Attachment 11 - MAHG171095 Renovate Stennis Hall - Additional QA.pdf
PDF 63 KB Posted
- Attached to
- MAHG 17-1095 Stennis Hall
- Solicitation number
- FA301026R0010
About this file
This is a Questions and Answers document (Attachment 11) for federal contract opportunity FA301026R0010, Renovate Stennis Hall. The document addresses a single clarification regarding electrical panel specifications called out in the project drawings.
The document clarifies that Drawing E-702, Panel Schedule, which originally specified new Square D Type NEHB breakers, should utilize existing breakers rather than replacing the panels. The answer confirms that contractors should reuse the existing, obsolete breakers currently in service, rather than procuring new replacement components. This clarification eliminates ambiguity regarding whether panels should be replaced entirely or retrofitted with existing equipment.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA301026R0010
Renovate Stennis Hall
Additional Q&A:
1. Drawing E-702, Panel Schedule, calls for new Square D Type NEHB breakers. These breakers are obsolete. Please confirm whether the existing breakers are to be reused or if the panels are to be replaced.
Answer: Yes, reuse existing, obsolete breakers since these breakers are currently in service.
Attachment 11
FA301026R0010