This file contains Combined Request for Information (RFI) responses with answers related to the demolition of Building 90326 (Reef Dining Facility) at Hurlburt Field, Florida. The solicitation is issued under Sealed Bid procedures (FAR Part 14) and FAR Part 36 for Construction and Architect-Engineer Contracts, with a bid opening date of April 30, 2026 at 2:00 PM Central Standard Time. The contract is a single-award, Firm-Fixed-Price agreement where the contractor must furnish all labor, materials, tools, supervision, and other items necessary to complete the demolition work. The Performance Period is 240 days, with work commencing at Notice to Proceed following contract award.

The scope includes demolition of the main building structure and foundation; removal of all electrical cables, communications cabling (back to point of origin or nearest manhole), transformers, DDC controls, and fire alarm systems; disconnection and capping of utilities (water, sewer, gas, electrical); removal of all trees, shrubbery, and site plants with site re-grassing; construction of replacement sidewalks (approximately 1,092–1,310 square feet) and curbing (70 linear feet); removal and proper disposal of asbestos-containing materials (ACM), lead-based paint (LBP), and contaminated soils; and site restoration including refurbishment of stormwater inlets and final grading. The contractor owns salvage rights to all remaining materials and equipment, except the HVAC chiller and freezer which the Government will remove. Hazardous materials abatement must follow NESHAP requirements and Florida administrative code. A January 2009 survey will be provided to bidders, with contractors responsible for verifying dimensions and discovering unforeseen hazardous materials. Key contacts include CE Gary Billow for utilities, CE Mike Disney for utility location coordination (Form 103), and the Base Recycling Center (850-884-7577). Utilities including water for wet demolition are provided at no cost to the contractor; a backflow preventer is required. A bid bond is required per Section L. As-built drawings and CAD drawings are available but too large for attachment; offerors should request access via DoD Safe Link email. The contractor must assume zero weather days when creating the project schedule and secure Environmental Permits and other required local/state permits prior to work commencement.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs

Section ReferencedContractor Question or RecommendationGovernment ResponseCategory
SOW; Para.1.3Please provide more information about the transformers including which shall remain in place, whether they serve only this building, whether any transformers should be removed, and which ones if so.The contractor shall coordinate with CE Electric Shop and CE Gary Billow to have electric service disconnected from transformers; contractor will then remove all remaining electrical cables.Demolition Scope
Please clarify the extent of demolition for communications cabling (copper, fiber). Shall all communications be demolished back to the point of origin, such as a site pedastal, pull box, etc?Yes, all communications be demolished back to the point of origin or nearest comm. manhole or workhole, by the contractor.Demolition Scope
Have all materials intended to be salvaged by the Govt or Hurlburt been disconnected and removed? If not Please clarify what equipment/ furnishings will remain inside the building and when all other items will be removed.Yes, the customer will remove anything they want/need and CE functionals will and Comm will remove all the equipment/cables they want before your start work. This includes the HVAC chiller, freezer-removed that will be removed by the Government. Anything remaining equipment/furnishings will become the property of the contractor for legal disposal, reuse, or resale by the contractor, with the following exceptions: If the contractor discovers any discrepancies, the Contracting Officer shall be notified.Demolition Scope
Meeting minutes appear to indicate limitations on the extent of demolition of sidewalks and driveways. Please clarify limits of demolition for all hardscape to include asphalt/ concrete paving, sidewalks, curbs, etc.As-built drawings will be provided to propspective bidders. Please be aware the as-builts may not accurately reflect the current condictions of the building. The contractor will be responsible for verifying any questionable dimensitons or installation to safely and correctly perform IAW the PWS and contract. New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs.Demolition Scope
Is the back up fuel cell part of the scope of work to be removed?The fuel tank for the back-up generator will be removed before the NTP of this project.Demolition Scope
The drawings included in the Solicitation are not scalable and cannot be enlarged without being pixelated. Are up to date as-built drawings available for existing site utilities in and around the site, structural, Mech, Electr, Plumbing drawings as well as a final site drawing indicating final grades/ slopes, swales, for final grading and location/ configuration of new sidewalks (1092 sf) and curbing (182LF) as noted in the Solicitation. Please specify any/ all site features that should remain or that will need to be protected (trees, sidewalks, curbs, asphalt, etc).As-built drawings will be provided to prospective bidders. Please be aware the as-builts may not accurately reflect the current conditions of the building. The contractor will be responsible for verifying any questionable dimensions or installation to safely and correctly perform IAW the PWS and contract. New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs. Site trees, shrubbery, and plants will be removed and site will be re-grassed per PWS.Drawings / Plans
Solicitation & SOWThe Section C and text in SF 1447 Block 10 include, in two locations each, text that reads: "provide drawings, reports as required in PWS Sated 31 Jan 2026." However, the referenced SOW dated 31 January 2026 does not mention any required drawings to be provided by the contractor. It does state "The Contractor shall confine activities to areas defined by the drawings and specifications". Please provide these referenced drawings and specifications.Section B description includes "Drawings", this wording was deleted from the soliciation. Clauses 52.236-21 and 52.236-1 Alt 1 - are required for Construction Contracts. However if drawings are needed at a later date they will be included as a Addendum and with discussion between the Contractor and the Govt to determine what is needed and any additional costs.Drawings / Plans
SOW; Para.1.2Please provide a drawing showing the limits of the construction (i.e. termination lines for removal of driveway & approaches, extent of removal of sidewalks, site lighting, and etc.) for this project.New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs. Please see as-builts for locations of existing site features.Drawings / Plans
SOW; Para.1.4Please provide a drawing identifying the removed sidewalks and the location for the new sidewalks and curbs.New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs. Please see as-builts for locations of existing site features.Drawings / Plans
SOWPlease provide all utility drawings and include the location to which the contractor is required to remove the existing utilities and cap.To locate utilities, the contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information. As-built drawings will be provided to prospective bidders.Drawings / Plans
SOWPlease confirm the existing concrete block screen on the East side of the building is to be demolished.Yes.General
Has DDC controls been disconnected or is that to be included in the Contractor’s SOW?The DDC controls will be disconnected by NTP.General
Is there any active IDS or security systems within the building? Has this been disconnected or is that to be included in the Contractor’s SOW?No IDS or security systems are known to exist within the building.General
Please provide pictures of the building.We will not be providing pictures. A site visit was held on 24 Mar 26 to allow contractors to take pictures and view the site.General
Please confirm if any specific phasing will be required for the project.Per the PWS, paragraph 1.1 General Description"...Sequences shall include ACM, LBP, and other hazardous materials testing, abatement and legal disposal; demolition of main building, foundation, and site features; test and abatement of site hazardous-containing materials and soils; and site restoration. ..."General
Is the landfill on the base that we can use for C&D waste?No, the contractor to legally dispose of non-hazardous and non-recyclable materials at a licensed C&D landfill off base.General
SOW; Para.1.2Please provide the size and location of the existing grease trap for the kitchen.Contractor to verify after award or during site visit on 24 Mar 26.General
SOW; Para.1.2It was mentioned at the site visit that metals will be disposed of at the base recycling center. Please advise if the base will provide a recycling dumpster and if any dump fees are required.The Recycling Center can be contacted at 850-884-7577 to see what they can offer. It depends on how much metal you are recycling for them to provide a separate dumpster.General
Does the contractor own the salvage rights to the building materials and contents? Please advise.YesGeneral
SOW; Para.3.10.2Please confirm that there are no existing historical, archaeological, and cultural resources within the contractor's work areaNo historical, archeological or cultural items, remains, or conditions are known to be within the confines of this project. If any are discovered during the course of this project, the contractor is to immediately stop work and contact the Contracting Officer for instructions.General
SOW; Para.3.14.2Please confirm air monitoring and CIH inspections are only required during the abatement activities.Yes.General
SOW;Please confirm all existing site concrete from Westfall Cir. North to the building is required to be demolished.Replacement sidewalk is expected to be approximately 1092 SF to 1310 SF. Curb is expected to be approximately 70 LF curb. Amend PWS to 70 LF of curb.General
SOWPlease confirm no asphalt paving, or rework to the existing southside approach is required. Contractor will only sawcut the pavement where it meets the concrete drive on the south side of the building.No asphalt paving will be required, but sidewalks, curb, dumpster pad and dumpster driveway driveway will be replaced.General
SOWPlease advise if the existing refrigerant should be disposed of offsite or at base recycling.Existing refrigerant should be legally disposed of off base. Contractor may confirm with Base Recycling if they will take it: 850 884-7577.General
The bid opening date is noted as April 30, 2026, but it was not evident on what day/ time bids are due to be submitted to the Govt.The solicitation in SAM first page, top right. Current date offers due April 30, 2026 at 3:00 PM CDT. Which will be corrected to reflect the ACTUAL DUE DATE OF 30 April 2026, 2:00 (CST). This is also the date included in Section L, Instructions to Offerors, Paragraph 2.1 - Bid Opening will be conducted at the 1st Special Operations Contracting Squadron Conference Room, located at 350 Tully Street, Bldg. 90039, Hurlburt Field, FL 32544. The bid opening date is 30 April 2026 at 2:00 PM (Central Standard Time).General
Has fire alarm, Monaco, and all FA communications cabling been disconnected or is that to be included in the Contractor’s SOW?The fire alarm, Monaco, and all FA communications cabling will be disconnected by the NTP.General
Are there any remaining communications connections within the building requiring disconnection/ coordination with outside users/ servers?Base Comm. will disconnect building comm. systems before the project NTP.General
Many of these older buildings have Communications 'cross-connections' within them which could disable communications to other areas on base when communications are disconnected at this location. Please clarify if this is the case and how this should be addressed.Building 90326 is not a Comm. Hub. Base Comm. will disconnect building comm. connections before NTP.General
SOW; Para.3.10.2Please confirm that there are no existing historical, archaeological, and cultural resources within the contractor's work area. Will an Archaeologist be required on-site during excavation due to any existing historical, archaeological, or cultural resource limitations?An archaeologist is not expected to be required to be on site during the POP of this project. No historical, archeological or cultural items, remains, or conditions are expected to be encountered with the confines of this project. If any are discovered during the course of this project, the contractor is to immediately stop work and contact the Contracting Officer for instructions.General
Please confirm site supervision required for this project. Will a single "triple-hat" superintendent, QC manager, and SSHO be acceptable to satisfy the contract requirements for supervision?Yes, the Site Superintendent can perform the requirements of Superintendent, SSHO, and QCM.General
Meeting minutes denote ‘Attendees: listed on separate sign-in sheet’. The noted sing-in sheet was not included in the addendum with the meeting minutes. Can/ will the sign-in sheet be provided/ distributed via addendum?The sign in sheet has been included. Interested parties will need to request access to view it.General
Are there any AC units?There are two AC units. One of which will be removed by the shops before NTP. The other will be demo-ed during the project.General
Is the owner removing anything that’s in the buildings at this time?The customer will remove any items they wish to retain no later than 24 April 2026. All materials, equipment, and furnishings will become the property of the contractor for legal disposal, reuse, or resale by the contractor, with the following exceptions: HVAC chiller, freezer-removed by the Government. If the contractor discovers any discrepancies, the Contracting Officer shall be notified.General
What is the extent of backfill for site if any?Match the existing grade on the site as much as possible. Stormwater inlets, one just south of dumpster and one on other side of drive way shall be re-furbished. Refer to as-buillts for grading, any other inlets or stormwater control.General
Instead of stone entry/egress can we use FOD Matts?Any entry/egress means of protecting the site and nearby airfields will need to be submitted and approved.General
Is a Bid Bond required?Yes, per Section L, 4.1. Documents to be considered responsive of the Solicitation - found on page 66 - a bid bond is required.General
It was mentioned recycling is on base what does that mean?The Recycling Center can be contacted at 850-884-7577 to see what they can offer. It depends on how much metal you are recycling for them to provide a separate dumpster.General
SOW; Para.3.18Please confirm no local or state building/demolition permits are required.Refer to PWS and question 40 below.General
What permits need to be pulled if any for this project?Refer to PWS dated 31 Jan 26, Para 1.1 - Environmental Permit will be required. 3.12, Compliance with applicable federal, state and local laws, ordances, codes, rules and regulations. 3.18 Licenses and permits, The contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information.General
Will after hours work be permitted? Weekends?Yes, however the requests will have to be approved 24 hours in advance. Please refer to section 3.6 of the PWSGeneral
SOW; Para.2.2For the project schedule described in SOW paragraph 2.2, are we correct to assume that the format is the Working Time Analysis (WTA) provided as Attachment 3? If not, please clarify desired format.There's no specific form that's required but we've attached a fillable progress schedule PDF for reference as to what we need.General
SOW; Para.2.2Please confirm the contractor should assume no (0) weather days when creating the project schedule.That is correct, please refer to section 3.6 and 3.8 of the PWSGeneral
SOW; Para.1.1 vs. SolicitationThere appears to be a discrepancy regarding the POP duration of the project within the Solicitation documents. Sect. F. denotes 240D (5/1/26 to 12/27/26) as does the Work-Time Analysis. The PWS, however states 334D. Please clarify POP duration as well as whether the POP start date shall coincide with the award date or the NTP.The PoP duration of this project is 240 days. The PWS will be corrected to reflect 240 days. The POP will start at the time of NTP, to be issued by the Contracting Officer after award.General
SOW; Para.1.3We note that the IFB says "Disconnection and capping of building utilities (water, sewer, gas, electrical) are the Contractor's responsibility…." Does the water pipe contain asbestos?Site utilities and piping are not expected to contain ACM. Should any evidence to the contrary present itself, the contractor is to stop work immediately and contact the Contracting Officer for further instruction.Hazardous Materials
SOWAt the site visit, we heard from 1 SOCONS that the soil underneath and surrounding Bldg. 90326 is contaminated and that the expectation is for the contractor to remove and properly dispose of this contaminated soil. Please confirm that this is part of the project scope.That is correct, please refer to section 1.1 of the PWSHazardous Materials
Please confirm no PFAS/ PFOS contaminated soils exist on the project site and that no further testing for PFOS/ PFAS will be required within the scope of this project.No known PFAS/PFOS are expected within the confines of this project. If suspect materials are encountered during the execution of this project, the contractor shall immediately stop work and notify the Contracting Officer.Hazardous Materials
SOW; Para.2.1Block 10 on the SF 1447 and Section C both mention "abatement of site hazardous-containing materials and soil" and Section C also mentions "hazardous materials testing, abatement and legal disposal." We note that the Site Visit Summary states that "asbestos has been identified in the building; surveys for asbestos, lead, and other hazards will be provided. Mr. Javier will provide surveys for asbestos, lead etc." Is it the USAF's expectation that the forthcoming surveys will provide enough information about the type and quantity of hazardous material and contaminated soil for contractors to use for bidding purposes? Uncertainty in this aspect of the scope will increase contractor bids. To reduce this uncertainty, would the USAF provide information and assumptions to support hazardous materials abatement/disposal cost estimates?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available. . If during demolition something different is identified immediately notify the Contractingt officer and we will address with contractor and CE functionals. We cannot provide you an estimate for hazardous materials and disposal cost. We do have a site on base that will accept some items, at no cost, Paint, etc.Hazardous Materials
SOWIn the absence of information that is sufficient to support cost estimates for the transportation and disposal of hazardous materials and contaminated soils, will USAF consider providing plug numbers for transportation & disposal of hazardous materials and contaminated soils so that post-award adjustments can be made via contract modification should the actual waste and soil volumes vary from the basis of estimate?Prospective contractors (bidders) will be responsible for providing their best estimate for transporting and disposal of hazardous materials and contaminated soils.Hazardous Materials
SOWWill the existing above ground fuel tank that previously fed the removed generator be demolished as part of this solicitation or if it will be removed by the Government? Will the Government remove the remaining fuel from the tank? Please advise on this scope for this potential hazardous tank.The customer will remove any items they wish to retain no later than 24 April 2026. Anything left behind will need to be properly removed and/or demolished.Hazardous Materials
SOWPlease confirm geotechnical surveys and surveying are not required.That is correct, geotechnical surveys and surveying are not required.Hazardous Materials
SOWWould the USAF please extend the deadline for questions on this solicitation to a date that is no sooner than one week after the referenced existing soils report and hazardous materials survey report have been released via amendment so that contractors may have the opportunity to submit questions on those findings?Not at this time. If additional issues arise we will assess any delay at that time.Hazardous Materials
In accordance with section 3.11 of the Solicitation, ‘areas known to contain/ not contain Asbestos Containing Materials will be identified to the Contractor’; Please provide any information/ documentation regarding environmental debris including Asbestos Containing Materials, Lead Based Paint, contaminated soils, etc. so these can be quantified for bid purposes.A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available. The asbestos will need to be removed before demo and the waste will be manifested as “Asbestos Containing Material, Demolition Debris”, disposed in Florida permitted Class I or III landfill.
To meet NESHAP requirements, F.A.C 62-204.800/F.A.C Rule 62-257.301 (Notice of Demolition or Asbestos Renovation) adopted and incorporated EPA 40 CFR/Chpt 1/Subpart C/Part 61/Subpart M/Sec. 61.145 – Standard for Demolition and Renovation (Asbestos).Hazardous Materials
Has a pre-demolition hazardous materials survey been completed? If so, can that please be distributed in an addendum?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available.Hazardous Materials
Please provide all abatement surveys that are on file for the building?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if avialable. The asbestos will need to be removed before demo and the waste will be manifested as “Asbestos Containing Material, Demolition Debris”, disposed in Florida permitted Class I or III landfill.
To meet NESHAP requirements, F.A.C 62-204.800/F.A.C Rule 62-257.301 (Notice of Demolition or Asbestos Renovation) adopted and incorporated EPA 40 CFR/Chpt 1/Subpart C/Part 61/Subpart M/Sec. 61.145 – Standard for Demolition and Renovation (Asbestos).Hazardous Materials
Is there an asbestos report or survey for the building?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available.Hazardous Materials
If contractors do a asbestos survey and asbestos is found in the building, will that be considered as a potential change order?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available. If you find something different thann what is in the surveys notify the Contracting Officer and we will assess at that time.Hazardous Materials
Please provide the soil contaminants report that was mentioned at the site visit. How were the contaminants confirmed?The 2009 ACM and LBP survey report indicates the soil under the kitchen containes ACM, and recommended the area be restricted and that it was necessary to encapsulate it within concrete.Hazardous Materials
What happens if additional surveys are necessaryNotify the Contracting Officer immediatley and we will assess with the Functionals if additional sureveys are required and if so, who, Contractor or Govt, will provide them.Hazardous Materials
SOW; Para.3.10.1Please clarify which trees and the extent of landscaping to be removed. Please specify if this includes the large oak trees on the perimeter of the site. Please identify which trees must be protected and saved.All site trees, shrubbery and site plants are to be removed. The site will be re-grassed after slab is demo-ed and contaimnated soils removed and legally disposed.Landscaping
SOWWill there be any requirement for soils compaction? If so, please specify.The contractor to backfill in 6" to 8" lifts, with compaction will required to 90% maximum dry density.Landscaping
SOWAfter demolition is there any requirement for soil import or will this be considered a balanced site? If import is required, would USAF please identify how many CY should be brought onsite?Contractor will be required to replace abated contaminated soils with clean soils. Contaminated soils to be legally disposed of. Contractor is responsible to determine amount to be replaced.Landscaping
SOWWhat is the required final site grading plan?Match the existing grade on the site as much as possible. Stormwater inlets, one just south of dumpster and one on other side of drive way shall be re-furbished. Refer to as-buillts for grading, any other inlets or stormwater control.Landscaping
SOW; Para.1.3We note that the IFB says "Disconnection and capping of building utilities (water, sewer, gas, electrical) are the Contractor's responsibility…." If known, please provide the depth of these utilities to support contractor pricing?Site utilities are expected to be located at 3' to 3.5' from surface. Contractor is expected to verify utilities. As-built drawings will be provided to prospective bidders for building information. The contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information.Utilities
SOW; Para.1.3Please clarify all utility providers and contact information – Power, Water, Sewer, Comm. Please confirm that water, sewer, electric, and communication utilities are all owned by the base and would be shut down by 1SOCES.The contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information. All utilities provided by Hurlburt Field, with exception of gas (owned by Okaloosa Gas) and external Cox Cable (owned by Cox Cable.).Utilities
SOW; Para.1.5; 3.10.3.5Paragraph 1.5 specifies watering, as required, for 60 days. Paragraph 3.10.3.5 states potable water may not be used for irrigation systems. Are there existing irrigation lines/systems available (with non-potable water) that can be used at no cost for the required watering? Would 1 SOCES please elaborate on their expectations/requirements for the watering systems (temporary or permanent) included in this project's scope?Irrigation piping may be exiting on the site, but are non-functioning and shall be removed. Water is available at the site at no charge to the contractor. Contractor is to utilize backflow preventer and coordinate with CE Gary Billow.Utilities
SOW; Para.1.3If gas lines are part of the demolition or capping scope, are we correct to assume that Okaloosa Gas is the company required to do this work?Capping the gas lines is a part of the scope. That is correct, it is "owned" by Okalossa GasUtilities
SOW; Para.3.10.3Please advise the extent of the stormwater and erosion control expected. Only around the perimeter and surrounding existing inlets?Match the existing grade on the site as much as possible. Stormwater inlets, one just south of dumpster and one on other side of drive way shall be re-furbished. Refer to as-buillts for any other inlets or stormwater control.Utilities
SOWStatement of work states demolition should be wet. Please advise whether the contractor may use potable water, at no cost, to wet the site.Water will be provided by Hurlburt Field for contractor use at no charge to the contractor. A backflow preventer will be utilized.Utilities
SOWPlease confirm grading for sheet flow should direct water on the Southside of the building to the existing storm catch basin located the curb near west fall circle.Yes. Existing catch basin and inlet will need refurbishing.Utilities
Please clarify if the chilled water piping serving the AHU originates within the perimeter of the project or if the chilled water is served from a central chiller plant outside of the project perimeter. If served from outside the project perimeter, please clarify the limit of demolition for chilled water piping and location of isolation valve.Yes, the chilled water piping is served by a central chiller plant outside of the project perimeter. The contractor will be will be responsible to isolate the building piping during the project with existing isolation valves.Utilities
Please clarify which underground utilities Hurlburt will locate/ identify (Primary power, secondary power, sanitary, domestic water, chilled water, hot water, steam, communications, etc). Please include any other utilities that may be existing, passing through this project site that we may need to be aware of.The contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information. All utilities provided by Hurlburt Field, with exception of gas (owned by Okaloosa Gas) and external Cox Cable (owned by Cox Cable.).Utilities
Please provide the location of closest water supply we can have access to perform the wet demolition.Water is available on the site. A backflow preventer is required to be utilized. Contact Gary Billow at CE to arrange water connection.Utilities
Please confirm the electrical utility connection location and runs from each building.The contractor will be responsible for locating and verifying utilites' locations. To locate utilites, the contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordiate with CE POC Mike Disney for more information. As-built drawings will be provided to propspective bidders for building information.Utilities
Is power and water available at no additional charge?Yes, Utilities are available at the site free of charge. Backflow prevention is required for water.Utilities

Demolition Scope

Section ReferencedContractor Question or RecommendationGovernment ResponseCategory
SOW; Para.1.3Please provide more information about the transformers including which shall remain in place, whether they serve only this building, whether any transformers should be removed, and which ones if so.The contractor shall coordinate with CE Electric Shop and CE Gary Billow to have electric service disconnected from transformers; contractor will then remove all remaining electrical cables.Demolition Scope
Please clarify the extent of demolition for communications cabling (copper, fiber). Shall all communications be demolished back to the point of origin, such as a site pedastal, pull box, etc?Yes, all communications be demolished back to the point of origin or nearest comm. manhole or workhole, by the contractor.Demolition Scope
Have all materials intended to be salvaged by the Govt or Hurlburt been disconnected and removed? If not Please clarify what equipment/ furnishings will remain inside the building and when all other items will be removed.Yes, the customer will remove anything they want/need and CE functionals will and Comm will remove all the equipment/cables they want before your start work. This includes the HVAC chiller, freezer-removed that will be removed by the Government. Anything remaining equipment/furnishings will become the property of the contractor for legal disposal, reuse, or resale by the contractor, with the following exceptions: If the contractor discovers any discrepancies, the Contracting Officer shall be notified.Demolition Scope
Meeting minutes appear to indicate limitations on the extent of demolition of sidewalks and driveways. Please clarify limits of demolition for all hardscape to include asphalt/ concrete paving, sidewalks, curbs, etc.As-built drawings will be provided to propspective bidders. Please be aware the as-builts may not accurately reflect the current condictions of the building. The contractor will be responsible for verifying any questionable dimensitons or installation to safely and correctly perform IAW the PWS and contract. New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs.Demolition Scope
Is the back up fuel cell part of the scope of work to be removed?The fuel tank for the back-up generator will be removed before the NTP of this project.Demolition Scope

Drawings & Plans

Section ReferencedContractor Question or RecommendationGovernment ResponseCategory
The drawings included in the Solicitation are not scalable and cannot be enlarged without being pixelated. Are up to date as-built drawings available for existing site utilities in and around the site, structural, Mech, Electr, Plumbing drawings as well as a final site drawing indicating final grades/ slopes, swales, for final grading and location/ configuration of new sidewalks (1092 sf) and curbing (182LF) as noted in the Solicitation. Please specify any/ all site features that should remain or that will need to be protected (trees, sidewalks, curbs, asphalt, etc).As-built drawings will be provided to prospective bidders. Please be aware the as-builts may not accurately reflect the current conditions of the building. The contractor will be responsible for verifying any questionable dimensions or installation to safely and correctly perform IAW the PWS and contract. New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs. Site trees, shrubbery, and plants will be removed and site will be re-grassed per PWS.Drawings / Plans
Solicitation & SOWThe Section C and text in SF 1447 Block 10 include, in two locations each, text that reads: "provide drawings, reports as required in PWS Sated 31 Jan 2026." However, the referenced SOW dated 31 January 2026 does not mention any required drawings to be provided by the contractor. It does state "The Contractor shall confine activities to areas defined by the drawings and specifications". Please provide these referenced drawings and specifications.Section B description includes "Drawings", this wording was deleted from the soliciation. Clauses 52.236-21 and 52.236-1 Alt 1 - are required for Construction Contracts. However if drawings are needed at a later date they will be included as a Addendum and with discussion between the Contractor and the Govt to determine what is needed and any additional costs.Drawings / Plans
SOW; Para.1.2Please provide a drawing showing the limits of the construction (i.e. termination lines for removal of driveway & approaches, extent of removal of sidewalks, site lighting, and etc.) for this project.New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs. Please see as-builts for locations of existing site features.Drawings / Plans
SOW; Para.1.4Please provide a drawing identifying the removed sidewalks and the location for the new sidewalks and curbs.New sidewalks and curbing to be located near street to extend to neighboring sites' existing sidewalk and curbs. Please see as-builts for locations of existing site features.Drawings / Plans
SOWPlease provide all utility drawings and include the location to which the contractor is required to remove the existing utilities and cap.To locate utilities, the contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information. As-built drawings will be provided to prospective bidders.Drawings / Plans

General

Section ReferencedContractor Question or RecommendationGovernment ResponseCategory
SOWPlease confirm the existing concrete block screen on the East side of the building is to be demolished.Yes.General
Has DDC controls been disconnected or is that to be included in the Contractor’s SOW?The DDC controls will be disconnected by NTP.General
Is there any active IDS or security systems within the building? Has this been disconnected or is that to be included in the Contractor’s SOW?No IDS or security systems are known to exist within the building.General
Please provide pictures of the building.We will not be providing pictures. A site visit was held on 24 Mar 26 to allow contractors to take pictures and view the site.General
Please confirm if any specific phasing will be required for the projectPer the PWS, paragraph 1.1 General Description"...Sequences shall include ACM, LBP, and other hazardous materials testing, abatement and legal disposal; demolition of main building, foundation, and site features; test and abatement of site hazardous-containing materials and soils; and site restoration. ..."General
Is the landfill on the base that we can use for C&D waste?No, the contractor to legally dispose of non-hazardous and non-recyclable materials at a licensed C&D landfill off base.General
SOW; Para.1.2Please provide the size and location of the existing grease trap for the kitchen.Contractor to verify after award or during site visit on 24 Mar 26.General
SOW; Para.1.2It was mentioned at the site visit that metals will be disposed of at the base recycling center. Please advise if the base will provide a recycling dumpster and if any dump fees are required.The Recycling Center can be contacted at 850-884-7577 to see what they can offer. It depends on how much metal you are recycling for them to provide a separate dumpster.General
Does the contractor own the salvage rights to the building materials and contents? Please advise.YesGeneral
SOW/3.10.2Please confirm that there are no existing historical, archaeological, and cultural resources within the contractor's work areaNo historical, archeological or cultural items, remains, or conditions are known to be within the confines of this project. If any are discovered during the course of this project, the contractor is to immediately stop work and contact the Contracting Officer for instructions.General
SOW; Para.3.14.2Please confirm air monitoring and CIH inspections are only required during the abatement activities.Yes.General
SOW;Please confirm all existing site concrete from Westfall Cir. North to the building is required to be demolished.Replacement sidewalk is expected to be approximately 1092 SF to 1310 SF. Curb is expected to be approximately 70 LF curb. Amend PWS to 70 LF of curb.General
SOWPlease confirm no asphalt paving, or rework to the existing southside approach is required. Contractor will only sawcut the pavement where it meets the concrete drive on the south side of the building.No asphalt paving will be required, but sidewalks, curb, dumpster pad and dumpster driveway driveway will be replaced.General
SOWPlease advise if the existing refrigerant should be disposed of offsite or at base recycling.Existing refrigerant should be legally disposed of off base. Contractor may confirm with Base Recycling if they will take it: 850 884-7577.General
The bid opening date is noted as April 30, 2026, but it was not evident on what day/ time bids are due to be submitted to the Govt.The solicitation in SAM first page, top right. Current date offers due April 30, 2026 at 2:00 PM CST. Also refer to Section L, Instructions to Offerors, Paragraph 2.1 - Bid Opening will be conducted at Bid opening will be conducted at the 1st Special Operations Contracting Squadron Conference Room, located at 350 Tully Street, Bldg. 90039, Hurlburt Field, FL 32544. The bid opening date is 30 April 2026 at 2:00 PM (Central Standard Time).General
Has fire alarm, Monaco, and all FA communications cabling been disconnected or is that to be included in the Contractor’s SOW?The fire alarm, Monaco, and all FA communications cabling will be disconnected by the NTP.General
Are there any remaining communications connections within the building requiring disconnection/ coordination with outside users/ servers?Base Comm. will disconnect building comm. systems before the project NTP.General
Many of these older buildings have Communications 'cross-connections' within them which could disable communications to other areas on base when communications are disconnected at this location. Please clarify if this is the case and how this should be addressed.Building 90326 is not a Comm. Hub. Base Comm. will disconnect building comm. connections before NTP.General
Are there any known existing historical, archeological or cultural resources within the perimeter boundary of the affected site?No historical, archeological or cultural items, remains, or conditions are known to be within the confines of this project. If any are discovered during the course of this project, the contractor is to immediately stop work and contact the Contracting Officer for instructions.General
SOW/3.10.2Please confirm that there are no existing historical, archaeological, and cultural resources within the contractor's work area. Will an Archaeologist be required on-site during excavation due to any existing historical, archaeological, or cultural resource limitations?An archaeologist is not expected to be required to be on site during the POP of this project. No historical, archeological or cultural items, remains, or conditions are expected to be encountered with the confines of this project. If any are discovered during the course of this project, the contractor is to immediately stop work and contact the Contracting Officer for instructions.General
Please confirm site supervision required for this project. Will a single "triple-hat" superintendent, QC manager, and SSHO be acceptable to satisfy the contract requirements for supervision?Yes, the Site Superintendent can perform the requirements of Superintendent, SSHO, and QCM.General
Meeting minutes denote ‘Attendees: listed on separate sign-in sheet’. The noted sing-in sheet was not included in the addendum with the meeting minutes. Can/ will the sign-in sheet be provided/ distributed via addendum?The sign in sheet has been included. Interested parties will need to request access to view it.General
Are there any AC units?General
Is the owner removing anything that’s in the buildings at this time?The customer will remove any items they wish to retain no later than 24 April 2026. All materials, equipment, and furnishings will become the property of the contractor for legal disposal, reuse, or resale by the contractor, with the following exceptions: HVAC chiller, freezer-removed by the Government. If the contractor discovers any discrepancies, the Contracting Officer shall be notified.General
What is the extent of backfill for site if any?Match the existing grade on the site as much as possible. Stormwater inlets, one just south of dumpster and one on other side of drive way shall be re-furbished. Refer to as-buillts for grading, any other inlets or stormwater control.General
Instead of stone entry/egress can we use FOD Matts?Any entry/egress means of protecting the site and nearby airfields will need to be submitted and approved.General
Is a Bid Bond required?Per Section L, 4.1. Documents to be considered responsive of the Solicitation - found on page 66 - yes a bid bond is required.General
It was mentioned recycling is on base what does that mean?The Recycling Center can be contacted at 850-884-7577 to see what they can offer. It depends on how much metal you are recycling for them to provide a separate dumpster.General
SOW; Para.3.18Please confirm no local or state building/demolition permits are required.Refer to PWSGeneral
What permits need to be pulled if any for this project?Refer to PWS dated 31 Jan 26, Para 1.1 - Environmental Permit will be required. 3.12, Compliance with applicable federal, state and local laws, ordances, codes, rules and regulations. 3.18 Licenses and permits, The contractor will be required to file Form 103, Dig Permit and Sunshine Notification (800-432-4770) and coordinate with CE POC Mike Disney for more information.General
Will after hours work be permitted? Weekends?Yes, however the requests will have to be approved 24 hours in advance. Please refer to section 3.6 of the PWSGeneral
SOW; Para.2.2For the project schedule described in SOW paragraph 2.2, are we correct to assume that the format is the Working Time Analysis (WTA) provided as Attachment 3? If not, please clarify desired format.There's no specific form that's required but we've attached a fillable progress schedule PDF for reference as to what we need.General
SOW; Para.2.2Please confirm the contractor should assume no (0) weather days when creating the project schedule.That is correct, please refer to section 3.6 and 3.8 of the PWSGeneral
SOW/1.1 vs. SolicitationThere appears to be a discrepancy regarding the POP duration of the project within the Solicitation documents. Sect. F. denotes 240D (5/1/26 to 12/27/26) as does the Work-Time Analysis. The PWS, however states 334D. Please clarify POP duration as well as whether the POP start date shall coincide with the award date or the NTP.The POP duration of this project is 240 days. The PWS will be corrected to reflect 240 days. The POP will start at the time of NTP, to be issued by the Contracting Officer after award.General

Hazardous Materials

Section ReferencedContractor Question or RecommendationGovernment ResponseCategory
SOW; Para.1.3We note that the IFB says "Disconnection and capping of building utilities (water, sewer, gas, electrical) are the Contractor's responsibility…." Does the water pipe contain asbestos?Site utilities and piping are not expected to contain ACM. Should any evidence to the contrary present itself, the contractor is to stop work immediately and contact the Contracting Officer for further instruction.Hazardous Materials
SOWAt the site visit, we heard from 1 SOCONS that the soil underneath and surrounding Bldg. 90326 is contaminated and that the expectation is for the contractor to remove and properly dispose of this contaminated soil. Please confirm that this is part of the project scope.That is correct, please refer to section 1.1 of the PWSHazardous Materials
Please confirm no PFAS/ PFOS contaminated soils exist on the project site and that no further testing for PFOS/ PFAS will be required within the scope of this project.No known PFAS/PFOS are expected within the confines of this project. If suspect materials are encountered during the execution of this project, the contractor shall immediately stop work and notify the Contracting Officer.Hazardous Materials
SOW; Para.2.1Block 10 on the SF 1447 and Section C both mention "abatement of site hazardous-containing materials and soil" and Section C also mentions "hazardous materials testing, abatement and legal disposal." We note that the Site Visit Summary states that "asbestos has been identified in the building; surveys for asbestos, lead, and other hazards will be provided. Mr. Javier will provide surveys for asbestos, lead etc." Is it the USAF's expectation that the forthcoming surveys will provide enough information about the type and quantity of hazardous material and contaminated soil for contractors to use for bidding purposes? Uncertainty in this aspect of the scope will increase contractor bids. To reduce this uncertainty, would the USAF provide information and assumptions to support hazardous materials abatement/disposal cost estimates?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available. . If during demolition something different is identified immediately notify the Contractingt officer and we will address with contractor and CE functionals. We cannot provide you an estimate for hazardous materials and disposal cost. We do have a site on base that will accept some items, at no cost, Paint, etc.Hazardous Materials
SOWIn the absence of information that is sufficient to support cost estimates for the transportation and disposal of hazardous materials and contaminated soils, will USAF consider providing plug numbers for transportation & disposal of hazardous materials and contaminated soils so that post-award adjustments can be made via contract modification should the actual waste and soil volumes vary from the basis of estimate?Prospective contractors (bidders) will be responsible for providing their best estimate for transporting and disposal of hazardous materials and contaminated soils.Hazardous Materials
SOWWill the existing above ground fuel tank that previously fed the removed generator be demolished as part of this solicitation or if it will be removed by the Government? Will the Government remove the remaining fuel from the tank? Please advise on this scope for this potential hazardous tank.The customer will remove any items they wish to retain no later than 24 April 2026. Anything left behind will need to be properly removed and/or demolished.Hazardous Materials
SOWPlease confirm geotechnical surveys and surveying are not required.That is correct, geotechnical surveys and surveying are not required.Hazardous Materials
SOWWould the USAF please extend the deadline for questions on this solicitation to a date that is no sooner than one week after the referenced existing soils report and hazardous materials survey report have been released via amendment so that contractors may have the opportunity to submit questions on those findings?Not at this time. If additional issues arise we will assess any delay at that time.Hazardous Materials
In accordance with section 3.11 of the Solicitation, ‘areas known to contain/ not contain Asbestos Containing Materials will be identified to the Contractor’; Please provide any information/ documentation regarding environmental debris including Asbestos Containing Materials, Lead Based Paint, contaminated soils, etc. so these can be quantified for bid purposes.A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available. The asbestos will need to be removed before demo and the waste will be manifested as “Asbestos Containing Material, Demolition Debris”, disposed in Florida permitted Class I or III landfill.
To meet NESHAP requirements, F.A.C 62-204.800/F.A.C Rule 62-257.301 (Notice of Demolition or Asbestos Renovation) adopted and incorporated EPA 40 CFR/Chpt 1/Subpart C/Part 61/Subpart M/Sec. 61.145 – Standard for Demolition and Renovation (Asbestos).Hazardous Materials
Has a pre-demolition hazardous materials survey been completed? If so, can that please be distributed in an addendum?A survey from January 2009 will be included to prospective bidders. Other ACM, LBP surveys or information on known hazardous materials will be provided if available.Hazardous Materials