Attachment 1 - MAHG171095 Renovate Stennis Hall - Specifications.pdf
PDF 3 MB Posted
- Attached to
- MAHG 17-1095 Stennis Hall
- Solicitation number
- FA301026R0010
About this file
This is a Specification and General Requirements document (Attachment 1) for a federal construction contract to renovate and repair mechanical, electrical, and plumbing systems at Stennis Hall (Building B1002) on Keesler Air Force Base in Biloxi, Mississippi. The project, identified as MAHG171095 with contract number FA301026R0010, involves complete renovation of the mechanical system in each building quadrant, replacement of two existing chillers and main electrical switchgear, replacement of all plumbing fixtures, modernization of the elevator, and replacement of Computer Room Air Conditioning (CRAC) units. The work includes asbestos abatement in Rooms 119 and 124, acid cleaning of restrooms, and fire alarm system upgrades. The project will be phased to allow the facility to remain occupied during construction, with the second floor provided first for HVAC quadrant and restroom work, followed by the first floor. The performance period is 600 calendar days from the Notice to Proceed.
The specifications establish comprehensive administrative, scheduling, and quality control requirements for the contractor. Key submittals required include project schedules using Critical Path Method (CPM) within 15 calendar days of NTP for preliminary schedule and 10 calendar days for initial schedule, Schedule of Values, quality control plans, safety plans, environmental protection plans, and operation and maintenance data. The contractor must maintain a project superintendent with minimum 10 years' construction experience and 5 years as superintendent on similar projects. Work is restricted to 9-hour days between 7 a.m. and 5 p.m., Monday through Friday, excluding federal holidays, with Contracting Officer approval required for weekend or after-hours work. Security requirements include KAFB identification cards, vetting through Air Force Office of Special Investigations for non-US citizens, and compliance with base traffic and FPCON procedures. The solicitation is a Total Small Business set-aside with contract value exceeding $10,000,000; a pre-bid site visit is scheduled for August 5, 2026, at 9:00 a.m. CDT, requiring valid driver's license, vehicle registration, and proof of insurance for base access.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAHG171095
PROJECT:
Repair HVAC Stennis Hall, B1002
PROJECT NUMBER:
MAHG171095
KEESLER AIR FORCE BASE
BILOXI, MISSISSIPPI
508 L Street
Keesler AFB, MS 39534
FA301026R0010
Attachment #1
INDEX
SECTION DESCRIPTION
01 11 00 Summary of Work
01 14 00 Work Restrictions
01 30 00 Administrative Requirements
01 32 01.00 10 Project Schedule
01 33 00 Submittal Procedures
01 35 26 Governmental Safety Requirements
01 42 00 Sources for Reference Publications
01 45 00 Quality Control
01 58 00 Project Identification
01 78 00 Closeout Submittals
01 78 23 Operation and Maintenance Data
02 41 00 Demolition
03 30 00 Cast-in-Place Concrete
05 12 00 Structural Steel
06 10 00 Rough Carpentry
06 20 00 Finish Carpentry
07 92 00 Joint Sealants
09 51 10 Acoustical Panel Ceilings
09 68 00 Carpet
10 21 13 Toilet Compartments
10 28 13 Toilet Accessories
14 24 00 Hydraulic Elevators
21 13 13 Wet Pipe Sprinkler Systems, Fire Protection
22 00 00 General Plumbing
22 07 19.00 40 Plumbing Piping Insulation
23 03 00.00 20 Basic Mechanical Materials and Methods
23 05 15 Common Piping for HVAC
23 05 48.00 40 Vibration and Seismic Controls for HVAC Piping and Equipment
23 05 48.19 Seismic Bracing for HVAC
23 05 93 Testing Adjusting and Balancing for HVAC
23 07 00 Thermal Insulation for Mechanical Systems
23 09 00 Instrumentation and Control for HVAC
23 21 23 Hydronic Pumps
23 23 00 Refrigerant Piping
23 30 00 HVAC Air Distribution
23 31 13.00 40 Metal Ducts
23 64 10 Water Chillers, Vapor Compression Type
23 64 26 Chilled, Chilled-Hot, and Condenser Water Piping Systems
23 73 13.00 40 Modular Indoor Central Station Air Handling Units 23 81 23 Computer Room Air Conditioning Units 25 05 11 Cybersecurity for Facility-Related Control Systems 26 05 71.00 40 Low Voltage Overcurrent Protective Devices 26 20 00 Interior Distribution System 26 24 13 Switchboards 26 29 23 Adjustable Speed Drive (ASD) Systems under 600
Volts 28 31 76 Interior Fire Alarm and Mass Notification System, Addressable 31 00 00 Earthwork 31 10 00 Site Clearing 32 92 23 Sodding
SECTION 01 11 00 Page 3
SECTION 01 11 00
SUMMARY OF WORK
02/24, CHG 1: 05/25
PART 1 GENERAL
1.1 ACRONYMS/DEFINITIONS
ACM Asbestos Containing Material AF Air Force AFB Air Force Base
AFI Air Force Instruction
AHU Air Handling Unit
APR Air Purifying Respirator
BMP Best Management Practice
BOS Base Operating Service
C&D Construction and Demolition
CE Civil Engineering
CES Civil Engineer Squadron
CEV Civil Engineering Environmental
CFR Code of Federal Regulations
CM
CPM
Contract Monitor/Construction Manager Critical Path Method
CO Contracting Officer
CUI Controlled Unclassified Information
DOD Department of Defense
DDC Direct Digital Control
EISA Energy Independence and Security Act
EPA Environmental Protection Agency
FPCON Force Protection Condition
FOIA Freedom of Information Act
FT Foot
GFCI Ground Fault Circuit Interrupter
HEPA High Efficiency Particulate Air (filter)
IAW In Accordance With
IBC International Building Code
IN Inch
LBP Lead Based Paint
LF Linear Feet
MAU Makeup Air Unit
MDEQ MS Department of Environmental Quality
MDOT Mississippi Department of Transportation
MSS Material Submittal Schedule
NEC National Electric Code
NFPA National Fire Protection Association
OSHA Occupational Safety and Health Act
PM Project Manager
SECTION 01 11 00 Page 4
POC Point of Contact PPE Personal Protection Equipment
RAMS Random Antiterrorism Measures
RCRA Resource Conservation and Recovery Act
RFI Request for Information
SDS Safety Data Sheets
SF Square Foot
SOW Statement of Work
SWPPP Storm Water Pollution Prevention Plan
SY Square Yard
TAB Test, Adjust and Balance
UFC United Facilities Criteria
VAV Variable Air Volume
VFD Variable Frequency Drive
WT Work Task
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan; G
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1. Project Description
The contractor shall furnish all equipment, labor, supervision and materials necessary to provide renovations to the mechanical and electrical systems, fire alarm, restrooms and other miscellaneous work for Stennis Hall Cyber Training, B1002 on Keesler AFB.
This contract will be a complete renovation of the mechanical system in each quadrant, the replacement of the 2 (two) existing chillers and the main electrical switch gear. Additional work includes the replacement of all plumbing fixtures and acid cleaning of the restrooms, modernization of the elevator, and the replacement of the CRAC units.
The project will be phased, and the existing tenants of the facility will occupy portions of the facility during construction. The electrical, telecommunications, and HVAC will have to remain operable for the duration of the work. Any shutdowns will require CO approval. Repairs and modifications in the building will be required to accommodate the training mission of the base. Refer to sheet G004 in the drawings for the phasing plan.
The entire second floor will be provided to the Contractor first for HVAC quadrant and restroom work. The contractor is to complete the second floor HVAC quadrant mechanical room work prior to work on the first floor HVAC quadrant mechanical rooms. The entire first floor will be provided at one time. Restroom work to occur at the same time as the phase of the HVAC quadrant mechanical room work.
Replace the two existing 10” water tower isolation valves. Contractor is responsible to update the water tower chemical treatment system to be functional, and is responsible to update the chilled water chemical pot feeder to be functional.
SECTION 01 11 00 Page 5
The required end state is a fully operational cooling and heating system integrated into a new DDC package. All work is to be performed in accordance with all contract documents and is subject to the terms and conditions of the contract.
Hazardous material has been detected in Room 119, and Room 124 in the black mastic and requires abatement. However, most of the building has been tested and cleared, but should additional hazardous material be encountered, the Contractor is to immediately stop work and contact the CO. All hazardous material will be handled IAW paragraphs 1.8, 1.9, and 1.10 of this Section.
1.3.2. General Scope Notes
Contractor shall provide and maintain filters, etc. to prevent construction dust and debris from spreading throughout the HVAC system, Fire System Devices, and IT equipment.
Contractor shall provide constant daily cleaning of the building area.
Contractor shall be responsible for disposing of all material and cleaning the area of work at the completion of the project.
Contractor shall provide 5% additional stock of ceiling tile and all new finish material as applies to this project.
Contractor to ensure occupied rooms are not to be disturbed during construction in adjacent spaces.
The contract requires work to be performed within secure areas of the building. It is the contractor’s responsibility to ensure those that will be working within the secure are properly vetted according to Keesler AFB standards.
Contractor to ensure occupied rooms are not to be disturbed during construction in adjacent spaces.
All Furniture and building equipment to be moved away from work area and covered with tarp or plastic for dust control. Personal items are to be removed by the customer unless directed otherwise. All furniture and building equipment to be moved back to their original location following construction work. Clean all areas during and after work of gypsum dust, debris and gypsum mud.
1.3.3. Period of Performance
Performance will begin after receiving the Notice to Proceed and end six-hundred
(600) calendar days later.
No Work shall begin until all submittals related to that work have been received and approved. The government will provide a response to submittals within 10 calendar days of receipt of submittal required by the MSS and 14 calendar days for any submittal that requests or requires deviation from the contract drawings or specifications.
Punch list items noted during inspections shall be corrected and accepted prior to the end of the Period of Performance or the contract will be considered past due.
1.3.4. Location
The work is located at Stennis Hall, B1002, Keesler AFB, Biloxi MS, approximately as indicated.
1.4 OCCUPANCY OF PREMISES
SECTION 01 11 00 Page 6
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
The project will be phased per Drawings and this specifications.
Before work is started, Contracting Officer approval is required for the following: a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.5 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.6 LOCATION OF UNDERGROUND UTILITIES
PERMITS:
Contractors will be required to obtain permits as required by Keesler in the performance of their work. Contractors shall post or have readily available all permits before work is commenced.
The following permits shall be obtained anytime referenced work is required:
DIG PERMIT – BOS/CE Customer Service
BURN PERMIT – Keesler AFB Fire Department (certified personnel only)
CONFINED ENTRY PERMIT – BOS/CE CM; Notification to Fire Department of actual day and time work is accomplished.
CRANE PERMIT - Coordinate crane usage with the Subcontract Technical Monitor (STM). Submit notice with the Federal Aviation Administration (FAA) at least 45 days before the start of the proposed construction or the date an application for a construction permit is filed, whichever is earliest.
1.6.1 INTERRUPTION OF SERVICES:
If interruption of any building utility services such as but not limited to the following: chilled water, electrical power, domestic water, fire protection water supply, or communications etc. are required, the Contractor shall perform the work during normal work week hours.
Contracting Officer approval is required for any work during the weekend or on non-training Fridays. The Contractor shall coordinate the interruption of the utilities 14 days in advance with the CM and user regardless of the option chosen. The Contractor shall include any additional cost of performing the work in their original bid.
The Contractor shall submit a Utility Service Outage Request to the
SECTION 01 11 00 Page 7
Contracting Officer. The Contracting Officer may require the Contractor to attend a coordination meeting to assess the purpose, intent, and impact of the outage request with the facility and any or all operations departments. Contractors shall not shut down or start-up any mechanical, electrical and/or plumbing system without the coordination and/or permission of the CO.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with dual frequency Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.2 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.7 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 2 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
1.8 REQUIRED ASBESTOS ABATEMENT AND MANAGEMENT PROCEDURES:
These steps are in accordance with Air Force Instruction (AFI), EPA, and MDEQ. OSHA regulations govern all worker safety requirements and shall be complied with at all times by the Contractors and sub-Contractors. These requirements are summarized in the Keesler Air Force Base Asbestos Operations and Management Plan.
The following steps are required by all personnel or Contractors doing work on Keesler AFB:
1.7.1 If the personnel or Contractor encounters what they think may be asbestos, they are required to stop and call the KAFB Asbestos Point of Contact (APOC) for the Keesler Environmental Section (BOS/CEV) at 228- 377-1262 or EMCS (228- 377-4179) after hours.
1.7.2 Once it is determined by the APOC that asbestos is present, the following actions described below are required (Only the APOC and Bioenvironmental are certified to make that determination).
SECTION 01 11 00 Page 8
1.9 NO ABATEMENT WORK IS TO BEGIN WITHOUT WRITTEN APPROVAL FROM THE APOC:
A Mississippi State certified asbestos abatement Contractor shall be used to conduct the abatement. Please note that non-friable asbestos can easily be made friable and become regulated.
1.9.1 Before: The following documents shall be submitted to the CO and approved in writing before abatement can begin:
1.9.1.1 10 Day MDEQ notification and return acknowledgment letter.
1.9.1.2 Asbestos Hazard Abatement Plan (to be certified by a
Mississippi Certified Management Planner and/or Certified Industrial Hygienist).
1.8.1.3 Asbestos Work Plan (scope of work, removal
procedures, worker protection, air monitoring, disposal location, containment procedures).
1.9.1.4 MDEQ Asbestos Abatement Certification for the
Company.
1.9.1.5 Supervisor’s qualifications and state certification.
1.9.1.6 CURRENT State Certifications (applications will not
be accepted) for all individuals working on site.
1.9.1.7 Respirator fit tests for all individuals.
1.9.1.8 Physicals for all individuals.
1.9.2 During: Once the submittals are approved in writing, the following actions are required:
1.9.2.1 The Contractor is required to set up their
containment areas, negative air machine, and critical barriers and obtain approval from the Asbestos POC to begin work.
1.9.2.2 The Asbestos POC routinely checks the abatement work
to ensure the containment area and critical barriers are secure, the workers are wearing the appropriate personal protective equipment, the asbestos-containing material is being bagged appropriately, and air monitoring is being conducted on the workers and outside the abatement area. This also includes reviewing the daily log maintained on site to assure no uncertified individuals are performing abatement work.
1.9.2.3 Upon completion of the abatement work, the Contractor contacts the Asbestos POC to conduct a walk-through of the area and approve all abatement has been completed and the area has been cleaned of asbestos fibers. This action will require at least a 24-hour period. Please reference cleaning procedures in the Asbestos Management and Operations Plan.
1.9.2.4 Air sampling results are required to be collected and submitted for approval by the Asbestos POC before the containment area, negative air machine, and critical barriers can be removed.
1.9.2.5 All asbestos waste shall be handled and disposed of
in accordance with State law. The Asbestos POC shall review the waste prior to leaving the base and the manifest will be signed
SECTION 01 11 00 Page 9 by a designated Keesler government representative. Contractors will not sign manifests for asbestos containing material (ACM).
1.9.3 After: After the abatement has been complete and approved by the Asbestos POC, the Contractor shall submit the following items in a post-job submittal to be maintained in the Asbestos Abatement Files:
1.9.3.1 Air sampling results.
1.9.3.2 Daily report logs.
1.9.3.3 Daily workers sign in/out sheets.
1.9.3.4 Waste manifest (Generator Copy)
1.9.4 The Asbestos POC and Environmental Section (BOS/CEV) are available at any time to provide asbestos awareness training and consultation to CM’s, PM’s, Contractors and Sub-Contractors prior to beginning the project.
1.10 REQUIRED LEAD-BASED PAINT MANAGEMENT PROCEDURES:
Appropriate OSHA worker protection is the responsibility of the employer. All projects will be monitored and inspected by BOS/CEV. The purpose of these instructions is to provide guidance to safely remove or encapsulate lead-based paint without causing a hazard. All work shall be performed in accordance with OSHA, MDEQ and any local regulations for all work and disposal. The regulations are divided into two parts;
a) lead-based paint on non-child occupied/non-target housing buildings and
b) child occupied/target housing buildings.
1.10.1 Non-child occupied/ commercial buildings:
1.10.1.1 For non-child-occupied/commercial buildings, the
minimum requirement for Contractors is to protect workers IAW OSHA requirements, use poly lay-down to collect paint chips, and turn into BOS/CEV for disposal. At minimum the supervisor of the project should be LBP trained and supply proof of certification before work begins. The Contractor shall notify BOS/CEV before start of any project. Contractor shall place plastic on the ground sufficient to capture all loosened paint chips and control water run-off. Removal methods preferred at Keesler AFB are the use of an approved chemical stripper or wet sanding methods for better collection of LBP chips and waste. These processes minimize lead dust and allow for maximum collection of LBP chips.
1.10.1.2 The Contractor shall meet with BOS/CEV prior to
beginning the project to discuss protective measures, best management practices (BMP’s), any landfill disposal, and maintenance of chips and their collection (until they are turned over to BOS/CEV).
1.10.1.3 Any buildings with lead-based paint, if bead blasted to remove old paint, shall be supervised by a Contractor with proper training. Bead blasting upon prior approval only (see preferred method above).
1.10.1.4 The Contractor, under OSHA rules, shall comply with
the lead-based paint rules (including notification to BOS/CEV, if the job is abatement), certify appropriate training, and maintain
SECTION 01 11 00 Page 10 personal monitors on workers until it is demonstrated there is no airborne lead risk.
1.10.1.5 BOS/CEV will inspect all projects involving Lead
Based Paint removal and any required documentation shall be provided to BOS/CEV prior to beginning work.
1.10.2 Child-occupied/target housing buildings:
1.10.2.1 Any child-occupied/target housing building older than 1978 shall be painted using Lead Paint Protocol, including poly-lay-down, collection of paint chips, and the Contractor shall always have a minimum of lead hazard training for all workers.
The Contractor shall notify BOS/CEV before start of any project.
1.10.2.2 A paint Contractor shall collect paint chips in
their own clean buckets and have BOS/CEV dispose (if contract requires BOS/CEV dispose). Contractor shall place plastic on the ground sufficient to capture all loosened paint chips and control water run-off.
1.10.2.3 For work on child-occupied/target housing buildings
falling under the Lead Paint Protocol, the Contractor shall use water or amended water when scraping or chipping. All members of the Contractor’s work force shall wear protective clothing and comply with all OSHA rules and regulations. OSHA regulation compliance is the employer’s responsibility and is subject to inspection by OSHA and the Base. Suggested PPE include foot protection (ex. Rubber Boots) worn while on the poly. All PPE shall be stored on the protective plastic when not in use and shall be decontaminated or disposed of in an approved manner.
Minimum respiratory protection for any OSHA “trigger task” such as scraping, manual sanding, demolition, heat gun and power tool cleaning is a half-mask air purifying respirator (APR) with HEPA filter that is at least 99.97 percent efficient (i.e., P100). APR fit tests evidence shall be provided for inspection. Other circumstances may warrant higher protection. PPE determination is the responsibility of the Contractor.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
SD-07 Certificates
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.
a. Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
b. No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines.
The Contracting Officer will identify designated smoking areas.
Section 01 14 00 Page 2
c. Working Hours
Regular working hours will consist of an 9 hour period established by the Contracting Officer, between 7 a.m. and 5 p.m., Monday through Friday excluding Government holidays.
d. Work Outside Regular Hours
The Contractor will not normally be permitted to work on weekends or on the following federal holidays (or the day the Federal Government observes these holidays) unless approved by the CO. (Sundays will generally not be approved for weekend work.) To be approved by the CO, the Contractor shall provide documentation showing work performed outside the hours of work will benefit the project’s mission. If approved by the CO, the Contractor shall coordinate such work with the CM at least seven (7) calendar days in advance:
New Year’s Day
Martin Luther King Jr.’s Birthday
Washington’s Birthday
Memorial Day
Juneteenth
Independence Day
Labor Day
Columbus Day
Veteran’s Day
Thanksgiving Day
Christmas Day
The following days are not federal holidays but may require work stoppage:
Special Olympics- Thursday through Sunday of First NON-Training weekend in May
1.3.2 Occupied Building
a. Work will be in an existing building which is occupied.
b. The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
c. Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the building during the construction period.
d. Relocate movable furniture approximately 6 feet away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
1.3.3 Project Phasing
a.All work shall be phased to allow the facility to remain occupied and operational during construction. Refer to Sheet G-04 for the project phasing Plan.
Section 01 14 00 Page 3
The entire second floor will be provided to the contractor first for HVAC quadrant and restroom work.
b. The contractor is to complete the second floor HVAC quadrant mechanical room work prior to work on the first floor HVAC quadrant mechanical rooms.
c. The entire first floor will be provided at one time.
d. Contractor to ensure occupied rooms are not to be disturbed during construction in adjacent spaces.
1.3.4 Utility Cutovers and Interruptions
d. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays.
Conform to procedures required in paragraph WORK OUTSIDE
REGULAR HOURS.
e. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
f. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and data are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
Such interruptions are further limited to 48 hours. This time limit includes time for deactivation and reactivation.
g. Operation of Station Utilities: Do not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. Notify the Contracting Officer within 7 calendar days giving reasonable advance notice when such operation is required.
1.4 SECURITY REQUIREMENTS
1.4.1 Passes:
a. Passes for Contractor employees may be requested through the 81st Civil Engineer Squadron. Pass requests shall be submitted in accordance with the procedures included in DAFFARS clause - 5352.242-9000. Requests shall include full name of employees as it appears on their identification, length of pass needed (up to 30 days), and days needed (if other than standard working hours).
b. Upon contract award, Superintendents will complete a Keesler AFB (KAFB) Form 299, Application for KAFB Identification Card. After issuance of a DBIDS identification card, the Superintendent will submit a KAFB Form 298, Appointment/Termination Record - Signature Card which will grant the Superintendent the role of a Pass and ID Alternate Issuing Official. This role will enable the designated superintendent to function as a sponsor and request passes for all contractor and sub-contractor personnel performing work on the installation cited in the contract. Contractor personnel who are non-US citizens must be approved and vetted through the Air Force Office of Special Investigations (AFOSI) before a pass is issued.
c. Paperwork required for passes: Only documents meeting the security
Section 01 14 00 Page 4 standards set by the REAL ID Act of 2005 will be accepted.
For vehicle operators:
Current driver license for each employee in support of work on Keesler AFB.
Vehicle Registration and Proof of Insurance.
For non-vehicle operators:
Current driver license, official ID card, or passport.
1.4.2 Reporting Requirements:
The Contractor shall comply with AFI 71-l0l, Volume¬1, Criminal Investigations and Volume-2, Protective Service Matters, requirements. Contractor personnel shall report to an appropriate authority, any information or circumstances of which they are aware may pose a threat to the security of DOD personnel, Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.
1.4.3 Physical Security:
a. Areas controlled by Contractor employees shall comply with Base Operations Plans/instructions for FPCON procedures, Random Antiterrorism Measures (RAMS) and local search/identification requirements. The Contractor shall safeguard all government property, including controlled forms, provided for Contractor use. At the close of each work period, government training equipment, ground aerospace vehicles, facilities, support equipment, and other valuable materials shall be secured.
b. The Contractor shall not employ persons for work on this contract if such employee is identified by the government or BOS Contract officials as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.
1.4.4 Vehicle Safety And Traffic Laws:
a. The Contractor and its employees shall comply with base traffic laws and regulations.
b. The Contractor shall ensure employees have a current and valid driver’s license and commercial permits/licenses for the type of vehicle operated, before allowing the employee to operate a Contractor-owned or rental vehicle on Keesler AFB.
c. The Contractor shall provide all vehicles to perform the requirements of the contract. All vehicles shall be in operable condition and meet local, state and federal safety requirements, and be specifically designed for the purpose intended for use. Vehicles shall have, clearly visible on each side, the Contractor company name, a unique vehicle identification number, in addition to all required Department of Transportation (DOT) markings and information.
d. Airfield Driving: All Contractors must have an escort or receive airfield drivers training prior to driving on the airfield IAW (AFI 13-213, 2.1.3.39.7). This training will be provided by Airfield Management at
B0233 PH:228-377-2215.
e. Cellular Phones: The use of cellular phones while operating a vehicle is prohibited while on Keesler AFB property.
Section 01 14 00 Page 5
1.4.5 Controlled Unclassified Information (CUI):
The Contractor shall comply with Executive Order 13556, “Controlled Unclassified Information”, regarding Controlled Unclassified Information (CUI), and requirements. The DoD Instruction (DoDI) 5200.48, “Controlled Unclassified Information”, sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding CUI material.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section
Section 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
15 CFR 772 Definition of Terms
15 CFR 773 Special Licensing Procedures
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
SD-02 Schedule of Values (SOV); G
1.3 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.4 SUPERVISION
1.4.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years’ experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual shall be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual shall be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project.
Section 01 30 00 Page 2
The superintendent is not permitted to also serve as the Quality Control (QC) Manager, as established in Section 01 45 00 QUALITY CONTROL, However, the Site Safety and Health Officer (SSHO) may serve dual roles as the SSHO and QC Manager. The QC Manager shall have qualifications in accordance with Section 01 45 00.
1.4.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual shall also have fluent English communication skills.
1.4.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative shall be on-site at all times during the performance of this contract until the work is completed and accepted.
1.4.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.5 PRECONSTRUCTION
Immediately after award, Contractor may coordinate with the Contracting Officer a time and place to meet for the Preconstruction meeting. The purpose of this is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:
daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.
Contractor shall present and discuss their basic approach to scheduling the construction work and any required phasing.
The Contractor shall submit a preliminary Schedule of Values (SOV) with their proposal for the Contracting Officer's review and approval. This preliminary SOV will establish the basis for all subsequent, post-award SOVs. Throughout the project, the Contractor shall update the SOV as directed by the Contracting Officer and obtain approval for all revisions.(See Section 01 33 00 for additional information).
1.5.1 Attendees
Section 01 30 00 Page 3
Contractor attendees shall include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.6 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried out to expeditious closure and turnover to the Client. Start planning the turnover process prior to start of construction and convene at regularly scheduled Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:
1.6.1 Red Zone Checklist
1.6.1.1. Contracting Officer's Technical Representative (COTR) or CM will provide the Contractor with a copy of the Red Zone Checklist template.
1.6.1.2. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.6.2 Meetings
1.6.2.1. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
1.6.2.2. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer. At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
1.6.2.3. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
1.6.2.4. During the Red Zone Meetings discuss with the COTR or CM any upcoming activities that require Government involvement.
1.6.2.5. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.7 MOBILIZATION
Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the job site.
1.8 JOBSITE MAINTENANCE AND STORAGE AREAS:
The Contractor shall maintain the jobsite and staging areas in conformance with the standards below and as directed by the CO.
1.8.1 Lay down/staging areas shall be kept neat and free of loose debris
Section 01 30 00 Page 4 at all times. Grass shall be cut and maintained regularly. Height and maintenance shall be consistent with Base standards and consistent with the immediate area.
1.8.2 Vehicle operation is restricted to paved parking areas and driving lanes. Driving or parking on any other surfaces, including sodded areas, sidewalks, landscaped areas, is prohibited. Exceptions may be granted on a case-by-case basis by the Contracting Officer, but such approval can be revoked without notice.
1.8.3 Jobsites and lay down/staging areas shall be enclosed with a 6’ high chain link fence with brown fabric screening unless otherwise noted. Materials and equipment may be stored inside storage units. Items stored in the lay down area shall be arranged neatly.
1.8.4 All temporary storage trailers and storage containers shall present a neat and clean appearance and shall be in a state of good repair and shall be located within the fenced area described in paragraph above.
1.8.5 If allowed by the contract and if approved by the CO, an office mobile unit may be located outside of a fenced area. At a minimum, this unit shall be in a paved area and shall present a neat, professional appearance. Unit shall be of Keesler standard colors, shall have presentable skirting and access stairs. Ancillary items, such as porches and canopies, shall be neat and painted Keesler brown. Contractor shall submit a picture of the proposed unit for approval before unit is moved to Base.
1.8.6 Execution of work may require excavation or other type of work both at and away from primary work area. These areas shall be secured, and work times shall be kept to a minimum. Open excavations shall be directly in progress or shall be covered directly after work is complete. Open excavations requiring extended period of inactivity shall be temporarily backfilled. In no case shall an excavation be open for more than 72 hours. Barricades, fences and other warning devices shall be maintained neatly at all times.
1.8.7 The Contractor shall maintain the premises, including any staging area or storage areas, free from accumulations of waste, debris, and rubbish caused by the Contractor’s work and shall minimize the spread of dust and flying particles. As work is completed, or at the end of each day, the site shall be cleaned, and all waste material shall be properly disposed of.
1.8.8 Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practical precaution to minimize danger to persons and damage to property. These precautions shall be coordinated through the CO and shall include closing all openings; removing all loose materials, tools, and equipment from exposed locations; securing all material, tools, equipment and construction work; as well as removing or securing scaffolding and other temporary work. The Contractor shall also coordinate all efforts with the CO and follow the Base Commander’s direction in the event of an upcoming storm or hurricane which may range from securing sites to complete demobilization of all equipment and material from the base.
PART 2 PRODUCTS
PART 3 EXECUTION
Section 01 30 00 Page 5
SECTION 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/23, CHG 1: 08/24
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASSOCIATION FOR THE ADVANCEMENT OF COST ENGINEERING,
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
AACE 84R-13 (2015) Planning and Accounting for Adverse Weather
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 67-17 (2017) Schedule Delay Analysis
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (2017) Administration -- Project Schedules
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G
Preliminary Project Schedule; G
Preliminary Schedule of Values; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler shall have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6, Microsoft Project, or equivalent project management software.
Representative shall have a comprehensive knowledge of Critical Path Method
SECTION 01 32 01.00 10 Page 2
( CPM) scheduling principles and application.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM) in a Gantt Chart format.
3.1.1 Scheduling Expectations Kickoff Meeting (SEKO)
In conjunction with the post award conference or preconstruction conference the Government and the Contractor may hold a separate and distinct Scheduling Expectations Kickoff Meeting (SEKO). The intent of this meeting is for the Government to review with the contractor the requirements of the scheduling specification, communicate the Government’s expectations regarding schedule development and management, and answer any questions the Contractor may have regarding the schedule requirements.
This meeting can be held the same day as the post award conference or preconstruction conference.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will have final project schedule approval.
3.2.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Non-procurement activities Original Durations (OD) are not to exceed 20 workdays or 30 calendar days.
3.2.3 Procurement Activities
Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.2.4 Mandatory Activities
SECTION 01 32 01.00 10 Page 3
Include the following activities in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of testing and air balance (TAB).
f. Submission of TAB specialist design review report.
g. Submission and approval of fire protection specialist.
h. Contractor's pre-final inspection.
i. Correction of punch list from Contractor's pre-final inspection.
j. Government's pre-final inspection.
k. Correction of punch list from Government's pre-final inspection.
l. Final inspection.
3.2.5 Government Activities
Show in schedule, Government and other agency activities that could impact progress. These activities include, but are not limited to approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.2.6 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.2.6.1 Project Start Date Milestone and Constraint
The first activity in the project schedule shall be a start milestone titled "NTP Acknowledged," which shall have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.2.6.2 End Project Finish Milestone and Constraint
The last activity in the schedule shall be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the
SECTION 01 32 01.00 10 Page 4 longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
3.2.6.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.2.6.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.2.6.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.2.7 Adverse Weather
Ensure anticipated adverse weather is accounted for in the Project Schedule. AACE 84R-13 provides methodologies for techniques in planning for adverse weather. The preferred methodology is the use of a weather calendar. If a method other than a weather calendar is proposed, discuss the reason during the SEKO meeting.
Keesler AFB, MS Weather Station indicates expected inclement weather days each month as follows: Jan: 10; Feb: 8; Mar: 9; Apr: 7’ May: 9; Jun: 9; Jul:
9; Aug: 12; Sept: 8; Oct: 5; Nov: 8; Dec: 9.”
3.2.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If a weather calendar is used its…