Attachment 1b-General Requirements (Revised-0001)

View the file

Other files for this federal contract opportunity

Other files attached to FY18 Multiple Award Construction Contract (MACC), newest first.
File Type Posted
FBO_Posting.pdf PDF
50_A-4_4_REFLECTED_CEILING_PLAN.PDF PDF
50_A-3_3_ARCHITECTUAL_FLOOR_PLAN.PDF PDF
50_First_Floor_Revised.pdf PDF
50_P-2_PLUMBING_DEMOLITION.PDF PDF
FY18_MACC_RFI_Log_(0009).pdf PDF
50_P-1_BATHROOM_PLUMBING.PDF PDF
FA440718R0002-0005.pdf PDF
50_E-2_10_FLOOR_PLAN_LIGHTING.PDF PDF
50_A-2_TOILET_LAYOUT.PDF PDF
50_A-3_FLOOR_PLAN_DETAILS.PDF PDF
50_F-442-A_FOUNDATION_PLAN_DETAILS.PDF PDF
50_P-1_8_PLUMBING_FLOOR_PLAN.PDF PDF
13-B50_SOW_Rev_5.pdf PDF
50_FP-1_12_FIRE_PROTECTION_FLOOR_PLAN.PDF PDF
26-FY18_MACC_RFI_Log_(0004).pdf PDF
FA440718R0002-0004.pdf PDF
29-Pre-Proposal_Conference_Sign_In_Sheet.pdf PDF
28-Pre-Proposal_Conference_Slide_Show.pdf PDF
FA440718R00020004_(Conformed_0004).pdf PDF
26-FY18_MACC_RFI_Log_(0003).pdf PDF
26-FY18_MACC_RFI_Log_(0002).pdf PDF
27-Visitor_Instructions.pdf PDF
01c-Historic_Preservation.pdf PDF
FA440718R0002_(Conformed_0001).pdf PDF
FA440718R0002-0001.pdf PDF
11-PPI_(20180412).docx DOCX document
16-B50_Drawings.pdf PDF
06-WD-IL17_(IL180017-20180216).pdf PDF
25-Price_Schedule.pdf PDF
08-SAFB_Map.pdf PDF
14-B50_Specifications.pdf PDF
01a-TO_Procedures.pdf PDF
07-SAFB_Climatic_Data.pdf PDF
22-B50_Existing_Furniture.pdf PDF
02-MACC_Gen_Rqmts-EMCS.pdf PDF
23-B50_CPO_Remove_Furniture.pdf PDF
24-B50_Questions-Answers.pdf PDF
11-PPI.docx DOCX document
12-PPQ.pdf PDF
15-B50_Design_Analysis.pdf PDF
03-SAFB_Arch_Comp_Plan.pdf PDF
17-B50_Schedule_of_Submittals.pdf PDF
21-B50_Existing_Floor_Plan.pdf PDF
18-B50_PWS_New_Furniture.pdf PDF
13-B50_SOW_Rev_4.pdf PDF
10-Real_ID_Act_(v21).pdf PDF
05-WD-IL7_(IL180007-20180316).pdf PDF
19-B50_Reconfigured_Floor_Plan.pdf PDF
FA440718R0002.pdf PDF
Show all 50

FY18 Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scott AFB General Requirements (10 JAN 2018) Page 1 of 35

SECTION 01010

GENERAL REQUIREMENTS

(Revised 10 JAN 2018)

GENERAL REQUIREMENTS SPECIFIED IN THIS SECTION REPRESENT A BASELINE

STANDARD. THEY ARE OPERATIVE FOR PROJECTS PERFORMED FOR SCOTT AIR

FORCE BASE TO THE EXTENT APPLICABLE AND NOT IN CONFLICT WITH OTHER,

MORE STRINGENT PROJECT-SPECIFIC REQUIREMENTS, WHICH WOULD BE

GOVERNING.

I. GENERAL

A. DESCRIPTION OF WORK: The contractor shall furnish all labor, equipment, tools, materials, supervision, and other items and services necessary to accomplish what the

Statement of Work (SOW) and/or contract issued pursuant to it, calls for to be performed and provided (the work). All work done shall conform to: the terms of the contract/task order;

applicable government regulations and building codes individually referenced or not;

manufacturers’ instructions; and generally-accepted standards in relevant design professions and building trades.

B. COMPLETE PROJECT: Documents the government provides to the contractor describing a project’s design intent and the work are meant to convey what the government expects and requires from the work and to define a complete project. The contractor is responsible to resolve any uncertainty before committing to do the work. Thereafter, any omission of express reference to specific services or materials reasonably inferred to fall within the project scope, or that are commonly understood within the applicable design profession or building trade as necessary to properly complete a project, will not relieve the contractor of the responsibility to perform or provide such at no additional cost to the government.

C. TYPES OF WORK AND DELIVERY CONTRACTS: As used herein, the types of work are: design of a project (Design); construction of a project designed by others (Construction);

or design and construction of a project under the same contract or task order (Design/Build).

D. LOCATION: Facilities to be constructed or altered are located at Scott Air Force Base, Illinois. The base is located approximately 20 miles East of St. Louis, Missouri, just South of

Interstate Highway 64.

E. STANDARD WORKDAY/WEEK: Work shall be accomplished during the standard 8-hour day, 5-day week, Monday through Friday, between the hours of 7:30 a.m. and 4:30 p.m. local time, excluding federal legal holidays and non-work days resulting from holidays occurring on weekends.

If desiring to work other than within a normal workday, the contractor shall submit a written request at least three (3) work days prior to the proposed performance of work to the

Contracting Officer (CO) and coordinate with the Civil Engineer Squadron (CES) Project

FA440718R0002

Attachment 1b

Scott AFB General Requirements (10 JAN 2018) Page 2 of 35

Manager (PM) stating the proposed performance of work, day/days, time/amount of work, and reason why permission should be granted to perform work during non-standard hours.

Scott Air Force Base observes the following federal legal holidays on the day shown or the

Friday before if it falls on a Saturday or the Monday after if it falls on a Sunday:

New Year’s Day 1 January

Martin Luther King Day Third Monday in January

President’s Day Third Monday in February

Memorial Day Last Monday in May

Independence Day 4 July

Labor Day First Monday in September

Columbus Day Second Monday in October

Veteran’s Day 11 November

Thanksgiving Day Fourth Thursday in November

Christmas Day 25 December

F. BASE AND SAFETY REGULATIONS: The contractor shall comply with all applicable

Air Force regulations and directives pertaining to security, safety, occupational health, fire prevention, and environmental hazards, traffic, and personnel clearances while on base.

G. SECURITY: For entry to the base, submit an entry authorization request letter for each individual requiring access to the project at least 10 calendar days prior to beginning work.

The contractor shall email the Contracting Squadron (CONS) requests for all base passes. A valid Federal/State Government issued photo identification and base pass will be required for all individuals when entering the base. All base passes issued must be returned to the CO upon termination of the employee or completion of the project, whichever is sooner. The contractors must comply with the latest version of the Real ID Act.

1. Flight line Access: Check-in and check-out with the Base Operations Dispatcher daily.

During check-in, advise the dispatcher of intended work areas and type of work scheduled, and receive a flight line pass. Follow all flight line procedures. (FOD check, etc.)

a. While on any runway, taxiway, or aircraft parking apron, immediately remove any dirt, debris, or other material spilled or caused by the contractor’s operations.

b. During check-out, brief the dispatcher on completed work and status of any airfield facilities affected by the work.

c. Airfield communication: Maintain communication with base operations and the air traffic control tower at all times.

H. SAFETY BRIEFING: The contractor shall brief employees and all subcontractors on safety, occupational health, and fire prevention regulations, emphasizing the requirement to obtain a welding permit, when welding, cutting and brazing operations are required, and obtain authorization from the base fire chief when open burning is intended. The contractor shall maintain documentation showing that all subcontractors have been briefed as required.

FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 3 of 35

I. ANTI-TERRORISM/FORCE PROTECTION STANDARDS: All constructed work shall conform with UFC 4-010-01, DoD Minimum AT Standards for Buildings issued under the authority of DoD Instruction Number 2000.16, DoD Antiterrorism Standards which requires

DoD components to adopt and adhere to common criteria and minimum construction standards to mitigate antiterrorism vulnerabilities and terrorist threats.

II. SUBMITTAL REQUIREMENTS

A. SCHEDULE OF MATERIAL SUBMITTALS: The contractor is responsible for developing and submitting a material submittal schedule using the government-provided format (e.g. AF form 66), to the CO for approval. The contractor shall identify all planned submittals and dates, and shall submit the schedule to the CO within 14 calendar days after contract award or within another agreed-to date as directed by the CO.

B. SUBMITTALS: The contractor shall submit all items; whether as a one-time submittal or periodic reports; as required by the solicitation documents, specifications and submittal register to the CO for approval.

Material submittals shall comply with Unified Facilities Criteria (UFC) http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc, the Scott Air Force Base -

Architectural Compatibility Plan (January 2000), http://www.wbdg.org/ffc/af-afcec/design-guides-standards/scott-air-force-base-architectural-compatibility-plan, the Air Mobility

Command (AMC) Landscape Design Guide (September 1994) http://www.wbdg.org/ffc/af-afcec/design-guides-standards/landscape-design , the Air Mobility Command (AMC) Interior

Design Guide (April 1999) http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc, the

Historic Preservation Treatment Recommendations for The Scott Air Force Base (January

2013), (Solicitation Attachment 1c), all other design guides applicable to this project, and comply with all contract and solicitation documents.

The CO may request additional submittals when deemed necessary to adequately describe the intended work.

Each submittal shall include an original AF form 3000, Material Approval Submittal, and three (3) copies of supporting documentation. When available, the government may request electronic copies of submittals via email, in lieu of hard copies. The availability and practicality of submitting electronically versus hardcopy should be discussed and agreed to during the initial pre-construction conference after award. In general, submittals shall be provided a minimum of 14 calendar days in advance of scheduled purchase to allow sufficient time for government review. Additionally, unless stated otherwise, submissions of test results and other submittals of that nature shall be made within 14 calendar days, after the work or test is performed.

Each submittal shall be complete and in sufficient detail for ready determination of compliance with the contract requirements. Submittals shall include, but not limited to, items

FA440718R0002

Attachment 1b http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc http://www.wbdg.org/ffc/af-afcec/design-guides-standards/scott-air-force-base-architectural-compatibility-plan http://www.wbdg.org/ffc/af-afcec/design-guides-standards/scott-air-force-base-architectural-compatibility-plan http://www.wbdg.org/ffc/af-afcec/design-guides-standards/landscape-design http://www.wbdg.org/ffc/af-afcec/design-guides-standards/landscape-design http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

Scott AFB General Requirements (10 JAN 2018) Page 4 of 35 such as contractor or manufacturers shop drawings, descriptive literature, catalog cuts, diagrams, operation charts or curves, certifications, samples, test reports, test cylinders, operating manuals, installation procedures and recommendations, templates, and other descriptive material. Catalog cuts and other descriptive data which may have more than one model or type shall be clearly marked to show the model, type, size, and all optional accessory equipment the contractor proposes to install. Submittals on component items forming a system or interrelated items shall be submitted at one time as a single submittal in order to demonstrate that the items have been properly coordinated and will function as a unit. Submittal items which are disapproved shall be promptly corrected and resubmitted within 10 calendar days by the contractor. No material shall be installed until the submittal is approved by the CO. Approved submittals shall be available at the job site for inspection by the PM and the inspector at all times. Material samples shall be submitted for all color selections, patterns and other aesthetic attributes of finish materials. Finish material for interior application and exterior application, shall each be submitted at one time.

C. SUBSTITUTION OF MATERIALS AND EQUIPMENT: If the contractor proposes to use materials, equipment or accessories other than those specified, the contractor shall supply the following data for justification: scaled plans and elevation drawings identifying all applicable pipe locations, electrical connections, penetrations, equipment data and dimensions, and all other supporting equipment/materials associated with the proposed substitute; all required catalog cut sheets and/or descriptive data and a written justification for the proposed substituted item. The CO reserves the right to accept or reject any or all of what is proposed to be changed based on the design intent conveyed in the drawings and specifications, and the completeness and clarity of the request submittal.

For reasons of compatibility, and experience with certain critical existing equipment, systems, components, materials etc., the government will not entertain requests to substitute others for those identified as “base standard” in project drawings or specifications, e.g., the base standard lock cylinder core is by Stanley-Best Access Systems and, unless otherwise noted, no submittal providing for a similar core by another manufacturer will be approved.

It shall be understood and agreed that any substitution of materials and/or equipment, if approved, will be made by the contractor at no additional cost to the government in consequence of it, regardless of any changes in connections, spacing, electrical service, or appurtenances the substitution may require.

D. AS-BUILT DRAWINGS AND SPECIFICATIONS: The contractor shall submit plans and elevations drawings drawn to ¼” equals 1’ scale if the contractor purposes a piece of equipment and/or accessories on other than that specified. During the course of construction, the contractor shall keep an accurate record of differences in as-built drawings from the original designed or specified, by means of editing computer-aided design (CAD) files of contract drawings and word-processing files of specifications, saving them as separate files without overwriting the originals. When available, the government may provide record drawings of applicable facilities for use by the contractor to aid in developing as-built drawings. Drawings shall be editable in AutoCAD 2012 and specifications in Microsoft

FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 5 of 35

Word 2013. The contractor is responsible for providing any computer hardware and software required to prepare as-built drawings and specifications.

All variations from the contract drawings and specifications, including those made in consequence of the selection of optional or alternate materials, shall be clearly indicated.

They shall be shown in the same general detail utilized in the original versions. The as-built drawings and specifications shall be kept current during construction and readily available for review by the PM and construction inspector at all times. The final as-built drawings shall be furnished to the CO not later than 14 calendar days after the final inspection date.

As part of the as-built drawings submittal, a separate set of drawings shall be marked showing areas containing existing/remaining asbestos-containing materials and lead-based paint and methods of encapsulation, as applicable.

E. GEOBASE REQUIREMENTS: All geospatial deliverables shall be submitted no later than 30 calendar days after project completion date. All geospatial data shall conform to the following requirements:

1. The contractor shall use conventional surveying and other methods, such as total station or Global Positioning Systems (GPS) for field data collection at an accuracy level of +/-

2cm. All survey data collected shall be provided to the government in a digital format with an attached survey report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams, and field survey data. The contractor shall identify the horizontal and vertical order, classification, ID number, elevation, coordinate location and any other necessary attributes for all surveyed features. All geospatial data shall overlay on the installation’s most current orthorectified imagery provided by Scott AFB. Spatial data shall be established and submitted in the Illinois West State Plane Coordinate System, NAD83, Feet. The contractor shall prepare and submit an ESRI, ArcGIS 10.0 format geodatabase. The contractor shall utilize ESRI ArcGIS 10.0 topology rule to ensure the following:

a. No erroneous overshoots, undershoots, dangles or intersections in the line work.

b. Lines should all be continuous, (i.e., do not create dashed lines with many small line segments).

c. Point features should be digitized as points, not graticules, cells, symbols or icons.

d. No sliver polygons.

e. All polygons completely close and have a single unique centroid

f. Digital representation of the common boundaries for all graphic features must be coincident, regardless of feature layer.

2. Submittal data shall be in compliance with the Spatial Data Standards for Facilities, Infrastructure and Environment (SDSFIE). Entity naming conventions, attribute fields, FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 6 of 35 and domain names will be collected in the format defined by the CADD/GIS Technology

Center’s Spatial Data Standards release 2.4 (or current version available). This standards document can be found at: https://www.sdsfieonline.org/Home/Index .

3. Feature Attributes: The contractor shall identify the classification, type, location, ID number, and any other necessary attributes, specified by the government, for all surveyed, mapped, designed, or proposed features. Metadata should be submitted in ESRI ArcGIS

10.x format using the Federal Geographic Data Committee (FGDC) Content Standards for Digital Geospatial Metadata (CSDGM). The contractor shall complete all metadata elements marked mandatory and mandatory-if-applicable as defined by the FGDC

CSDGM for each layer collected. This standard document can be found at:

http://www.fgdc.gov/metadata/csdgm

F. ENVIRONMENTAL CONTROL: The contractor shall segregate hazardous or regulated materials, and non-hazardous or non-regulated materials during demolition; and handle, transport, store, and dispose of these hazardous and non-hazardous materials in accordance with applicable federal, state, and local laws, ordinances, or other rulings having the effect of law, including but not limited to the items listed below. In addition, the contractor shall obtain proper disposal manifests for both hazardous and regulated materials, and for non-hazardous or non-regulated materials, and submit these manifests to the CO. These manifests shall be included as a submittal on the AF Form 66, Schedule of Material Submittals. Submit original manifest with original signature of authorized representative from the SAFB

Environmental Management Office at Scott AFB 375 CES/CEIEC, to the CO within 30 calendar days of disposal. The original hazardous waste manifests will be provided to SAFB

Environmental Management Office, for tracking and reporting purposes. All handling, transporting, and disposal costs shall be considered as having been included as a factor in the contractor’s bid price. Any questions regarding proper handling or disposal of hazardous or non-hazardous materials may be directed through the CO to the SAFB Environmental

Management Office, at (618) 256-2092. Reference the following documents when submitting manifests:

Resource Conservation and Recovery Act (42 USC 6901)

Clean Water Act (33 USC 1251)

Toxic Substances Control Act (15 USC 260)

National Environmental Policy Act (42 USC 4321-4347)

Hazard Communication (OSHA 29 CFR 1910.1200)

Clean Air Act (42 USC 7401-7642)

1. All disposal manifests must be signed by Scott AFB 375 CES/CEIEC trained personnel appointed by the wing commander. See Hazardous Waste Manifest Delegation appointment letter obtained from Scott AFB 375 CES/CEIEC for all appointed

Environmental representatives. If possible, please provide a courtesy 1-2 working day notice prior to needing a manifest signed to ensure personnel from the SAFB

Environmental Management Office are available at that specified time.

FA440718R0002

https://www.sdsfieonline.org/Home/Index http://www.fgdc.gov/metadata/csdgm

Scott AFB General Requirements (10 JAN 2018) Page 7 of 35

2. Scott AFB has a unique EPA ID Number that must be on all manifests for future tracking purposes; this is something that will be verified by the SAFB Environmental

Management Office, along with other line items, before signing the manifest.

3. Additionally, this information is used in annual reporting that can and will be audited by the EPA. If manifests are not signed by an environmental representative and our office has no record of disposal, then this becomes a legal risk.

4. Asbestos Abatement/Lead-based Paint: It is the contractor’s responsibility to complete notification applications. The SAFB Environmental Management Office will review, sign, and submit completed forms to Illinois Environmental Protection Agency (IEPA), or Illinois Department of Public Health (IDPH) as applicable. Allow a minimum 15 calendar days of lead-time for IEPA notices or 48 hours for IDPH notices. All asbestos/lead-based paint waste will be segregated, properly containerized, and shipped with either a waste shipment record or manifest to an approved facility. All manifests shall be signed by personnel from the SAFB Environmental Management Office.

Original signed manifests will be given to the SAFB Environmental Management Office.

All asbestos removed from Scott AFB shall be disposed of at a licensed disposal site in the State of Illinois only.

5. Provide the PM with a chemical inventory and an estimated quantity to be used, prior to bringing hazardous materials on the base. An additional copy of the chemical inventory and appropriate Material Safety Data Sheets (MSDS) shall be provided to Scott AFB 375

CES/CEIEC. These requirements shall be included as a submittal on the AF Form 66, Schedule of Material Submittals.

6. All radioactive material or equipment using radioactive material must be approved for use prior to bringing it on the base. The written request for approval, along with a copy of the permit for the source and brief description of the intended activities, shall be submitted to the base Bioenvironmental Engineering Flight through the 30 calendar days prior to the contractor’s use. No work involving radioactive materials may proceed until receipt of the approved request. This requirement shall be included as a submittal on the

AF Form 66, Schedule of Material Submittals.

7. Any items containing radioactive material, especially radio luminescent exit signs, discovered while performing maintenance, repair, alteration or renovation activities, shall be turned in by the contractor to Scott AFB 375 CES/CEIEC for proper disposal.

8. The contractor will be held responsible for complying with all federal, state, and local environmental regulations as part of the processes of performing the work included in this project.

9. Lead in liquid paints or coatings shall be restricted to no more than 0.06 percent lead by weight of the non-volatile solids for use in or on all base facilities (24 CFR Part 35

Subpart B).

http://www.epa.illinois.gov/index

Scott AFB General Requirements (10 JAN 2018) Page 8 of 35

G. REAL PROPERTY RECORDS: At the completion of construction and before final payment, the following information, by building number, shall be provided by the contractor to the CO on a completed DD form 1354 for record purposes. The contractor will be furnished a copy of a filled-in sample 1354 worksheet, which should aid in completion of the form. The contractor shall:

1. Provide a draft DD form 1354 to the CO at least 45 calendar days prior to the contract completion date. At a reasonably scheduled time upon receipt of the draft, a representative from the Real Property Office with the contractor will do a thorough walk through and annotate any findings or corrections required.

2. Prepare an accounting of all installed/constructed property, by building number (if multiple buildings are included in the project/task order).

3. List government-furnished/contractor-installed items and contractor-furnished/ contractor-installed items.

4. List complete nomenclature of each item:

a. Manufacturer.

b. Model Number.

c. Serial Number.

d. Electrical rating, full nameplate data.

e. Capacity (MBTU, KVA, Tons, Sprinkler Heads, Etc.).

f. Cost of each item (Equipment cost only)

g. Other pertinent information (Warranty/guarantee information-start date, stop date)

5. List items including, but not necessarily limited to, the following:

a. Electrical equipment (special lighting fixtures, metering equipment, overhead door operators, exterior floodlights and poles, fire alarm and burglar alarm systems, etc.)

b. Mechanical equipment (commercial refrigeration equipment, heating equipment, air conditioning systems equipment, pumps, boilers, sprinklers, meters, and other items of mechanical equipment)

c. Other items that are considered to be real property installed equipment

6. The Real Property Office is the point of contact for questions, comments or concerns on property records. The CO can provide an example of a completed DD Form 1354. Both the worksheet and draft copy will be available at the onset of the project.

H. BUILDER DATA: At the completion of construction and before final payment, the following information, by building number, shall be provided by the contractor to the CO on a completed DD Form 1354 for record purposes. The contractor will be furnished a copy of a filled-in sample DD Form 1354 worksheet, which should aid in completion of the form.

Scott AFB General Requirements (10 JAN 2018) Page 9 of 35

The contractor shall provide BUILDER data for government validation at least 30 calendar days prior to O&M handover walk-through (conducted prior to contract close out). Following government validation of the BUILDER data the contractor will provide the government two copies of CD-ROM media with an electronic copy of the excel database file for the entire facility as part of the final close out document package.

I. A/E DESIGN-BUILD SUBMITTALS: The contractor shall hire licensed A/E to submit the following design submittals to 375 CONS and 375 CES.

1. Submit list of design-related items the contractor needs to complete design in a timely manner. List shall include detailed description of action item and name of individual or agency responsible.

2. Submit design documents for 35%, 65%, and 95% reviews must include three (3) sets of

½ size plans, three (3) copies of specifications, reports, studies or design analysis and supporting engineering data and 2 CD’s of AutoCAD drawings and Microsoft Word documents of everything submitted. Allow up to twenty-one (21) days for Government review and comment for each submittal and then CONS will schedule a Government review meeting to be held on base after each submittal. The Government will pay no additional compensation to the Contractor for the incorporation of comments. The

Contractor shall respond to all comments in advance of the Government review meeting.

The contractor’s response shall identify action taken with drawing number or specification paragraph. If the contractor disagrees technically and does not intend to comply with the comment, the contractor must give the reasons for non-compliance within five (5) days after close of the review period in order that the comment can be resolved. If the contractor believe the action required by any comment exceed the requirements of this contract, they should “flag” the comment as being outside the design scope.

3. Submit 100% design documents to include one (1) full sized plans and three (3) ½ sized plans, and three (3) specifications, reports, studies and design analysis and supporting engineering data with seals, signatures, stamps and dates and two (2) CD’s of AutoCAD drawings and Microsoft Word documents of everything submitted before construction can begin. No Government review meeting with be required.

4. All submittals shall be on an AF Form 3000, Material Approval Submittal, for approval by the CO and CES. All corrections or modifications to these drawings shall be corrected before construction can begin.

5. Submit shop drawing list and shop drawings on all equipment and colors for review.

6. Submit as-built drawings to include one (1) full sized plans and three (3) ½ sized plans, and three (3) specifications, reports, studies and design analysis and supporting engineering data with seals, signatures, stamps and dates and two (2) CD’s of AutoCAD drawings and Microsoft Word documents, O&M manuals and AF Form 1354.

Scott AFB General Requirements (10 JAN 2018) Page 10 of 35

III. WORK COORDINATION:

A. GENERAL: The contractor shall coordinate all work schedules with the PM and the construction inspector prior to the start of work. The contractor shall notify the PM and the construction inspector five (5) work days prior to moving onto the work-site to commence work. The contractor must provide notification the day when moving back to the work-site after an interruption of work of two (2) or more work days. Before initiating any work, the contractor shall meet with the CO, PM and inspector and agree on:

sequence of procedures means of access to premises and buildings placement of dumpsters and haul routes delivery of materials and use of approaches use of corridors, stairways, elevators, and similar means of egress requirements and means of communication location of partitions and barriers location of eating spaces and restroom for contractor’s employees other matters incidental to the project

1. Interruption of work: If it becomes necessary to interrupt work activities in buildings and/or areas for construction purposes (except as otherwise described in the solicitation documents), the contractor shall request permission, in writing, from the CO, or designated representative(s), at least ten (10) work days in advance.

2. Temporary Construction: Any contractor-installed temporary construction intended to prevent interruption of normal work activity or loss of utility services is subject to approval of the Base Civil Engineer (BCE) through the CO.

B. INSPECTION: The contractor shall obtain the construction inspector's approval prior to doing such work as closing walls or performing tests. The request shall be made three (3) work days in advance to permit an inspection of the area before completion. If the inspector fails to arrive at the site at the time agreed, the contractor may continue with the work in strict compliance with the project drawings and specifications. The inspector's approval or failure to appear does not relieve the contractor of its obligation to comply with the construction documents.

C. WATER UTILITY WORK: The water utility lines on Scott AFB are owned and operated by American Water Co. (AW). The contractor shall coordinate with 375 CES who will coordinate with AW when conducting any work pertaining to the water utility or fire suppression lines. Compliance with AW’s requirements does not relieve the contractor from complying with Scott AFB requirements, including submittals, as-builts, and other coordination.

D. ROAD CLOSURES: If any closure of a road is required, the contractor shall submit a request to do so to the construction inspector three (3) weeks prior to the planned date for the closure. The request shall include a map showing the location of the closure and a suitable

FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 11 of 35 alternate route for detouring traffic normally using the road to be closed. The contractor shall provide all signage, personnel and barricades required to properly direct traffic having to detour.

E. AIRFIELD CONSTRUCTION: For any construction work within the airfield restricted area, the following requirements must be met by the contractor through coordination with the

PM:

1. Obtain flight line drivers training and radio operation training.

2. Coordinate with Security Forces for a “Free Zone”.

3. Adhere to Unified Facilities Criteria (UFC) 3-260-01, Airfield and Heliport Planning and

Design, Section B14, for airport safety procedures. Construction work must be divided into phases to facilitate aircraft movement in accordance with UFC 3-260-01.

4. Attend a preconstruction meeting and risk management meeting with Airfield

Management.

5. Temporary construction waivers must be signed by the wing commander prior to work start.

6. Runway closures require lighted “X’s” to be placed over the runway numbers and be maintained/serviced.

7. Provide “low profile” airport rated barricades to define aircraft non-movement area(s).

8. Include Airfield Management as part of final inspection team for project.

F. PROJECT SUPERINTENDENT: Per FAR 36.506, the contractor must employ a full-time superintendent for the project on job site. The superintendent’s duties shall include the overall management of the project, coordination of the sub-contractors’ work, and liaison with the CO and the construction inspector. At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor. A competent representative is as defined by the Occupational Safety and Health Administration (OSHA)

Standards for Construction Industry part 1926.32, Definitions (29 C.F.R. 1926 OSHA). This paragraph supplements FAR clause 52.236-6, Superintendence by the contractor.

G. 24-HOUR POINT OF CONTACT: The contractor shall provide the CO with a 24-hour number or numbers where its authorized representative can be contacted at any time day or night. This number shall be provided at the pre-construction meeting, but, not later than the first day of contract work at the site or ten (10) calendar days after the Notice to Proceed date.

H. CONTRACTOR’S OFFICE SPACE: Office space required for the contractors operation shall be the responsibility of the contractor and self-provided. Trailers utilized by the contractor for administrative or material storage purposes must present a clean and neat exterior appearance and be in a state of good repair. 375 CES will determine if the trailers are adequate for use on base.

I. CONTRACTOR’S TRAILERS OR STORAGE AREA: Trailers or storage buildings will be permitted, where space is available, subject to the approval of the Contracting Officer.

FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 12 of 35

The trailers or buildings shall be in good condition, free from visible damage rust and deterioration, and meet all applicable safety requirements. Trailers shall be roadworthy and comply with all appropriate state and local vehicle requirements. Failure to maintain storage trailers or buildings to these standards shall result in the removal of non-complying units at the contractor’s expense. A sign not smaller than 24 by 24 inches shall be conspicuously placed on the trailer depicting the company name, business phone number, and emergency phone number. Trailers shall be anchored to resist high winds and must meet applicable state and local standards for anchoring mobile trailers. The location must be approved by the CO in advance. All other trailers, storage, and equipment must be stored at a site designated by the inspector. The government is not responsible for damages or losses. This paragraph supplements FAR clause 52.236-10, Operations and Storage Areas.

J. SITE AND STORAGE AREA MAINTENANCE: The contractor is responsible for maintaining the construction site and storage area(s) daily. This includes, but is not limited to, lawn mowing, ice and snow removal, and disposal of trash and debris. Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways; gravel gradation will be at the contractor’s discretion. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.

Cut grass (or annual weeds) within the construction and storage sites to a maximum 4 inch height at least once a week during the growing season unless the grass area is not visible to the public. Trim the grass around fences at time of grass cutting. Maintain grass or weeds on stockpile earth as described above.

Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store within the fenced area described above or at the supplemental storage area any materials resulting from demolition activities which are salvageable. All material should be neatly stacked for storage.

K. RESTORATION OF STORAGE AREA: Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.

After removal of trailers, materials, and equipment from within the fenced area, remove the fence that will become the property of the contractor. Restore to the original or better condition, areas used by the contractor for the storage of equipment or material, or other use.

Gravel used to traverse grassed areas must be removed and the area restored to its original condition, including top soil and seeding as necessary.

L. DUST CONTROL: The contractor shall control all excavations, embankments, stockpiles, access roads, and other such areas of work so as to avoid excess dust becoming a hazard or nuisance to base personnel or surrounding facilities. Approved sprinkling, chemical treatment, light bituminous treatment or similar methods will be permitted to control dust during work. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard may occur. Additionally, the contractor shall ensure that any equipment

FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 13 of 35 hauling rock, soil, or other debris is fitted with a tarp or other means adequate to contain it and prevent littering of parking lots or roadways. The contractor shall attempt to ensure its trucks and other equipment do not leave mud and debris on the roadways and shall pick up, clear and/or sweep away by whatever means necessary any that does get on the roadways to the satisfaction of the Contracting Officer. Reference Illinois Air Quality Standards.

M. PATCHING AND REPAIRING: After the work has been completed, any contractor-caused damages to government-owned structures or other facilities, streets, curbs, walks, lawns, etc., shall be properly patched, repaired, or replaced to the satisfaction of the CO.

Any holes, cuts, breakage or damage in/to finished surfaces in the area of work shall be properly repaired and the affected areas then refinished, resurfaced or otherwise repaired to match those of the adjacent to the satisfaction of the CO.

N. DISPOSITION OF REMOVED GOVERNMENT PROPERTY: All materials and equipment to be removed by the contractor and not reinstalled or recycled under this contract, including debris generated by the project work, shall be removed at regular intervals from the site and disposed of off-base by the contractor. Such disposal shall be in conformity with applicable federal, state, and local pollution regulations and at the contractor’s expense.

O. EXCAVATIONS & LANDSCAPING: The contractor shall backfill all excavations within

7 calendar days unless ongoing work in an excavation precludes such action. In no event shall the contractor stockpile removed earth material on the construction site unless it is to be used in another portion of the same project. For all disturbances to grounds, the contractor shall complete final grading within one (1) week of the disturbance/backfilling. The contractor shall complete final landscaping or seeding within three (3) weeks of the beginning of the planting season if possible or as soon as possible when suitable conditions exist.

Scarify existing subgrade and provide 4 inches of topsoil for newly graded finish earth surfaces and areas disturbed by the contractor. Topsoil shall not be placed when the subgrade is frozen, excessively wet, extremely dry, or in a condition otherwise detrimental to seeding, planting, or proper grading. Provide topsoil as required. Provide seed at 5 pounds per 1000 square feet and match existing vegetation. Provide CID A-A-1909, Type I, Class 2, 10-10-10 analysis fertilizer at 25 pounds per 1000 square feet. Provide straw matting to protect newly seeded areas and stake as required. Water newly seeded areas to establish seed germination and an acceptable stand of grass. Sod shall be provided in flight line areas.

P. FINAL CLEANUP: Upon completion of the project, all construction equipment and debris shall be removed from the site, and the site left in a condition acceptable to the CO. This paragraph supplements FAR 52.236-12, Cleaning Up.

IV. PERMITS:

A. GENERAL: The following outlines permits which may be required incidental to design or construction. The list is not a complete list and additional permits may be required. It is the

FA440718R0002

Scott AFB General Requirements (10 JAN 2018) Page 14 of 35 responsibility of the contractor to determine which permits are required, if any; and when they must be applied for, whether listed here or not. The contractor shall submit all permit applications to the CO and pay all permit fees due. Once completed application and fees have been received from the contractor through the CO, environmental permits will be submitted to applicable state agency by the SAFB Environmental Management Office.

B. SPECIAL PERMITS REQUIRED (as applicable to work):

1. EMERGENCY POWER GENERATOR PERMIT: The contractor shall contact the

SAFB Environmental Management Office, Air Quality program manager, to find out the requirements for an emergency power generator prior to having the generator delivered to the base. The generator shall be certified by the Family Emissions Limits (FELs). The

Point-of-Contact (POC) can be reached at (618) 256-2167.

2. BURN PERMIT: A USAF Welding, Cutting, and Brazing Permit (burn permit) must be obtained by the contractor from the base fire department prior to conducting any operation that will create a spark or flame. The POC there can be reached at (618) 256-

5130. If an open burn permit is required, the permit request shall be routed through the

SAFB Environmental Management Office, Air Quality program manager, no-later-than three (3) months prior to actual open burn effort.

3. NOTICE OF PROPOSED CONSTRUCTION OR ALTERATION: As described in

CFR Title 14 Code of Federal Regulations, part 77, when planning to build within 20,000 feet of an active runway or use equipment in construction which will penetrate a 100 to 1 slope from the nearest point of the runway, among other defined circumstances, notice to the Federal Aviation Administration (FAA) is required unless expressly exempted by the

FAA or the Scott AFB Community Planner. The contractor is responsible for ensuring that FAA Form 7460-1 is completed and submitted to the FAA at least 45 calendar days prior to the start of any construction and approved prior to the start of the project by the

Regional FAA Office. The FAA Form 7460-1 can be submitted either to (Chicago

Airports District Office, CHI-ADO-600; 2300 East Devon Avenue, Des Plaines, IL

60018; (847) 294-7336; FAX (847) 294-7036) or electronically at https://oeaaa.faa.gov/oeaaa/external/userMgmt/permissionAction.jsp. The contractor shall provide a copy of the submitted form to the PM. If the project involves the use of a crane, the PM must also notify the airfield manager at (618)256-4101 of the dates/times of a crane’s operation at the construction site.

4. SEWER PERMIT: Sewer extension, new installation, and connection to the existing sanitary sewer system require a permit. The application shall be signed, certified and stamped by an Illinois Registered Engineer and submitted to the SAFB Environmental

Management Office, water permits manager for local coordination, and signatures.

CEIEC will submit the final package to the Illinois Environmental Protection Agency, Division of Water Pollution Control. Permit applications, with instructions are available at http://www.epa.state.il.us/water/forms.html#permits-wastewater. The POC for specific questions and guidance is the water permits manager at (618) 256-2531.

https://oeaaa.faa.gov/oeaaa/external/userMgmt/permissionAction.jsp http://www.epa.state.il.us/water/forms.html#permits-wastewater

Scott AFB General Requirements (10 JAN 2018) Page 15 of 35

5. GENERAL NPDES PERMIT: Storm water discharge from a construction site requires a Notice of Intent (NOI) under the National Pollutant Discharge Elimination System

(NPDES) to be submitted to the Illinois Environmental Protection Agency (IEPA) prior to any construction activities. The NOI shall be signed, certified and stamped by an

Illinois Registered Engineer and submitted electronically along with three (3) hardcopies to the SAFB Environmental Management Office water permits manager for local coordination, and signatures. The final package will then be submitted by SAFB

Environmental Management Office to the IEPA Division of Water Pollution Control.

General information, forms and instructions are available on-line at http://www.epa.state.il.us/water/forms.html. For specific questions and guidance contact the water permit manager at 618-256-2531.

a. A Storm Water Pollution Prevention Plan (SWPPP) will be written and submitted to

SAFB Environmental Management Office for approval as required by IEPA MS4 permit requirements. Coordinate with SAFB Environmental Management Office in order to obtain an IEPA Notice of Intent (NOI) for a general permit to discharge storm water associated with construction site activities (lead time, for permit signatures and IEPA review, is approximately 60 calendar days after the SWPPP is approved by SAFB Environmental Management Office).

b. An Army Corps of Engineers’ 404/401 permit application will be submitted to SAFB

Environmental Management Office for work performed within the high banks of a channel, including construction of any outfall pipes into a creek (lead time is approximately 60 days for permit application). Coordination with SAFB

Environmental Management Office is required to obtained proper signatures for permit submittal.

6. WATER UTILITY WORK: The water utility lines on Scott AFB are owned and operated by American Water Co. The contractors shall coordinate with American Water

Co. when conducting any work pertaining to the water utility lines. Compliance with

American Water’s requirements does not relieve the contractor from complying with

Scott AFB requirements (i.e. – submittals, as-built drawings, coordination, etc.).

a. WATER PERMIT: An application for construction / operation must be submitted to

American Water Co. for water main installation and connection. Permit applications, with instructions, from the State of Illinois are available on the IEPA website at http://www.epa.state.il.us/water/forms.html#permits-drinking-water. The contractor may contact the American Water Customer Service at 1-800-422-2782 or infoaw@amwater.com with questions

b. AMERICAN WATER WORK PERMIT: All work affecting the water utility system, shall be reviewed and a permit for it issued by American Water Co. prior to being done. All work must conform to what is stated on the permit. The contractor shall submit the application for the permit to American Water. Applications, with instructions, are available on line at http://www.epa.state.il.us/water/forms.html#permits-drinking-water. American

FA440718R0002

Attachment 1b http://www.epa.state.il.us/water/forms.html http://www.epa.state.il.us/water/forms.html#permits-drinking-water mailto:infoaw@amwater.com http://www.epa.state.il.us/water/forms.html#permits-drinking-water

Scott AFB General Requirements (10 JAN 2018) Page 16 of 35

Water has an office on Scott Air Force Base at 34004 New Mexico Street and can be contacted at (618) 744-9631.

7. ABOVEGROUND/UNDERGROUND STORAGE TANK PERMITS: A permit is required to install or work on any aboveground storage tank larger than 110 gallons, to include generator sub-base tanks, and any underground storage tank or associated piping.

Forms are available on-line at: http://www.state.il.us/osfm/PetroChemSaf/home.htm.

8. EXCAVATION PERMIT: The contractor shall apply for and obtain a government

Excavation Permit, also known as a “digging permit” (Scott AFB Form 1031, AF Form

103, Base Civil Engineer Work Clearance Request), prior to any excavation. The permit can be obtained from the Civil Engineering, Operations – Engineering Services , Building

57, 501 East Winters Street. There is no charge for the permit. The digging permit is required for the government to locate and mark existing underground utilities as well as for the government’s internal notification and coordination. The contractor shall not begin any below-grade work until this permit has been completed and approved. The contractor shall make every attempt to identify and locate all valve and utility shut-off locations for use in the event of accidental damage. The contractor shall note any utilities discovered during excavations not shown or shown incorrectly on the contract drawings

(including any erroneous or missing dimensions on government record drawings), and clearly identify those discoveries on the as-built drawings.

The contractor shall initiate the request for a digging permit a minimum of five (5) work days prior to any excavation or ground penetration. The site plan shall clearly delineate the proposed work area and, if within a reasonable distance, the nearest building and cross street to the location of digging, etc. The location of the excavation or ground penetration shall be marked with white, water soluble, spray paint, or white utility marking flags, and the markings maintained until the area is reviewed and cleared by all utility agencies concerned. In the event a representative of a designated utility does not respond, the contractor shall immediately notify the CO. After identified utilities have been cleared through each office affected, a copy of the digging permit will be provided.

The digging permit must be on the job site during the excavation process and every precaution taken during excavation to prevent damage to the existing utilities. The contractor must immediately notify Civil Engineering, Operations – Engineering Services and the construction inspector if any utility is damaged during the excavation process.

Dig permits and JULIE numbers can be obtained by contacting 375.ces.ceoe@us.af.mil.

It is the contractor’s responsibility to maintain all markings for each project.

a. CONSTRUCTION RUBBLE/DEBRIS REPORT: The contractor will provide a quarterly report (Jan-Mar, Apr-Jun, Jul-Sep, and Oct-Dec) by the 10th of the following month and at the completion of construction detailing disposition of debris and ruble generated and removed from the site. The report will give weights in tons for materials taken to a landfill, materials recycled, and materials reused.

9. BASE OUTAGES: Accomplish all work required in connection with utility outages on weekends or off-duty hours, or as directed by the CO.