I n t e g r i t y - S e r v i c e - E x c e l l e n c e Headquarters U.S. Air Force
Pre-Proposal Conference & Site Visit Mr. Brian T. Reese Contracting Officer, 338 SCONS
Mr. Tony Williams Program Manager, AETC A4PM
Mr. Richard Milhollon Chief COR, 82 CES/CEY
July 24, 2017 Sheppard AFB Base Maintenance Support
Good morning ladies and gentlemen! Welcome to the Sheppard Base Maintenance Support Pre-proposal conference and site visit. My name is Brian Reese, Procuring Contracting Officer, from Randolph AFB in San Antonio, TX. We’ll begin with introductions to Team Sheppard and move along to the Mission brief provided by Mr. Todd Raines.
Source Selection Information See FAR 2.101 & 3.104
82 TRW MISSION BRIEF
Mr. Todd Raines 82d Contracting Squadron
AGENDA & ANNOUNCEMENTS
Conference Agenda
| Monday, 24 Jul 17 | ||
| 0800 – 0815 | Assembly and Introductions | Mr. Brian T. Reese, PCO |
| 0815 – 0830 | 82 TRW Mission Brief | Mr. Todd Raines, 82 CONS |
| 0830 – 0930 | - Announcements |
- PWS Requirements
- Performance Oversight
- RFP & Evaluation Process Mr. Brian T. Reese, PCO Mr. Tony Williams, PM Mr. Richard Milhollon, Chief COR Mr. Brian T. Reese, PCO
| 0930 – 1200 | Site Visit Bus Tour (Part I) | ||
| 1200 – 1315 | Lunch | ||
| 1330 – 1530 | Site Visit Bus Tour (Part II) | ||
| 1530 – 1630 | Assembly for Questions & Answers | Government Panel | |
| Tuesday, 25 Jul 17 | |||
| 0800 – 1100 | Site Visit Bus Tour (Part III) | ||
| 1100 – 1200 | Lunch | ||
| 1200 – TBD | 1-on-1 meetings / 30 Minute Sessions | ||
| *No more than 3 reps per company | Government Panel |
During the tour of the facilities, please limit your verbal questions but please write them down. We’ll gather here again for brief questions and answers after the tour and we will provide verbal answers if we can. But please remember, no verbal answers are official until they are written and posted on FBO.
Announcements
| RFP RELEASED: 11 Jul 17 |
| Proposal Due: 12:00 p.m. CST, 8 Sep 17 |
| If any conflicts are identified between this presentation, the site visit & RFP, the RFP shall take precedence |
| No Gov’t responses are ‘official’ until provided in writing |
| Q&A Ground Rules - |
| Hold all questions until the open Q&A session |
| Submit written questions on Q&A forms provided |
| Formal written responses will be posted to FBO and take precedence over any verbal responses provided today |
| Other Administrative/Emergency Information |
As you know, the RFP was released on 11 Jul and your proposals are due on 8 Sep at 12:00 PM Central Standard Time.
I must make a few disclaimers here. First, if anything said today differs from what’s stated in the RFP, the formal RFP will take precedence. Also any verbal Government responses are not official until provided in writing and posted on FBO. We’ll have a open Q&A session at the end of this briefing so please try to hold your questions, unless something that needs to be corrected during the briefing.
Now, Mr. Milhollon who is the Chief COR here at Sheppard will give you some useful facility orientation and local information. Please note photographs and video are strictly prohibited so please refrain from using your devices during the site visit.
PWS REQUIREMENTS & CONTRACT SURVEILLANCE
Mr. Richard Milhollon Chief COR, 82 CES/CEY
Mr. Tony Williams Program Manager, HQ AETC
I will turn it over to Mr. Williams and Mr. Milhollon for the PWS requirements and Contract surveillance.
| Base Maintenance services for the 82d Training Wing & 80th Flying Training Wing |
| PWS provides requirements for the following functional areas: |
(10) Installation Management
(11) Operations Management
(12) Installation Engineering
(14) Readiness and Emergency Management
| Appendices provide additional information |
| Workload data, Publications, Maps, Required Reports, Plans, Special Training, GFP, etc. |
| Technical Library is available by AMRDEC File Transmittal |
Overview
| All Service Functions: |
| Programs that apply across all areas of the contracts |
| Safety |
| Security |
| Records Management |
| Quality Control |
| Environmental Protection |
| Disaster Preparedness |
| Property Management |
| Information System Management |
Performance Work Statement
| Installation Management Functions: |
| Civil Engineering Financial Management |
| Real Property Management |
| Legacy and Next Generation Information Technology |
| Environmental Management (including Utility Privatization & Enhanced Use Lease) |
| Operations: |
| Operations Management |
| Operations |
| Heavy Repair |
| Infrastructure Systems |
| Facility Systems |
| Requirements and Optimization |
| Transportation and Utilities Activity Management Plans |
| Installation Engineering: |
| Engineering Management |
| Portfolio Optimization |
| Project Management |
| Readiness and Emergency Management: |
| Emergency Management |
| Notable Items: |
| Two Geographically Separated Units |
| Texoma Annex (Lake Texoma), Frederick Airfield |
| Support for two Wings, 82d TRW & 80th FTW |
| Govt Provided Services – 10 CE Service contracts |
| Housing privatized in 2007 – Property owner, Balfour Beatty Communities (BBC) |
| Utilities privatization could result in some contract requirements being removed |
CE Service Contracts: Custodial Services, Elevator Maintenance, Grounds Maintenance (SAFB, Frederick & Lake Texoma), Kitchen Exhaust Hoods Cleaning, Oil/water/grease Traps, PCM (Paint & signs)(Greater than 32 sq. ft. of painted area), Integrated Solid Waste Management (SAFB & Lake Texoma)(Includes Recycling), Environmental Services (ESOHMS & HMMP), Wastewater Treatment (Lake Texoma)
Housing Management Office provides oversight and referral services in support of privatized housing on/off base, as well as local community referral services; Directly manages three Permanent Party dormitories with a total of 436 bed spaces; Accountable for furnishings in 19 dormitories, with 5K+ bed spaces; Oversees three warehouses for lodging and dormitories; total Sheppard AFB furnishings worth $65M
| Contract Oversight & Performance Evaluation |
| Provided by Contracting Officer Representatives assigned to |
82 CES/CEY Performance Management Function
| Based on PWS requirements |
| Contracting Officer Representative |
| ~10 CORs assigned |
| Government commitment - Fair & objective performance evaluations based on the SDS |
| Open/frequent/cooperative communication with SP |
Contract Oversight
| Performance Management |
| Contract Management |
| On-site CORs for all BMC Functional Areas (4) |
| Periodic Surveillances |
| Performance Documentation & Customer Feedback |
| Chief, Performance Management Office (PMO) |
| Performance Assessment Analysis to Performance Management Review (PMR) based on COR files |
| Quarterly Performance Assessments with SP & PMR |
| Administrative Contracting Officer (ACO) |
| Ensure SP complies with contract T&Cs |
| Annually document SP performance in CPARS |
| Management Structure |
| Multi-Functional Team approach with SP |
Contract Oversight & Performance Evaluation
Performance Management Review (PMR), chaired by the 82 Mission Support Group Commander or delegate.
| Inspection Methods and Frequency |
| Periodic Inspections (Monthly, Quarterly & Annual) |
| 100% Inspection when Deliverables are performed/submitted |
| Customer Feedback – Positive & Negative |
| Initial Performance Review within 30 calendar days after mobilization |
| Incentives for Successful Performance |
| Favorable CPARS |
| IOP Eligibility |
| Unacceptable Performance - Failure to Meet Performance Standards |
| Negative CPAR ratings, re-performance at no additional cost to the government, corrective action request |
| IOP Ineligibility |
| PMR Performance Assessment Analysis Review |
| Quarterly |
| Emphasis on schedule, performance and process improvement |
Annual Execution Reviews
Performance Requirement Performance Plan & Metrics
RFP & EVALUATION PROCESS
Mr. Brian T. Reese Procuring Contracting Officer, AFICA 338 SCONS
Tentative Proposal Milestones
| Action | Date |
| RFP Issued and Posted | 11 Jul 17 |
| Pre-Proposal Conference/Site Visit | 24 Jul- 25 Jul 17 |
| Questions Due | 3 Aug 17 |
| Proposal (All Volumes) Due | 8 Sep 17 |
| Contract Award | 1 May 18 |
| Base Year Period of Performance (including Mobilization) | 1 Sep 18 |
These are some of the projected major milestone dates and events.
Acquisition Approach
| Firm-Fixed-Price (FFP) Contract |
| Full & Open Competition |
| Basis of Award: Lowest Priced Technically Acceptable (LPTA) |
| Technical factor - evaluated on a acceptable/unacceptable basis |
| Govt intends to evaluate & award without discussions |
| Ensure initial proposal contains the best terms from a price and technical standpoint |
I am not saying anything here that wasn’t already clearly stated in the RFP. But I’d like to bring your attention to the last bullet. I keep saying the same thing on every site visit I conduct…please make sure your initial proposal represents your best price and technical approaches. Don’t automatically assume the Govt. will hold discussions to bring your technical proposal to an acceptable rating. Please keep in mind the Govt. always reserves the right to award without discussions, if it is in the best interest for the Govt.
(Possible example: It could be price and/or non-price variables such as time and effort it will take to hold discussions may not be worth the contract cost savings.)
Discussions & Evaluation Process
| Step 1: Rank all proposals by total proposed prices from low to high |
| Step 2: Evaluate Price, Technical & Past Performance proposals concurrently starting with lowest priced offeror |
| The Govt may cease evaluations & award to the lowest priced, technically acceptable offeror |
| Source Selection Authority (SSA) will make award decision or determine a competitive range for the purpose of holding discussions. |
| If it is in the Government's best interest to conduct discussions, the CO may recommend the SSA establish a competitive range IAW FAR 15.306(c). If there is a high volume of proposals received, for the purposes of efficiency, the CO may limit the number proposals in the competitive range to an efficient number that will permit an efficient competition for this LPTA source selection. |
As used above, the term “Acceptable Proposal” means the proposal is rated acceptable in the Technical and Past Performance factors, the price is determined fair and reasonable and the CO determines the offeror to be responsible IAW FAR 9.104-1.
As stated in the RFP, your proposals will be racked and stacked by the initial prices from low to high. Then our price, technical and past performance teams will start the evaluation concurrently and independently with the lowest price offeror. This is where your basic math accuracy in Section B becomes very important because inaccurate total price can mean your proposal being looked at or not looked at.
Under Step 2, the first sub-bullet is clear. If the lowest priced offer with an acceptable technical and past performance represents the best value for the Govt., we may cease further evaluation and award without discussions.
The SSA may make the decision to award without discussion or establish a competitive range to hold discussions. It is also noteworthy to note that if it is in the Government's best interest to conduct discussions, the CO may recommend the SSA establish a competitive range IAW FAR 15.306(c). **If there is a high volume of proposals received, for the purposes of efficiency, the CO may limit the number proposals in the competitive range to an efficient number that will permit an efficient competition for this LPTA source selection.
Proposal Organization
| Volume I: Price |
| Volume II: Technical |
| Volume III: Past Performance |
| Volume IV: Other Contracting Considerations |
Volume I: Price and Other Contracting Considerations
| Price must be Fair, Reasonable & Balanced |
| Price Data |
| Whole dollar unit prices only! |
| Price all FFP CLINs only! |
| Total Evaluated Price (TEP) = Sum of all FFP CLINs |
| Use Schedule B Worksheet |
| Subcontracting Plan |
| Required for Large Business offerors |
| Not required with proposal submission |
| Negotiated with apparently successful offeror |
| Must be determined acceptable prior to award |
When evaluating price, the team will determine if price is reasonable and balanced. The price team will collaborate with the technical team to conduct a technical analysis as a part of the overall price analysis by using many tools listed in FAR 15.403.
In Section B, please provide prices for Firm-Fixed-Price CLINs and ensure the unit prices are a whole dollar amount with no hidden decimals in your electronic file submission. The Total Evaluated Price, TEP, equals the sum of all fixed-price CLINs. It is important to note Schedule B will only be accepted using the excel worksheet provided in the RFP; any other format will not be accepted so please adhere to the instructions in Section L for filling this out.
Subcontracting Plan is required by all large business offerors; however, it is not an evaluation criterion. The apparent awardee’s Subcontracting Plan will be reviewed under Responsibility Determination and will be determined acceptable prior to award.
Volume II: Technical
| Pass/Fail basis |
| Ratings: |
| Acceptable |
| Unacceptable |
Failure to meet subfactor requirement may result in a “technically unacceptable” determination
| Table A-1 Technical Ratings | |
| Rating | Description |
| ACCEPTABLE | Proposal meets the requirements of the solicitation. |
| UNACCEPTABLE | Proposal does not meet the requirements of the solicitation. |
Technical Subfactors
| Subfactor 1: Mobilization Approach |
| Subfactor 2: Technical Approach |
| Subfactor 3: Program Management & Staffing Approach |
| Subfactor 4: Performance Management/Quality Control Approach |
All these elements subject to technical evaluation are listed under each Subfactor in the RFP.
The Government technical evaluation team will evaluate the technical proposal of the lowest priced offeror, and, if needed thereafter, the technical proposal(s) of higher priced offerors, in order of price rank, assigning a rating of Acceptable or Unacceptable. Any proposal evaluated shall be evaluated utilizing the four (4) technical subfactors listed below, as they apply to the PWS.
Note: Any subfactor evaluated as “Unacceptable” will render the entire proposal “Unacceptable” and, therefore, unawardable.
Volume III: Past Performance
| Recency: Performed within 3 yrs of RFP issuance date |
| Must have minimum of 1 year documented performance from RFP issuance date |
| Performance meeting criteria will be evaluated in entirety |
| Relevancy: Scope, magnitude & complexity |
| Table A-2 Relevancy Ratings | |
| RATING | DESCRIPTION |
| Relevant | Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires. |
| Not Relevant | Present/past performance effort involved little, or none of the scope and magnitude of effort and complexities the solicitation requires. |
Recency: The Govt. will consider proposed past performance information that occurred within the last 3 years of the date of the solicitation and will include at least 6-month of documented performance prior to the date of issuance of the solicitation. Once the proposed contract meets this recency criteria, the Govt. will evaluate performance information for the entire contract period of performance.
Relevancy: It has 3 components – Scope, Magnitude and Complexity.
Scope refers to BMC work. When judging similarity, we will look at BMC work performed as the prime contractor.
Magnitude refers to the duration and contract dollar value for base maintenance operations similar to those described in the solicitation. In other words, we’ll assess how closely the term of the evaluated contract related to the overall 7-yr period of the RFP. For the dollar value, we’ll assess how closely the dollar value of the evaluated contract compared to this solicitation based on IGE, dollar values of the current contract and other similar contracts within the DoD.
Complexity refers to the number and volume of primary PWS areas. For the number, the evaluation team will assess how closely the evaluated contract relates to the primary PWS functions such as if the contract effort includes important PWS areas that Mr. Williams and Mr. Milhollon briefed you earlier. The bottom line: the more you have experience in these critical functions, the more credit will be given to complexity. For the volume, we will consider the number of functional areas, etc. as size indicators of the complexity of the requirement. So the relevancy increases as an evaluated contract performed a greater volume of work when compared to the requirements at Sheppard. The Govt. will assign a separate rating for scope, magnitude and complexity, and then integrate these ratings into a combined relevancy rating for each contract. Each contract evaluated will be given a rating of R or NR.
Volume III: Past Performance Performance Quality Assessment Ratings:
| TABLE A-3 - Past Performance Evaluation Ratings | |
| RATING | DESCRIPTION |
| Acceptable | Based on the Offeror’s performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort or the Offeror’s performance record is unknown. (See note below). |
| Unacceptable | Based on the Offeror’s performance record, the Government does not have a reasonable expectation that the Offeror will be able to successfully perform the required effort. |
| Note: In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the Offeror shall be determined to have unknown past performance. In the context of Acceptability/Unacceptability, “Unknown” shall be considered “Acceptable.” |
To assess performance quality ratings, the Govt. will make an integrated assessment of your past performance as it relates to factors such as your meeting basic contract PWS and technical requirements, adhering to schedules, including the administrative aspects of performance, and commitment to customer satisfaction. For this, we’ll rely primarily on CPARS and PPQ but we also conduct phone interviews to get more performance information or validate the CPARS or PPQ rater’s comments. We’ll also do an independent research through the DoD contract data base such as PPIRS or Google, in effort to find other similar requirements that you have performed that meet our recency criteria. The Past Performance team gather information on already adjudicated ratings and substantiate discrepancies we may find.
After all that, the team will assign a performance quality assessment rating of Acceptable or Unacceptable per offeror based on integrated recency, relevancy, performance quality on all evaluated contracts.
Performance Incentive Plan
| Incentive Option Periods (IOPs) |
| 6th & 7th option periods are “IOPs” |
| IOPs are not “Award Term Options”…IOPs not entitlements to additional years of performance |
| Eligibility for IOPs contingent upon “Satisfactory” or better CPARS ratings |
| ACO determines eligibility within 45 days of CPARS finalization |
| Eligible IOPs will be executed IAW FAR 52.217-9, Option to Extend the Term of the Contract |
| IOP pricing evaluated as a part of the TEP |
There are two Incentive Option Periods, IOPs, the 6th and 7th option periods. When you become eligible for one or both IOPs based on at least “Satisfactory” CPARS ratings on all categories, it still does not guarantee additional performance periods. Once eligible, each IOP will be executed in accordance with -9, as a regular option exercise. So even after the IOP eligibility early on, if the performance starts to decline, the Govt. has the right not to exercise the 6th or/and 7th options. The IOP pricing will be evaluated as a part of the TEP.
IOP Implementation
This flow chart was included in Attachment#11 of the RFP. Was this chart clear for you to see how the IOP implementation will be carried out?
Tips for Building Solid Proposal
| Price |
| Ensure Section B math is accurate |
| Whole dollar unit prices…no hidden decimal places |
| Technical |
| Review PWS thoroughly & consider CBA related restrictions (i.e. limited cross-utilization) |
| Use Govt provided workload data in RFP |
| Justify annual manning adjustments (increase/decrease) w/supporting calculations |
I’d like to provide you with some unsolicited advice on how to build a good proposal. Some are just emphasis pertaining to the Sheppard requirement and some are based on my experience from having gone through more than enough source selections. So I humbly ask you to pay attention to these tips.
For the Price Factor – I am going to repeat one more time to double check your math and adhere to whole dollar unit prices in Section B.
For the Technical Factor – Please review the PWS and CBA very carefully. When building your workforce, please use the workload data provided in the RFP. Often, I’ve seen offerors take initiative to use their own workload estimation and build the manpower accordingly. The Govt. can only evaluate it against what we posted in the RFP. We cannot validate the accuracy of any privately developed workload estimation. Also, when the annual manning increases or decreases, please provide sufficient explanation with supporting calculations. We cannot assume anything.
Tips for Building Solid Proposal
| Past Performance (PPI) |
| Provide detailed description of the characteristics of each contract |
| Identify and explain which aspects of the past/current contracts are relevant to PWS and how they relate |
| If proposing subcontractor, teaming and/or JV partner, establish a nexus between the SP and the proposed partner (i.e. Be specific about what meaningful/critical work it will perform and what role it will play) |
For the Past Performance Information – please include sufficient description of each contract in PPI. We want to know what you actually performed under that contract and relate it to the scope, magnitude and complexity determination. Also provide justification why you think that particular contract is relevant to the Keesler requirement. And this is important…when proposing a subcontractor, teaming or joint venture partner, be specific as to what that partner will perform and what role that partner will play. A vague statement like, “we’ll borrow the company X’s technical expertise” or “Company X will play a important management role to enhance overall performance” provides very little useful information for us.
Miscellaneous
| Question Submittal |
| Questions must be submitted IAW Section L: |
| Excel Spreadsheet |
| Ensure all questions are submitted in writing: |
| Magdalenda Hudson-Murray |
| Brian T. Reese |
| AMRDEC File Transmittal |
| Technical Library shall be requested from the POCs above and provided via online transmittal (AMRDEC). Once received files may be viewed and downloaded within 14 days before the link expires. If expired, a new request to the POCs above must be made |
Question submittal shall be done in both formats as this is an administrative requirement on our end and we greatly appreciate your cooperation submitting it as required in Section L. The only POCs for this requirement are the individuals listed above. Offerors are prohibited from having contact with personnel outside this list regarding this requirement.
Experience with AMRDEC? In order to facilitate organized file transmittal we are using AMRDEC as the tool to get you the RFP attachments. The only documents which will be uploaded on FBO are the RFP documents and any amendments. Any revised documents as a result of any amendments require you to request access from the individuals above. Offerors have 14 days to open, view and download the documents transmitted via AMRDEC. If for some reason you forget to download or lose the link all you need to do is send us another request. Also, if any RFP attachments are revised as a result of an amendment, a new AMRDEC request needs to be sent so you can access the amended documents. Any questions?
QUESTION AND ANSWER SESSION
15 Minute Break – Please pass/bring question forms to front
I know many of you have a plenty of experience and attended many site visits like this one, perhaps more than you want to count. But I sincerely hope this briefing was useful to you in some way. I am pretty open and straightforward in my communication with industry because I’d really like to get solid proposals from you. No hidden agenda. Self interest? Absolutely. So I ask you to communicate with me the same way and I will make myself available to answer all your questions since I am your only point of contact. Please bring your questions and see you in 15 min.
SITE VISIT
Site Visit
RULES OF ENGAGEMENT
| Pictures/video allowed in certain areas; please refrain from pictures/video in designated areas per tour guide |
| Questions during site visit – ask/write them! |
| Please be patient as we document your questions |
| Verbal answers will be given |
| Official answers will be posted to FBO |
SUMMARY
Summary
| RFP released 11 Jul 17 |
| Questions due NLT 12:00PM CST, 3 Aug 17 |
| Proposals due NLT 12:00PM CST, 8 Sep 17* |
| Mr. Brian T. Reese, and Ms. Magdalenda Hudson-Murray, are the sole individuals authorized to contact offerors |
| Prior to submitting proposals, offerors are highly encouraged to verify accuracy, include all required documentation, ensure clarity of intent, and comply with all RFP requirements |
| Please submit questions as soon as possible: |
| Magdalenda.Hudson-Murray.1@us.af.mil |
| Brian.Reese.2@us.af.mil |
*Ask if the due date for questions is sufficient time for vendors to review the package and submit valid questions prior to proposals being due.