This document is a Question and Answer Form for Project Number SXHT 16-1037, which involves repairing streets and parking areas at Patrick Space Force Base (PSFB) in Florida. The Q&A addresses multiple technical details about the construction project, including pavement and base replacement specifications, parking stop handling, testing requirements, and striping methods. Key clarifications include replacing existing asphalt and limestone base with 3.0" of asphalt paving in two courses and 9" of limestone base, removing and reinstalling existing parking stops, and using thermoplastic striping for final markings.
The associated federal contract opportunity is a small business set-aside construction contract with a project value between $500,000 and $1,000,000, categorized under NAICS code 237310 for highway, street, and bridge construction. Critical dates include badge requests due by 25 July 2025, a site visit on 31 July 2025, questions due by 5 August 2025, and bid submission due by 21 August 2025. The contract will have a 90-calendar day performance period after notice to proceed, and the government notes that funds are contingent on appropriation availability.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
08/05/25
QUESTION AND ANSWER FORM #1
Project Number: SXHT 16-1037
Project Description: Repair Streets and Parking Various, PSFB
RFP Section:
Paragraph:
Specs/Drawings Paragraph/Page: SXHT 16-103 MAINTAIN STREETS AND PARKING, VAR, PSFB Revised Plans Sheet CP-103
Other (specify):
1. Question: Are we re-working the existing subbase and limerock base or removing and bringing in new?
Answer: Per “PAVEMENT MILL – OVERLAY SECTION 1,” Drawing CP-103, replace existing asphalt and limestone base with 3.0” of asphalt paving in 2 courses and 9” of limestone base.
Specs/Drawings Paragraph/Page: SXHT 16-103 MAINTAIN STREETS AND PARKING, VAR, PSFB Revised Plans Sheet CP-101
Other (specify):
2. Question: Are we removing and re-installing existing parking stops or installing new ones?
Answer: REMOVE, STORE, PROTECT, & REINSTALL PARKING STOPS.
Specs/Drawings Paragraph/Page: SXHT 16-103 MAINTAIN STREETS AND PARKING, VAR, PSFB Revised Plans Sheet CP-103
Other (specify):
3. Question: Are we responsible for providing our own proctor density testing for the stabilized subbase and limerock base?
Answer: Vendors that sell road construction products typically provide test results for the products they sell. The tests and road construction products must meet FDOT standards.
In place density tests are required per FDOT standards.
4. Question: What is the existing asphalt and base thickness on Challenger Ave.?
Answer: Assume 4” thickness of asphalt paving.
5. Question: What location can the contractor use for a laydown/staging area?
Answer: The Contractor may request a laydown area as part of the Submittal process. A laydown area near the Challenger Street site will be designated through the laydown area request process.
6. Question: In order to provide smooth transitions for all hatched areas, do the hatched areas need to be milled 1.5" and overlayed with the 2nd course 1.5" Type
SP-9.5?
Answer: Mill the joint area before and/or after paving operations to produce a relatively smooth transition. Feathering of the top asphalt overlay course may be necessary to create a relatively smooth transition.
7. Question: Is the final striping to be paint of thermo.?
Answer: Per Specification Section 32 17 23 use thermoplastic striping for the final striping.
Temporary striping can be painted.
8. Question: When is the anticipated NTP?
Answer: Typically, the preconstruction meeting is held within three weeks of contract award and Notice-To-Proceed is issued within a few days of the preconstruction meeting.
9. Question: Can FDOT crushed concrete base be used in lieu of limerock base?
Answer: Crushed concrete that meets FDOT specifications for Recycled Concrete Aggregate (RCA) base material. The crushed concrete must meet minimum LBR value, gradation, plasticity FDOT requirements for limerock base.
10. Question: Please confirm that an alternate spreadsheet can be used that clearly shows where all costs were derived including labor and equipment rates, subcontract pricing and material costs. Or would a unit priced bid form showing activity descriptions be preferrable?
Answer: Yes, alternate spreadsheets may be used. Per section L-5(4e) of the SF1442, a CECC Form 3052 or Similar Computer-generated form is acceptable to include the breakdown of disciplines and cost elements and the total price of the entire project.
1557397783A Underline