachment 4 - SC20260022 Berkeley.pdf PDF
Attachment 8 - PPQ.pdf PDF
Attachment 3 - SC20260016 Orangeburg.pdf PDF
Attachment 20 - Evaluation Factors (Section M).pdf PDF
Attachment 17 - Sample Project - AB B325 Floorplans.pdf PDF
Attachment 11 - Technical Exhibit for Base Signage.pdf PDF
Attachment 5 - SC20260023 Charleston.pdf PDF
Attachment 7 - SC20260030 Sumter.pdf PDF
Attachment 15 - Sample Project SOW (Protective Coating).pdf PDF
Attachment 6 - SC20260024 Dorchester.pdf PDF
Attachment 12 - UFC Protective Coatings and Paints.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Facility Enhancement & Maintenance IDIQ (FEM)

FLOORCOVERING

Building 325 – Air Base Commons

100 Hill Blvd., Joint Base Lindsey Graham, SC June 2026

GENERAL: The work to be performed is the removal and installation of approximately 8,028 square feet of floor covering. The contractor shall provide all labor, materials, equipment, tools, transportation, and storage for floor covering materials to perform removal and replacement of floor covering, including furniture relocation.

LOCATION: Building 325, 100 Hill Blvd., Joint Base Lindsey Graham, SC.

SCOPE OF WORK: The work includes but is not limited to the following items:

1. Contractor shall lift and relocate existing furniture and appliances to facilitate the installation of the new materials. (Section 3.1.1)

a. Relocate approx. 1 ea. system furniture – Removable Stage.

b. Remove approx. 8,028 sq. ft. of floor covering. (Section 3.1.2)

2. Contractor shall prepare the floor to acceptable industry standard as per new floor covering requirements. (Section 3.1.3)

a. Subflooring shall be in a smooth, true, level plane, except where indicated as sloped.

b. Repair holes, cracks, depressions, or rough areas using material recommended by the floorcovering or adhesive manufacturer.

c. Any necessary preparation and compliance with industry standards and manufacturer recommendations shall be the responsibility of the contractor.

3. Contractor shall provide and install new carpet tiles in the identified areas.

Samples will be provided so the customer can make selections. (Section 3.1.4)

a. Installation of 892 sq.yds. carpet tiles w/adhesive in Magnolia Ballroom.

Applicable Instructions:

Work areas may be occupied by the employees while work is being accomplished.

Caution must be taken to ensure all safe work practices are adhered to.

Caution shall be taken to prevent damage to the wall surfaces during removal process.

All work shall be in accordance with applicable federal, state, and local regulations, specifications, commercial practices, manufacture specifications, and industry standards. Low VOC materials shall be used, and work areas shall be well ventilated. Contractor shall keep a clean work area daily.

--End--