This is a Total Building Commissioning (TBCx) specification section for the Stennis Hall Renovation project at Keesler Air Force Base in Biloxi, Mississippi (MAHG 17-1095). The specification establishes a systematic, quality-focused process to verify and document that all commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet project requirements, with the primary objective of reducing cost and performance risks while increasing value to owners, occupants, and users.
The Commissioning Firm must be a first-tier, financially and corporately independent subcontractor that employs qualified Commissioning Specialists. The Lead Commissioning Specialist (CxC) must have a minimum of five years of commissioning experience including two similar projects and hold certification from NEBB (SCA), ACG (CxA), ICB/TABB, BCA (CCP), AEE (CBCP), University of Wisconsin-Madison (QCxP), or ASHRAE (BCxP). Mechanical Commissioning Specialists require five years of HVAC commissioning experience with relevant certifications; Electrical Commissioning Specialists require five years of experience inspecting and testing electrical equipment. The scope of commissioned systems includes heating, ventilating, air-conditioning, refrigeration systems, and associated controls. Key deliverables include Commissioning Firm qualifications (due within 60 days of Notice to Proceed), Interim and Final Construction Phase Commissioning Plans, Pre-Functional Checklists, Certificates of Readiness, Functional Performance Test and Integrated Systems Test Checklists, Issues Log, training documentation, Initial and Final Commissioning Reports, and an Updated Final Commissioning Report following the 9-month warranty inspection. Testing procedures encompass Pre-Functional Checks, Functional Performance Tests (100 percent sample for central plant equipment and system-level equipment, 20 percent sample for identical single-zone equipment), and Integrated Systems Tests to verify interactive operations between systems. The specification requires monthly commissioning coordination meetings during system installation and bi-weekly meetings within 30 days of scheduled functional performance testing, with the Government Commissioning Authority (CxG) retaining final approval authority for all commissioning deliverables.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAHG 17-1095 STENNIS HALL RENOVATION
KEESLER AFB, BILOXI, MS
SECTION 01 91 00.15 20
TOTAL BUILDING COMMISSIONING
02/21
PART 1 GENERAL
Total Building Commissioning (TBCx) is a systematic, quality-focused process for enhancing the delivery of a project that focuses on verifying and documenting that all of the commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the project requirements. The purpose is to reduce the cost and performance risks associated with delivering facilities projects, and to increase value to owners, occupants, and users.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 202 (2018) Commissioning Process for Buildings and Systems
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
ANSI/SMACNA 014 (2013) HVAC Systems Commissioning Manual, 2nd Edition
1.2 DEFINITIONS
Commissioning Process (Cx) - a quality-focused process for enhancing the delivery of a project. Refer to ASHRAE 202 for a comprehensive description of the commissioning process.
Commissioning Provider (CxC) - The entity who leads, plans, and coordinates the Commissioning Team. The terms Commissioning Provider, Commissioning Firm, Lead Commissioning Specialist, Commissioning Specialist, and Commissioning Authority (CA or CxA) when used by sustainable Third Party Certification (TPC) programs, are interchangeable.
Government Commissioning Authority (CxG) – The Government retains the authority as the commissioning authority for oversight, assurance of the entire commissioning process, and final approval of all commissioning
SECTION 01 91 00.15 20 Page 1
Attachment 10 -
FA301026R0010
MAHG 17- 1095 STENNI S HALL RENOVATI ON
KEESLER AFB, BI LOXI , MS
del i ver abl es.
1. 3 COMMUNI CATI ON WI TH THE GOVERNMENT
The Lead Commi ssi oni ng Speci al i st ( CxC) must submi t al l pl ans, schedul es, r epor t s, and document at i on di r ect l y t o t he Cont r act i ng Of f i cer ' s Repr esent at i ve concur r ent wi t h submi ssi on t o t heManager .
The Lead Commi ssi oni ng Speci al i st must have di r ect communi cat i on wi t h t he Cont r act i ng Of f i cer ' s Repr esent at i ve r egar di ng al l el ement s of t he commi ssi oni ng pr ocess; however , t he Gover nment has no di r ect cont r act aut hor i t y wi t h t he Lead Commi ssi oni ng Speci al i st .
1. 4 SYSTEMS TO BE COMMI SSI ONED
Coor di nat e commi ssi oni ng and qual i t y cont r ol act i v i t i es f or t he f ol l owi ng syst ems, equi pment , and associ at ed cont r ol s. Syst em- speci f i c r equi r ement s ar e l ocat ed i n t he associ at ed speci f i cat i on Sect i ons. Commi ssi on t he f ol l owi ng syst ems, equi pment , and associ at ed cont r ol s i n accor dance wi t h t hi s sect i on and t he i nspect i on, t est i ng, and qual i t y cont r ol r equi r ement s of t hei r r espect i ve sect i ons:
Heat i ng, vent i l at i ng, ai r - condi t i oni ng, and r ef r i ger at i on syst ems ( mechani cal and passi ve) and associ at ed cont r ol s
1. 5 COMMI SSI ONI NG TEAM
The Commi ssi oni ng t eam wi l l i ncl ude, but i s not l i mi t ed t o t he f ol l owi ng t eam member s.
Ensur e al l Const r uct i on Act i v i t i es f or syst ems t o be commi ssi oned ar e coor di nat ed wi t h t he appr opr i at e commi ssi oni ng t eam member s.
a. Lead Commi ssi oni ng Speci al i st ( CxC)
b. Qual i t y Cont r ol Manager ( QCM)
c. Sub- Cont r act or Repr esent at i ves f or each t r ade r esponsi bl e f or const r uct i on/ i nst al l at i on of syst ems t o be commi ssi oned
d. Const r uct i on Manager ( CM) f . Techni cal Commi ssi oni ng Speci al i st s f or each syst em t o be commi ssi oned
g. TAB Repr esent at i ve
h. Equi pment manuf act ur er r epr esent at i ves i . Cont r act i ng Of f i cer j . Gover nment Commi ssi oni ng Aut hor i t y ( CxG)
k. Gover nment Accept ance Test i ng Repr esent at i ves l . I nst al l at i on Mai nt enance Repr esent at i ve
SECTI ON 01 91 00. 15 20 Page 2
m. Faci l i t y End User
1. 6 PROJECT SCHEDULE
I ncl ude t he f ol l owi ng t asks i n t he pr oj ect schedul e r equi r ed by Sect i on.
Ensur e suf f i c i ent t i me i s schedul ed t o compl et e each i t em. The or der of i t ems l i s t ed bel ow i s not i nt ended t o i mpl y a speci f i ed sequence:
a. Submi ssi on and appr oval of t he Commi ssi oni ng Fi r m Qual i f i cat i ons
d. Submi ssi on and appr oval of t he I nt er i m and Fi nal Const r uct i on Phase Commi ssi oni ng Pl ans
e. Commi ssi oni ng Ki ckof f Coor di nat i on Meet i ng f . Regul ar Commi ssi oni ng Coor di nat i on Meet i ngs
g. I nst al l at i on of per manent ut i l i t i es ( gas, wat er , el ect r i c) j . Manuf act ur er ' s Equi pment St ar t - Up f or each of t he syst ems t o be commi ssi oned
k. Submi ssi on and appr oval of t he Compl et ed Pr e- Funct i onal Checkl i st s l . Submi ssi on and appr oval of Cer t i f i cat e of Readi ness f or each syst em t o be commi ssi oned
m. Funct i onal Per f or mance Test i ng f or each syst em t o be commi ssi oned
n. I nt egr at ed Syst ems Test s
o. Post - t est def i c i ency cor r ect i on f or each syst em t o be commi ssi oned
p. Re- Test i ng r . Tr ai ni ng f or each of t he syst ems t o be commi ssi oned
s. Submi ssi on and appr oval of t he I ni t i al and Fi nal Commi ssi oni ng Repor t s t . Seasonal Test i ng
v. Updat ed Commi ssi oni ng r epor t
1. 7 SUBMI TTALS
Gover nment appr oval i s r equi r ed f or submi t t al sSubmi t t he f ol l owi ng:
SD- 06 Test Repor t s
I nt er i m Const r uct i on Phase Commi ssi oni ng Pl an; G
Fi nal Const r uct i on Phase Commi ssi oni ng Pl an; G;
I ni t i al Commi ssi oni ng Repor t ; G
I ssues Log; G
Compl et ed Pr e- Funct i onal Checkl i st s; G
SECTI ON 01 91 00. 15 20 Page 3
SD- 07 Cer t i f i cat es
Commi ssi oni ng Fi r m; G
Cer t i f i cat e Of Readi ness; G
SD- 11 Cl oseout Submi t t al s
Fi nal Commi ssi oni ng Repor t ; G
Updat ed Fi nal Commi ssi oni ng Repor t ; G
Fi nal Commi ssi oni ng Repor t ( eNot ebook) ; S
Updat ed Fi nal Commi ssi oni ng Repor t ( eNot ebook) ; S
1. 8 COMMI SSI ONI NG FI RM
Empl oy t he ser vi ces of a Commi ssi oni ng Fi r m and al l Commi ssi oni ng Speci al i st s r equi r ed t o per f or m wor k f or t hi s pr oj ect . The Commi ssi oni ng Fi r m must be a f i r st - t i er subcont r act or t hat i s f i nanci al l y and cor por at el y i ndependent f r om cont r act or and al l ot her subcont r act or s and t he Desi gner of Recor d.
a. Submi t t he Commi ssi oni ng Fi r m' s and Commi ssi oni ng Speci al i st s ' qual i f i cat i ons, i ncl udi ng t he name of t he f i r m and each CxC and each cer t i f i cat i on, no l at er t han 60 cal endar days af t er Not i ce t o Pr oceed.
b. I f , f or any r eason, a speci al i st l oses a cer t i f i cat i on dur i ng t hi s per i od, i mmedi at el y not i f y t he Cont r act i ng Of f i cer and submi t anot her Commi ssi oni ng Speci al i st f or appr oval . Val i dat e al l wor k per f or med f or t hi s pr oj ect by t he CxC who l ost a cer t i f i cat i on by an appr oved successor .
1. 8. 1 Commi ssi oni ng Speci al i st s ( CxC)
Assi gn Lead Commi ssi oni ng Speci al i st and ot her appr opr i at e Commi ssi oni ng Speci al i st s f or t he syst ems t o be commi ssi oned.
1. 8. 1. 1 Lead Commi ssi oni ng Speci al i st ( CxC)
Lead Commi ssi oni ng Speci al i st ( CxC) coor di nat es al l aspect s of t he commi ssi oni ng pr ocess. Dut i es i ncl ude l eadi ng and over seei ng t he commi ssi oni ng wor k, and act i ng as t he pr i mar y poi nt of cont act f or t he commi ssi oni ng wor k. CxC may ser ve as a syst ems Speci al i st i f al l r equi r ement s f or bot h desi gnat i ons ar e met . CxC must have a mi ni mum of f i ve year s of commi ssi oni ng exper i ence, i ncl udi ng t wo pr oj ect s of s i mi l ar s i ze and compl exi t y t o t hi s pr oj ect .
CxC must be cer t i f i ed i n one of t he f ol l owi ng:
NEBB qual i f i ed Syst ems Commi ssi oni ng Admi ni st r at or ( SCA)
ACG Cer t i f i ed Commi ssi oni ng Aut hor i t y ( CxA)
I CB/ TABB Cer t i f i ed Commi ssi oni ng Super vi sor
BCA Cer t i f i ed Commi ssi oni ng Pr of essi onal ( CCP)
SECTI ON 01 91 00. 15 20 Page 4
AEE Cer t i f i ed Bui l di ng Commi ssi oni ng Pr of essi onal ( CBCP)
Uni ver si t y of Wi sconsi n- Madi son Qual i f i ed Commi ssi oni ng Pr ocess Pr ovi der ( QCxP)
ASHRAE Bui l di ng Commi ssi oni ng Pr of essi onal ( BCxP) .
1. 8. 1. 2 Commi ssi oni ng Speci al i st s
Commi ssi oni ng Speci al i st s wi t h t he f ol l owi ng qual i f i cat i ons must per f or m t he t echni cal wor k associ at ed wi t h each syst em t o be commi ssi oned:
a. Mechani cal Commi ssi oni ng Speci al i st : The t echni cal wor k associ at ed wi t h mechani cal syst ems t o be commi ssi oned must be per f or med by a Commi ssi oni ng Speci al i st cer t i f i ed by NEBB, ACG, I CB/ TABB, AEE, Uni ver si t y of Wi sconsi n- Madi son, ASHRAE, or BCA i n t he commi ssi oni ng of HVAC syst ems wi t h f i ve year s of exper i ence i n t he commi ssi oni ng of HVAC syst ems.
b. El ect r i cal Commi ssi oni ng Speci al i st : The t echni cal wor k associ at ed wi t h el ect r i cal syst ems t o be commi ssi oned must be per f or med by an engi neer i ng t echni c i an wi t h f i ve year s of exper i ence i nspect i ng, t est i ng, and cal i br at i ng el ect r i cal di st r i but i on and gener at i on equi pment , syst ems, and devi ces.
1. 8. 2 Commi ssi oni ng St andar d
Compl y wi t h t he r equi r ement s of t he commi ssi oni ng st andar d under whi ch t he Commi ssi oni ng Fi r m and Speci al i st s qual i f i cat i ons ar e appr oved. When t he f i r m and speci al i st s ar e cer t i f i ed by BCA, AEE, ASHRAE, or t he Uni ver si t y of Wi sconsi n- Madi son, compl y wi t h t he r equi r ement s of one of t hese accept abl e st andar ds: ACG Commi ssi oni ng Gui del i ne, NEBB Commi ssi oni ng St andar d, ANSI / SMACNA 014, or ASHRAE 202. Compl y wi t h appl i cabl e NETA t est i ng st andar ds f or el ect r i cal syst ems.
a. I mpl ement al l r ecommendat i ons and suggest ed pr act i ces cont ai ned i n t he Commi ssi oni ng St andar d and el ect r i cal t est st andar ds.
b. Use t he Commi ssi oni ng St andar d f or al l aspect s of Commi ssi oni ng, i ncl udi ng cal i br at i on of i nst r ument s.
c. Wher e t he i nst r ument manuf act ur er cal i br at i on r ecommendat i ons ar e mor e st r i ngent t han t hose l i s t ed i n t he Commi ssi oni ng St andar d, adher e t o t he manuf act ur er cal i br at i on r ecommendat i ons.
d. Al l qual i t y assur ance pr ovi s i ons of t he Commi ssi oni ng St andar d such as per f or mance guar ant ees ar e par t of t hi s cont r act .
e. The Commi ssi oni ng Speci al i st s must devel op commi ssi oni ng pr ocedur es f or any syst ems or syst em component s not cover ed i n t he Commi ssi oni ng St andar d.
f . Use any new r equi r ement s, r ecommendat i ons, and pr ocedur es publ i shed or adopt ed by t he body r esponsi bl e f or t he Commi ssi oni ng St andar d at t he t i me of pr oj ect awar d.
g. I f t her e i s a conf l i c t bet ween t he r equi r ement s of t he cont r act document s and t he commi ssi oni ng st andar d used, t he cont r act document s
SECTI ON 01 91 00. 15 20 Page 5 t ake pr ecedent .
1. 9 I SSUES LOG
The Commi ssi oni ng Speci al i st devel ops and mai nt ai n an I ssues Log f or t he syst ems t o be commi ssi oned. The i ssues l og document s and t r acks r esol ut i on of def i c i enci es i dent i f i ed dur i ng submi t t al r evi ews, i nspect i on, and t est i ng. At any poi nt dur i ng const r uct i on, any commi ssi oni ng t eam member f i ndi ng def i c i enci es may communi cat e t hose def i c i enci es i n wr i t i ng t o t he Commi ssi oni ng Speci al i st f or i ncl usi on i nt o t he I ssues Log. For each i ssue, t he I ssues Log i ncl udes, but i s not l i mi t ed t o, a uni que r ef er ence number , descr i pt i on of t he i ssue wi t h cont r act r equi r ement r ef er enced, l ocat i on of or equi pment name/ t ags exhi bi t i ng t he i ssue, t he i ni t i al s of t he i ndi v i dual ' s name whom r epor t ed t he i ssue, t he dat e of f i r st obser vat i on, t he pr oposed r esol ut i on of t he i ssue and dat e pr oposed, t he dat e of any subsequent obser vat i ons wi t h appl i cabl e addi t i onal i nf or mat i on, and t he dat e of i mpl ement at i on of t he f i nal r esol ut i on of t he i ssue as conf i r med by t he Commi ssi oni ng Speci al i st and Cont r act i ng Of f i cer . I ssues must not be del et ed f r om t he i ssues l og.
CxC must submi t t he I ssues Log mont hl y and wi t hi n t hr ee wor ki ng days f r om changes t o t he I ssue Log. The CxC i s r esponsi bl e f or di st r i but i ng t he I ssues Log t o t he Commi ssi oni ng Team.
1. 10 CERTI FI CATE OF READI NESS
Pr i or t o schedul i ng Funct i onal Per f or mance Test s, t he Qual i t y Cont r ol Manager must i ssue a Cer t i f i cat e of Readi ness f or each syst em, cer t i f y i ng t hat pr e- f unct i onal checks have been compl et ed, open i ssues have been r esol ved, and t he syst em i s r eady f or Funct i onal Per f or mance Test i ng. The Cer t i f i cat e of Readi ness must i ncl ude, f or each syst em t o be commi ssi oned, equi pment and syst em st ar t - up r epor t s; compl et ed Pr e- Funct i onal Checkl i st s; Test i ng, Adj ust i ng, and Bal anci ng ( TAB) Repor t ; I ssues Log;
and HVAC Cont r ol s St ar t - Up Repor t s t o t he ext ent appl i cabl e t o t he syst em. Si gn and dat e t he Cer t i f i cat e of Readi ness, and i ncl ude si gnat ur es and dat es f r om t he CxC; t he Qual i t y Cont r ol Repr esent at i ve; t he Mechani cal , El ect r i cal , Cont r ol s, and TAB subcont r act or r epr esent at i ves.
Submi t t he Cer t i f i cat e of Readi ness f or each syst em 14 cal endar days pr i or t o Funct i onal Per f or mance Test s of t hat syst em. Do not schedul e Funct i onal Per f or mance Test s f or a syst em unt i l t he Cer t i f i cat e of Readi ness i s appr oved by t he Gover nment .
PART 2 PRODUCTS
Not used.
PART 3 EXECUTI ON
3. 1 CONSTRUCTI ON SUBMI TTAL REVI EWS
Coor di nat e const r uct i on submi t t al document r evi ews f or commi ssi oned syst ems and assembl i es wi t h t he CxC. The commi ssi oni ng submi t t al r evi ew does not r epl ace t he desi gner of r ecor d ( DoR) or Gover nment submi t t al r evi ew.
The CxC must i dent i f y const r uct i on submi t t al s t o be pr ovi ded by t he cont r act or f or t he commi ssi oned syst ems. The CxC must eval uat e const r uct i on submi t t al s f or compl i ance wi t h t he cont r act document s.
SECTI ON 01 91 00. 15 20 Page 6
I ncl ude a copy of t he submi t t al document r evi ew t r ansmi t t al and r esponse i n t he Commi ssi oni ng Repor t .
3. 2 COMMI SSI ONI NG KI CKOFF MEETI NG
Conduct a Commi ssi oni ng Ki ckof f Meet i ng, l ed by t he CxC, af t er appr oval of t he Commi ssi oni ng Fi r m and Commi ssi oni ng Speci al i st s, and no l at er t han 60 days f ol l owi ng const r uct i on not i ce t o pr oceed. Di scuss t he commi ssi oni ng pr ocess i ncl udi ng cont r act r equi r ement s, l i nes of communi cat i on, r ol es and r esponsi bi l i t i es, schedul es, document at i on r equi r ement s, i nspect i on and t est pr ocedur es, and l ogi st i cs as speci f i ed i n t hi s sect i on.
The Qual i t y Cont r ol t eam, Desi gner of Recor d, and t he Gover nment must at t end t hi s meet i ng. I nvi t e t he User and t o at t end t hi s meet i ng.
3. 3 REGULAR COMMI SSI ONI NG COORDI NATI ON MEETI NGS
CxC must conduct mont hl y commi ssi oni ng coor di nat i on meet i ngs when i nst al l at i on of commi ssi oned syst ems begi ns. Pr ovi de st at us of commi ssi oned syst ems, open i ssues l og i t ems, out st andi ng submi t t al s, and upcomi ng commi ssi oni ng act i v i t i es. Conduct bi - weekl y commi ssi oni ng coor di nat i on meet i ngs wi t hi n 30 days of t he schedul ed dat e f or f unct i onal per f or mance t est i ng.
3. 4 CONSTRUCTI ON PHASE COMMI SSI ONI NG PLANS
The I nt er i m Const r uct i on Phase Commi ssi oni ng Pl an i dent i f i es t he commi ssi oni ng and t est i ng st andar ds and out l i ne t he over al l commi ssi oni ng pr ocess, t he commi ssi oni ng schedul e, t he commi ssi oni ng t eam member s and r esponsi bi l i t i es, l i nes of communi cat i on, document at i on r equi r ement s f or t he const r uct i on phase of t he pr oj ect . Submi t t he I nt er i m Const r uct i on Phase Commi ssi oni ng Pl an 14 cal endar days af t er t he Const r uct i on Commi ssi oni ng Coor di nat i on Meet i ng and 14 days pr i or t o t he st ar t of const r uct i on of t he bui l di ng envel ope.
The Fi nal Const r uct i on Phase Commi ssi oni ng Pl an i ncl udes t he i nf or mat i on pr ovi ded i n t he I nt er i m Const r uct i on Phase Commi ssi oni ng Pl an as wel l as t he Pr e- Funct i onal Checkl i st s, I nt egr at ed Syst ems Test Checkl i st s, and Funct i onal Per f or mance Test Checkl i st s f or each bui l di ng, f or each syst em r equi r ed t o be commi ssi oned, and f or each component f or i ncl usi on i n t he Fi nal Const r uct i on Phase Commi ssi oni ng Pl an. Submi t t he Fi nal Const r uct i on Phase Commi ssi oni ng Pl an no l at er t han 90 cal endar days pr i or t o t he st ar t of Pr e- Funct i onal Checks. Once appr oved, f i l e t he appr oved pl an i n t he Sust ai nabi l i t y eNot ebook.
3. 4. 1 Pr e- Funct i onal Checkl i st s
The Pr e- Funct i onal Checkl i st s must i ncl ude i t ems f or physi cal i nspect i on or t est i ng t hat demonst r at e t hat i nst al l at i on and st ar t - up of equi pment and syst ems i s compl et e. Ref er t o par agr aph PRE- FUNCTI ONAL CHECKS.
Pr e- f unct i onal checkl i st s must be t ai l or ed t o ver i f y t he speci f i c i nst al l at i on r equi r ement s and det ai l s of t he const r uct i on document s and manuf act ur er ' s i nst r uct i ons.
3. 4. 2 Funct i onal Per f or mance Test Checkl i st s
Funct i onal Per f or mance Test Checkl i st s must i ncl ude pr ocedur es t hat expl ai n, st ep- by- st ep, t he act i ons and expect ed r esul t s t hat wi l l demonst r at e t hat t he syst em per f or ms i n accor dance wi t h t he cont r act .
SECTI ON 01 91 00. 15 20 Page 7
Ref er t o par agr aph FUNCTI ONAL PERFORMANCE AND I NTEGRATED SYSTEMS TESTS.
I ncl ude t he f ol l owi ng sect i ons and det ai l s appr opr i at e t o t he syst ems bei ng t est ed i n t he Funct i onal Per f or mance Test Checkl i st s:
a. Not abl e syst em f eat ur es i ncl udi ng i nf or mat i on about cont r ol s t o f aci l i t at e under st andi ng of syst em oper at i on
b. Concl usi ons and r ecommendat i ons. Concl usi ons must c l ear l y i ndi cat e i f syst em does or does not per f or m i n accor dance wi t h cont r act r equi r ement s. Recommendat i on must c l ear l y i ndi cat e t hat t he syst em shoul d or shoul d not be accept ed by t he Gover nment .
c. Test condi t i ons i ncl udi ng dat e, begi nni ng and endi ng t i me, and begi nni ng and endi ng out door ai r condi t i ons
d. At t endees
e. I dent i f i cat i on of t he equi pment i nvol ved i n t he t est f . Cont r ol syst em f eat ur e i dent i f i cat i on
g. Poi nt - t o- poi nt obser vat i ons i ncl udi ng demonst r at i ng syst em f l ow met er s and sensor s have been cal i br at ed and ar e cor r ect l y di spl ayed on t he Oper at or wor k st at i on
h. Act uat or oper at i on obser vat i ons demonst r at i ng act uat or r esponses t o commands f r om t he cont r ol syst em i . As- f ound condi t i on of t he syst em oper at i on j . Li st of t est i t ems wi t h st ep number s al ong wi t h t he cor r espondi ng f eat ur e or cont r ol oper at i on, i nt ended t est pr ocedur e, expect ed syst em r esponse, and pass/ f ai l i ndi cat i on.
k. Space f or comment s f or each t est i t em.
3. 4. 3 I nt egr at ed Syst ems Test Checkl i st s
I nt egr at ed Syst ems Test Checkl i st s must i ncl ude t est pr ocedur es t hat expl ai n, st ep- by- st ep, t he act i ons and expect ed r esul t s t hat wi l l demonst r at e t hat t he i nt er act i ve oper at i ons bet ween syst ems per f or ms i n accor dance wi t h t he cont r act . Ref er t o par agr aph FUNCTI ONAL PERFORMANCE AND I NTEGRATED SYSTEMS TESTS. I ncl ude t he f ol l owi ng sect i ons i n t he I nt egr at ed Syst ems Test Checkl i st s:
a. Not abl e f eat ur es of t he i nt er connect ed syst ems or gani zed by di sci pl i ne i ncl udi ng i nf or mat i on t o f aci l i t at e under st andi ng of syst em oper at i on
b. Concl usi ons and r ecommendat i ons. Concl usi ons must c l ear l y i ndi cat e i f t he syst ems do or do not per f or m i n accor dance wi t h cont r act r equi r ement s. Recommendat i on must c l ear l y i ndi cat e t hat t he syst ems shoul d or shoul d not be accept ed by t he Gover nment
c. Test condi t i ons i ncl udi ng dat e and begi nni ng and endi ng t i me
d. I dent i f i cat i on of t he equi pment and syst ems i nvol ved i n t he t est
e. Li st of t est i t ems wi t h st ep number s al ong wi t h t he cor r espondi ng f eat ur e or cont r ol oper at i on, i nt ended t est pr ocedur e, expect ed syst em
SECTI ON 01 91 00. 15 20 Page 8 r esponse, and pass/ f ai l i ndi cat i on.
f . Space f or comment s f or each t est i t em.
3. 5 PRE- FUNCTI ONAL CHECKS
Compl et e one Pr e- Funct i onal Checkl i st f or each i ndi v i dual i t em of equi pment or syst em f or each syst em r equi r ed t o be commi ssi oned i ncl udi ng, but not l i mi t ed t o, duct wor k, pi pi ng, equi pment , f i x t ur es ( l i ght i ng and pl umbi ng) , and cont r ol s. I ndi cat e commi ssi oni ng t eam member i nspect i on and accept ance of each Pr e- Funct i onal Checkl i st i t em by i ni t i al s.
Accept ance of each Pr e- Funct i onal Checkl i st i t em by each t eam member i ndi cat es t hat i t em conf or ms t o t he cont r act document s and accept ed desi gn i n t hei r ar ea of r esponsi bi l i t y . Commi ssi oni ng Speci al i st accept ance of each Pr e- Funct i onal Checkl i st i t em i ndi cat es t hat each i t em has been i nst al l ed cor r ect l y and i n accor dance wi t h cont r act document s[ and t he Owner ' s Pr oj ect Requi r ement s ( OPR) ] . Submi t t he i ni t i al ed and Compl et ed Pr e- Funct i onal Checkl i st s no l at er t han 7 cal endar days af t er compl et i on of i nspect i on of al l checkl i st s i t ems f or each syst em. I ncl ude manuf act ur er st ar t - up checkl i st s associ at ed wi t h equi pment wi t h t he submi ssi on of t he Pr e- Funct i onal Checkl i st s.
3. 6 FUNCTI ONAL PERFORMANCE AND I NTEGRATED SYSTEMS TESTS
Demonst r at e t hat al l syst em component s have been i nst al l ed, t hat each cont r ol devi ce and i t em of equi pment oper at es, and t hat t he syst ems oper at e and per f or m, i ncl udi ng i nt er act i ve oper at i on bet ween syst ems, i n accor dance wi t h cont r act document s[ and t he OPR] . Pr ovi de al l mat er i al s, ser vi ces, and l abor r equi r ed t o per f or m t he Pr e- Funct i onal Checks, I nt egr at ed Syst ems Test s, and Funct i onal Per f or mance Test s.
Commi ssi oni ng Speci al i st ' s dut i es i ncl ude l eadi ng and document i ng al l t est s f or t he syst ems t o be commi ssi oned wi t h appr opr i at e sub- cont r act or s per f or mi ng t he Test s. The r epr esent at i ves l i s t ed i n t he par agr aph Commi ssi oni ng Team must at t end t he t est s.
Per f or m I nt egr at ed Syst ems Test s onl y af t er t he Funct i onal Per f or mance Test s f or each associ at ed syst em ar e compl et ed wi t h al l def i c i enci es r esol ved and af t er t he r el at ed Funct i onal Per f or mance Test Checkl i st s have been si gned by each commi ssi oni ng t eam member .
3. 6. 1 Test Schedul i ng and Coor di nat i on
Conduct I ni t i al Funct i onal Per f or mance Test s as soon as al l cont r act wor k i s compl et ed, r egar dl ess of t he season. Devel op and i mpl ement means of ar t i f i c i al l oadi ng t o demonst r at e, t o a r easonabl e l evel of conf i dence, t he abi l i t y of t he HVAC syst ems t o handl e peak seasonal l oads. Schedul e Funct i onal Per f or mance Test s f or each syst em onl y af t er t he Cer t i f i cat e of Readi ness has been appr oved by t he Gover nment f or t he syst em. Cor r ect al l def i c i enci es i dent i f i ed t hr ough any pr i or r evi ew, i nspect i on, or t est act i v i t y bef or e t he st ar t of Funct i onal Per f or mance Test s.
Funct i onal Per f or mance Test s and I nt egr at ed Syst ems Test s must be per f or med wi t h t he CxG pr esent . Gover nment r eser ves t he r i ght t o wi t ness al l t est s. Coor di nat e t est schedul e wi t h Gover nment r epr esent at i ves.
3. 6. 2 Test i ng Pr ocedur es
Funct i onal per f or mance t est i ng i s conduct ed by s i mul at i ng condi t i ons at
SECTI ON 01 91 00. 15 20 Page 9 cont r ol devi ces t o i ni t i at e a cont r ol syst em r esponse. Over - wr i t i ng cont r ol i nput val ues t hr ough t he cont r ol syst em i s not accept abl e unl ess appr oved appr oved by t he Cont r act i ng Of f i cer . Do not s i mul at e condi t i ons when damage t o t he syst em or bui l di ng may r esul t .
Fol l ow t he Funct i onal Per f or mance Test f r om t he appr oved Fi nal Const r uct i on Phase Commi ssi oni ng Pl an. Per f or m Funct i onal Per f or mance Test s f or each i t em of equi pment and each syst em r equi r ed t o be commi ssi oned. Ver i f y al l sensor cal i br at i ons, cont r ol r esponses, saf et i es, i nt er l ocks, oper at i ng modes, sequences of oper at i on, capaci t i es, l i ght i ng l evel s, and al l ot her per f or mance r equi r ement s compl y wi t h cont r act , r egar dl ess of t he speci f i c i t ems l i s t ed wi t hi n t he checkl i st s pr ovi ded. I n gener al , t est i ng must pr ogr ess f r om equi pment or component s t o subsyst ems t o syst ems t o i nt er l ocks and connect i ons bet ween syst ems.
Commi ssi oni ng Speci al i st s ar e r esponsi bl e f or det er mi ni ng t he or der of component s and syst ems t o be t est ed. I ndi cat e accept ance of each i t em of equi pment and syst ems t est ed by s i gnat ur e of each commi ssi oni ng t eam member f or each t est . The Qual i t y Cont r ol Repr esent at i ve, Commi ssi oni ng Speci al i st s, and Cont r act i ng Of f i cer ' s Repr esent at i ve, i f pr esent , must i ndi cat e accept ance af t er t he equi pment and syst ems ar e f r ee of def i c i enci es.
3. 6. 3 I nt egr at ed Syst ems Test s
Fol l ow t he I nt egr at ed Syst ems Test Checkl i st s f r om t he appr oved Fi nal Const r uct i on Phase Commi ssi oni ng Pl an. I nt egr at ed Syst ems Test s must be per f or med f or t he i nt er act i ve oper at i on bet ween syst ems such as HVAC syst ems, f i r e pr ot ect i on syst ems, back- up el ect r i cal suppl y, ener gy gener at i on syst ems, and ot her syst ems, and ver i f y cor r ect i nt er act i ve oper at i on, accept abl e speed of r esponse, and ot her cont r act r equi r ement s f or bot h nor mal and f ai l ur e modes. Exampl es of I nt egr at ed Syst ems Test s i ncl ude t he cor r ect oper at i on of HVAC syst ems dur i ng emer gency syst em act i vat i on, cor r ect oper at i on of uni nt er r upt i bl e power suppl i es or ener gy gener at or s and connect ed syst ems, or l i ght i ng syst em oper at i on dur i ng power out age or emer gency syst em act i vat i on.
3. 6. 4 Sampl e St r at egy
Per f or m Funct i onal Per f or mance Test s and I nt egr at ed Syst ems Test s f or al l syst ems and equi pment t o be commi ssi oned usi ng t he sampl e st r at egy i dent i f i ed her ei n. Compl et e a Funct i onal Per f or mance Test Checkl i st f or each i t em of equi pment or syst em t o be t est ed. For sampl e s i zes l ess t han 100 per cent f or s i mi l ar equi pment , t he Cont r act i ng Of f i cer ' s Repr esent at i ve r eser ves t he r i ght t o sel ect t he speci f i c equi pment or syst em t o be t est ed dur i ng t est i ng. Per f or m I nt egr at ed Syst ems Test s f or al l syst ems and equi pment havi ng i nt er act i ve oper at i on. Compl et e an I nt egr at ed Syst ems Test Checkl i st f or each i t em of equi pment or syst em.
Test al l cent r al pl ant equi pment , pr i mar y ai r handl i ng uni t s, and pr ocess cool i ng or heat i ng equi pment . Test al l syst em- l evel equi pment ser vi ng mul t i pl e zones. Twent y per cent sampl e t est i ng i s al l owed f or l ar ge gr oups of i dent i cal equi pment wi t h i dent i cal cont r ol l er s ser vi ng si ngl e zones such as ai r t er mi nal uni t s, f an coi l uni t s, uni t ar y equi pment , l i ght i ng zones, and pl umbi ng f i xt ur es.
3. 6. 4. 1 100 Per cent Sampl e Pr ocedur es
Syst ems or equi pment f or whi ch 100 per cent sampl e s i ze ar e t est ed f ai l i f one or mor e of t he t est pr ocedur es r esul t s i n di scover y of a def i c i ency
SECTI ON 01 91 00. 15 20 Page 10 and t he def i c i ency cannot be r esol ved wi t hi n 5 mi nut es dur i ng t he t est .
Re- t est t o t he ext ent necessar y t o conf i r m t hat t he def i c i enci es have been cor r ect ed wi t hout negat i vel y i mpact i ng t he per f or mance of t he r est of t he syst em.
3. 6. 4. 2 Less t han 100 Per cent Sampl e Pr ocedur es
Randoml y t est each sampl e gr oup of i dent i cal equi pment . Sampl e s i ze must be at l east t hr ee uni t s. I f 10 per cent of t he uni t s i n t he f i r st sampl e f ai l t he f unct i onal per f or mance t est s, t est a second sampl e gr oup, t he same si ze as t he f i r st sampl e gr oup. The second sampl e must not i ncl ude any uni t s f r om t he f i r st sampl e gr oup.
I f 10 per cent of t he uni t s i n t he second sampl e f ai l , t est al l r emai ni ng uni t s. I f at any poi nt f r equent f ai l ur es occur , and t est i ng becomes mor e t r oubl eshoot i ng t han ver i f i cat i on, t he CxC may st op t he t est i ng and r equi r e t he cont r act or t o per f or m and document a checkout of t he r emai ni ng uni t s pr i or t o cont i nui ng f unct i onal t est i ng.
3. 6. 5 Abor t ed Test s and Re- Test i ng
Abor t any t est i f any def i c i ency pr event s successf ul compl et i on of t he t est or i f any r equi r ed commi ssi oni ng t eam member i s not pr esent f or t he t est . Re- t est af t er al l def i c i enci es i dent i f i ed dur i ng t he or i gi nal t est have been cor r ect ed. Cont r act i ng Of f i cer may wi t hhol d payment equi val ent t o l ost t i me, r e- t est i ng, and abor t ed t est s. These cost s may i ncl ude sal ar y, t r avel cost s, and per di em f or Gover nment commi ssi oni ng t eam member s.
3. 7 TRAI NI NG PLAN
CxC must r evi ew t he t r ai ni ng pl an f or t r ai ni ng associ at ed wi t h t he equi pment and syst ems t o be commi ssi oned, checki ng t hat each pl an has t he t r ai ner name, t r ai ner cont r act i nf or mat i on, t r ai ni ng schedul e and l ocat i on. Submi t r evi ew at l east 30 days pr i or t o t he f i r st t r ai ni ng event . I ncor por at e CxC r evi ew comment s pr i or t o submi t t i ng t r ai ni ng pl an i n accor dance wi t h Sect i on 01 78 23 OPERATI ON AND MAI NTENANCE DATA.
Updat e and r esubmi t t he t r ai ni ng pl an based on any cor r ect i ve act i on t aken.
Document t r ai ni ng at t endance usi ng t r ai ni ng at t endance r ost er s and submi t compl et ed at t endance r ost er s no l at er t han 7 cal endar days f ol l owi ng t he compl et i on of t r ai ni ng f or each syst em t o be commi ssi oned.
3. 7. 1 Syst ems Manual
The Syst ems Manual i ncl udes t he Basi s of Desi gn, syst em si ngl e l i ne di agr ams, as- bui l t sequences of oper at i on and cont r ol s dr awi ngs, as- bui l t cont r ol set poi nt s, r ecommended schedul e f or sensor and act uat or cal i br at i on, r ecommended schedul e of mai nt enance when not i n t he O&M manual s, r ecommended r e- t est i ng schedul e wi t h pr oposed t est i ng f or ms, and f ul l equi pment war r ant y i nf or mat i on f or al l commi ssi oned syst ems.
I ncor por at e CxC r evi ew comment s pr i or t o submi t t i ng Syst ems Manual i n accor dance wi t h Sect i on 01 78 23 OPERATI ON AND MAI NTENANCE DATA. Updat e and r esubmi t t he syst em manual i nf or mat i on based on any cor r ect i ve act i on t aken dur i ng t he war r ant y per i od.
SECTI ON 01 91 00. 15 20 Page 11
3. 8 COMMI SSI ONI NG REPORT
Submi t an I ni t i al Commi ssi oni ng Repor t no l at er t han 14 cal endar days f ol l owi ng commi ssi oni ng t eam accept ance of al l Funct i onal Per f or mance Test s and I nt egr at ed Syst ems Test s, wi t h t he except i on of Seasonal Test s.
Submi t a Fi nal Commi ssi oni ng Repor t upon compl et i on of t r ai ni ng and t r end l og r evi ews. I ncl ude t he f ol l owi ng i nf or mat i on i n t he Fi nal Commi ssi oni ng Repor t :
a. An execut i ve summar y descr i bi ng t he over al l commi ssi oni ng pr ocess, t he r esul t s of t he commi ssi oni ng pr ocess, out st andi ng def i c i enci es and r ecommended r esol ut i ons, and seasonal t est i ng t hat must be schedul ed f or a l at er dat e. I ndi cat e, i n t he execut i ve summar y, whet her t he syst ems meet t he r equi r ement s of t he cont r act document s[ and t he OPR] .
b. A l i s t of def i c i enci es di scover ed dur i ng t he commi ssi oni ng pr ocess and t he cor r ect i ve act i ons t aken i n t he r epor t .
c. Compl et ed Bui l di ng Envel ope I nspect i on Checkl i st s, Pr e- Funct i onal Checkl i st s, Funct i onal Per f or mance Test Checkl i st s, I nt egr at ed Syst ems Test Checkl i st s, t he Fi nal Const r uct i on Phase Commi ssi oni ng Pl an, t he I ssues Log, Tr ai ni ng At t endance Rost er s, t he Desi gn Revi ew Repor t s, Submi t t al Revi ew Repor t , and t he appr oved TAB Repor t .
3. 9 WARRANTY PHASE SI TE VI SI T
The Lead Commi ssi oni ng Speci al i st must v i s i t t he bui l di ng s i t e concur r ent wi t h t he 9 mont h war r ant y i nspect i on t o i nspect bui l di ng syst em equi pment and r evi ew bui l di ng oper at i on wi t h t he bui l di ng oper at i ng/ mai nt enance st af f , and i dent i f y any def i c i ency of t he bui l di ng syst ems t o oper at e i n accor dance wi t h t he cont r act document s. The Commi ssi oni ng Speci al i st must not i f y t he Cont r act i ng Of f i cer of any i dent i f i ed def i c i enci es and t he pr oposed cor r ect i ve act i on. Submi t Updat ed Fi nal Commi ssi oni ng Repor t and Syst ems Manual s, document i ng t he r esul t s of t he war r ant y phase i nspect i on. I ncl ude ot her war r ant y phase act i v i t i es, such as Seasonal t est i ng r esul t s.
- - End of Sect i on - -
SECTI ON 01 91 00. 15 20 Page 12
| 01 91 00.15 20 - TOTAL BUILDING COMMISSIONING |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.3 COMMUNICATION WITH THE GOVERNMENT |
| 1.4 SYSTEMS TO BE COMMISSIONED |
| 1.5 COMMISSIONING TEAM |
| 1.6 PROJECT SCHEDULE |
| 1.7 SUBMITTALS |
| 1.8 COMMISSIONING FIRM |
| 1.8.1 Commissioning Specialists CxC |
| 1.8.1.1 Lead Commissioning Specialist CxC |
| 1.8.1.2 Commissioning Specialists |
1.8.2 Commissioning Standard
| 1.9 ISSUES LOG |
| 1.10 CERTIFICATE OF READINESS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 CONSTRUCTION SUBMITTAL REVIEWS |
| 3.2 COMMISSIONING KICKOFF MEETING |
| 3.3 REGULAR COMMISSIONING COORDINATION MEETINGS |
| 3.4 CONSTRUCTION PHASE COMMISSIONING PLANS |
| 3.4.1 Pre-Functional Checklists |
| 3.4.2 Functional Performance Test Checklists |
| 3.4.3 Integrated Systems Test Checklists |
| 3.5 PRE-FUNCTIONAL CHECKS |
| 3.6 FUNCTIONAL PERFORMANCE AND INTEGRATED SYSTEMS TESTS |
| 3.6.1 Test Scheduling and Coordination |
| 3.6.2 Testing Procedures |
| 3.6.3 Integrated Systems Tests |
| 3.6.4 Sample Strategy |
| 3.6.4.1 100 Percent Sample Procedures |
| 3.6.4.2 Less than 100 Percent Sample Procedures |
3.6.5 Aborted Tests and Re-Testing
| 3.7 TRAINING PLAN |
| 3.7.1 Systems Manual |
| 3.8 COMMISSIONING REPORT |
| 3.9 WARRANTY PHASE SITE VISIT |