A8 SXHT 16-1037_Liquidated Damages 2025.pdf
PDF 142 KB Posted
- Attached to
- SXHT 16-1037 Repair Streets & Parking Various PSFB Federal contract opportunity
- Solicitation number
- FA252125B0010
About this file
This document is a 2025 Liquidated Damages Determination for a federal construction contract (Project Number SXHT 16-1037) involving street and parking repairs at Patrick Air Force Base. The document calculates potential damages for contractor delays, breaking down costs across legal, civil engineering, and contracting categories. The first day of delays would incur $471.76 in damages, with subsequent days costing $383.19, based on hourly rates from the US Office of Personnel Management 2025 Salary table plus a 30% labor burden. Rates include personnel costs for roles such as Staff Judge Advocate, Inspector, Engineering Management, Contracting Officer, and Administrator, along with vehicle mileage reimbursement at $0.70 per mile. The document notes that additional damages for lost income or incurred fees may be assessed on an individual basis and approved by the Contracting Officer.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2025 LIQUIDATED DAMAGES DETERMINATION
PROJECT NUMBER SXHT 16-1037
TITLE: Repair Streets & Parking, Various PAFB
FA2521-25-B-0010
a. LEGAL (Total):
Staff Judge Advocate 1 hour @ $88.57 $88.57 $88.57
(GS 14/5)
b. CIVIL ENGINEERING:
Inspector (GS 11/5) 2 hours @ $ 52.59 $ 105.17 Engineering/Management 1 hour @ $ 63.02 $ 63.02
(GS 12/5)
Vehicle –10 Miles/day 10 miles @ $ 0.70 $ 7.00 ($0.70 per mile)
TOTAL ENGINEERING COST $ 175.19
c. CONTRACTING:
Contracting Officer 1 hour @ $74.95 $74.95
(GS 13/5)
Administrator 2 hours @ $63.02 $126.05
(GS 12/5)
Vehicle – 10 Miles/day 10 miles @ $ 0.70 $ 7.00 ($0.70 per mile)
TOTAL CONTRACTING COST $208.00
d. ADDITIONAL DAMAGES:
Loss of Income $000.00 Loss of Use $000.00 Other $000.00
TOTAL ADDITIONAL DAMAGE COST $ 0.00
Total Liquidated Damages (1st day only) (a+b+c) $471.76
Total Liquidated Damages each day thereafter (b+c+d) $383.19
Note: The hourly rates above are based upon the US Office of Personnel Management 2025 Salary table plus 30% labor burden. Amounts are based upon the average grade of personnel holding these positions and the typical amount of time associated with the inspection and oversight per contract. Mileage rate determined by 2025 JTR rate as published by GSA on 01 Jan 2025. In addition to basic damages, additional damages may be assessed in cases of lost income or incurred fees due to contractor delays.
These additional damages will be identified by the customer for inclusion on an individual basis as applicable and annotated above as approved by the Contracting Officer.
File details come from the government source that posted it. Updated .