A8 SXHT 16-1037_Liquidated Damages 2025.pdf

PDF 142 KB Posted

Attached to
SXHT 16-1037 Repair Streets & Parking Various PSFB Federal contract opportunity
Solicitation number
FA252125B0010
Issued by
Department of the Air Force Space Command

About this file

This document is a 2025 Liquidated Damages Determination for a federal construction contract (Project Number SXHT 16-1037) involving street and parking repairs at Patrick Air Force Base. The document calculates potential damages for contractor delays, breaking down costs across legal, civil engineering, and contracting categories. The first day of delays would incur $471.76 in damages, with subsequent days costing $383.19, based on hourly rates from the US Office of Personnel Management 2025 Salary table plus a 30% labor burden. Rates include personnel costs for roles such as Staff Judge Advocate, Inspector, Engineering Management, Contracting Officer, and Administrator, along with vehicle mileage reimbursement at $0.70 per mile. The document notes that additional damages for lost income or incurred fees may be assessed on an individual basis and approved by the Contracting Officer.

View the file

Other files for this federal contract opportunity

Other files attached to SXHT 16-1037 Repair Streets & Parking Various PSFB, newest first.
File Type Posted
FA252125B0010_Abstract of Offers.pdf PDF
Solicitation Amendment FA252125B00100003 SF 30.pdf PDF
Solicitation Amendment - FA252125B00100003.pdf PDF
A1 SXHT 16-1037 Rpr Strts and Prkng SPECS FNL REV 080725.pdf PDF
Solicitation Amendment - FA252125B00100002.pdf PDF
Solicitation Amendment FA252125B00100002 SF 30.pdf PDF
SXHT 161037 Qustns and Answrs 1 080625 REV.pdf PDF
Solicitation Amendment FA252125B00100001 SF 30.pdf PDF
SXHT 161037 Qustns and Answrs 1 080625.pdf PDF
Solicitation Amendment - FA252125B00100001.pdf PDF
Site Visit Sign in Sheet.pdf PDF
A12 Badge Request 45 SFS Form V14.pdf PDF
A9 Energy Management and Control Systems Standards.pdf PDF
A11 Small Business Self Performance Worksheet.pdf PDF
Solicitation - FA252125B0010.pdf PDF
A4 SXHT 16-1037 Rpr Str and Prk Var PAFB SOW 053025_Redacted.pdf PDF
A10 QUESTION AND ANSWER FORM.docx DOCX document
A14 SXHT 16-1037 CECC Form 3052.xlsx XLSX spreadsheet
A1 SXHT 16-1037 Rpr Strts and Prkng SPECS.pdf PDF
A5 SXHT 16-1037 GPP Certification.pdf PDF
A6 SXHT 16-1037 Haz Waste.pdf PDF
A7 SXHT 16-1037 ODS.pdf PDF
A12 Badge Request 45 SFS Form V14.pdf PDF
A2 SXHT 16-1037-G-001 071525 REV Drwngs.pdf PDF
A3 SXHT 16-1037- Submittal Register 062525.xlsx XLSX spreadsheet
A13 DBA Wage Determination_4Jul2025.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2025 LIQUIDATED DAMAGES DETERMINATION

PROJECT NUMBER SXHT 16-1037

TITLE: Repair Streets & Parking, Various PAFB

FA2521-25-B-0010

a. LEGAL (Total):

Staff Judge Advocate 1 hour @ $88.57 $88.57 $88.57

(GS 14/5)

b. CIVIL ENGINEERING:

Inspector (GS 11/5) 2 hours @ $ 52.59 $ 105.17 Engineering/Management 1 hour @ $ 63.02 $ 63.02

(GS 12/5)

Vehicle –10 Miles/day 10 miles @ $ 0.70 $ 7.00 ($0.70 per mile)

TOTAL ENGINEERING COST $ 175.19

c. CONTRACTING:

Contracting Officer 1 hour @ $74.95 $74.95

(GS 13/5)

Administrator 2 hours @ $63.02 $126.05

(GS 12/5)

Vehicle – 10 Miles/day 10 miles @ $ 0.70 $ 7.00 ($0.70 per mile)

TOTAL CONTRACTING COST $208.00

d. ADDITIONAL DAMAGES:

Loss of Income $000.00 Loss of Use $000.00 Other $000.00

TOTAL ADDITIONAL DAMAGE COST $ 0.00

Total Liquidated Damages (1st day only) (a+b+c) $471.76

Total Liquidated Damages each day thereafter (b+c+d) $383.19

Note: The hourly rates above are based upon the US Office of Personnel Management 2025 Salary table plus 30% labor burden. Amounts are based upon the average grade of personnel holding these positions and the typical amount of time associated with the inspection and oversight per contract. Mileage rate determined by 2025 JTR rate as published by GSA on 01 Jan 2025. In addition to basic damages, additional damages may be assessed in cases of lost income or incurred fees due to contractor delays.

These additional damages will be identified by the customer for inclusion on an individual basis as applicable and annotated above as approved by the Contracting Officer.