FA2816-16-R-0008 – Questions & Answers #3

Posted 16 November 2016

NOTE: The Government responses are provided for informational purposes only. Any responses below shall NOT change the requirements as spelled out in RFP FA2816-16-R-0008, unless issued via an Amendment to the Solicitation via Standard Form 30.

Question #1:

We wonder if you inform us if the job walk regarding SABER Project is mandatory or not?

Answer #1:

No. The site visit is not mandatory.

Question #2:

Would the Government please provide clarification above and beyond references to the SOW as to what, exactly, is required for the Seed Project 35% design (RFP Section L, Subfactor 2, Criteria 2 Minimum Design Documentation (p. 77 of 92)? Our concern is that what is being requested would require the retention of a third party A-E firm if new 35% level design drawings are being requested because the provided 35% design documentation is not adequate.

Answer #2:

No additional design or changes to the Government-provided drawings located in “FA2816-16-

R-0008 Attachment 5: Seed Project ACJP161091 Drawings” are required. Offerors shall submit the current version of the drawings as they appear in Attachment 5, to meet the requirements of

Volume 2: Technical Proposal, Subfactor 2 – Seed Project, Criteria 2 – Minimum Design

Documentation.