Text version

FA2816-16-R-0008 – Questions & Answers #6

Posted 29 November 2016

NOTE: The Government responses are provided for informational purposes only. Any responses below shall NOT change the requirements as spelled out in RFP FA2816-16-R-0008, unless issued via an Amendment to the Solicitation via Standard Form 30.

Question #1:

We would like to replace one of the PPQ's with one from a much more relevant contract. Can we replace one of the PPQ's?

Answer #1:

Yes. Email the Contract Specialist, 2d Lt Ryan Kittle at ryan.kittle@us.af.mil, no later than the proposal deadline regarding which PPQ to remove.

Question #2:

Will the government accept PPQ Evaluations for past performance projects under a private owner or prime contractor?

Answer #2:

Yes.

Question #3:

How many Task Orders were issued under the previous SABER contract, by year, and what was the total amount awarded, by year?

Answer #3:

The numbers as displayed in Table 1: Planned Government Funding, located on page 70 of the solicitation, paragraph 1.1 – Budget/Funding Information, represent projected contract award values for each year. Information pertaining to the current SABER contract FA2816-11-D-0001 may be publicly accessed at www.fpds.gov.